Crosswall construction
Cross-wall construction is a form of construction in which load bearing walls provide the primary vertical support and lateral stability for precast floors. External wall panels, lift cores or staircases are used to provide the required longitudinal stability. Bridging components such as floors, roofs and beams are supported by the load bearing walls or façade wall.
If both walls and floors are of cast in situ reinforced concrete, the series of ‘boxes’ so formed is sometimes referred to as ‘box frame construction’.
The system is ideal for buildings with cellular and orthogonal grids, with rooms of up to 4 x 9 m. It is suitable for buildings up to a height of five storeys where the floors are similar and where internal separating or party walls are required, such as in blocks of flats and student accommodation.
It creates a structurally efficient building with high levels of acoustic and fire separation between adjacent rooms. This is due to the high mass of the structure and good airtightness. Cross wall construction also has good thermal mass.
Cross-wall systems can offer significant time and cost savings in comparison to traditional building techniques as the components can often be prefabricated. In addition, the arrangement of windows between crosswalls is unrestricted.
The precast elements are typically brought to site 'just in time'. Hidden joints and ties, both horizontally and vertically are grouted in place as the work develops. Other works such as installation of mechanical and electrical services and finishes that are required can start prior to the completion of the entire structure.
Cross-wall construction involves a number of key connections:
- Wall-to-wall at vertical joints.
- Wall-to-wall at horizontal joints.
- Wall-to-base/foundation.
Care must be taken in both design and construction to ensure that the junctions between the non-load bearing claddings and the crosswalls are weather resistant.
If a pitched roof is to be included with the ridge parallel to the lateral axis, there will need to be an edge beam to provide a seating for the rafters and to transmit roof loads to the crosswalls.
[edit] Related articles on Designing Buildings Wiki
- Cavity wall.
- Cladding.
- Concrete frame.
- Diaphragm wall.
- Modular buildings.
- Offsite manufacturing.
- Off-site prefabrication of buildings: A guide to connection choices.
- Party wall.
- Precast flat panel system.
- Prefabricated structural panels.
- Prefabrication.
- Preventing wall collapse.
- Wall types.
[edit] External resources
- ‘Building Construction Handbook’ (6th ed.), CHUDLEY, R., GREENO, R., Butterworth-Heinemann (2006)
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
38% of Gen Zs feel safe when a fire door is wedged open.
Stunning images from around the world
Shortlist for CIOB’s Art of Building photography competition.
Guidance for conversion of traditional pre-1919 stone buildings.
Industrial heritage in the Ruhr
A marked difference to the fate of industrial landscapes in the UK.
Communities will be able to build their own clean energy.
Why diversity and inclusion matters for SMEs
CIOB’s D&I Charter shows how practical changes can support long-term growth.
Cut electricity bills to power growth
Coalition sends joint letter to the Chancellor.
Gasholders: a history in pictures. Book review.
Recognition, influence and growth
SocEnv identifies three strategic pillars in new strategy to 2045.
Discover the future of roofing, cladding and insulation.
New guidance for professional practice, cultural change and regulation in social housing.
The heritage of nuclear and conventional power stations.


















Comments
Hi my house is of this design, I want to remove a timber and plasterboard partitionwall in my kitchen and make it bigger but am worried if it’s load bearing as it is pretty much the only interior wall downstairs of the house? Any help appreciated thanks in advance.
nick
If you're not certain, you should get a structural engineer to check it out for you. It should be relatively quick and straight forward job for them.