Sub-contractor
Contents |
[edit] Introduction
As buildings become increasingly complicated, so it becomes less and less likely that any one contractor will have the required skills to carry out all of the works necessary to construct them, and it may not make good commercial sense to take on new employees for one project that would then have to be laid off for the next.
Increasingly therefore, contractors will use sub-contractors to carry out particular elements of the works. Sub-contractors (or subcontractors) are sometimes referred to as 'subbies', or increasingly, simply as 'suppliers'.
Elements of the works that might be awarded to sub-contractors might include; piling, roofing, cladding, civil engineering, steelwork, plumbing, electrical services, and so on.
[edit] Types of sub-contractor
There are three main types of sub-contractor:
[edit] Domestic sub-contractor
A sub-contractor selected and appointed by the main contractor.
[edit] Nominated sub-contractor
A sub-contractor selected by the client to carry out an element of the works. The client negotiates a price with the nominated sub-contractor and then instructs the main contractor to appoint them for those works.
The main contractor will include the sub-contractors price as a prime cost sum in the contract sum for the main contract, to which they add overheads, profit and attendance. Some forms of contract (such as Joint Contracts Tribunal (JCT) contracts) no longer include provision for the nomination of sub-contractors.
[edit] Named sub-contractor
A sub-contractor for a particular package selected from a list of acceptable sub-contractors provided by the client. Named sub-contractors are allowed for in the tender documents for the main contract in the form of a provisional sum for which the main contractor makes allowances for mark up, attendance and programme within it’s tender offer.
Once appointed, the main contractor seeks tenders for the package from the named sub-contractors, places a sub-contract with the successful tenderer, and the provisional sum is replaced with the tendered figure.
NB According to NRM1: Order of cost estimating and cost planning for capital building work, the term ‘subcontractor' means; ‘…a contractor who undertakes specific work within the building project; known as specialist, works, trade, work package, and labour only subcontractors.’
[edit] Use of sub-contractors
The use of sub-contractors enables the main contractor to undertake more complex projects whilst not unacceptably increasing their risk, however, concerns have been expressed about the prevalence of sub-contractors because of a perception that the main contractor has less control over the skills and training of sub-contractor employees and so there may be a negative impact on quality and health and safety on site.
Sub-contractors might be managed by the contractors' sub-agent or package manager.
Increasingly, sub-contractors will themselves sub-contract elements of their package of works to other suppliers. This has resulted in the development of complex supply chains, with different tiers of suppliers, some of whom may be entirely unknown to the client. For more information see: Suppliers.
'Attendance' is the main contractor’s mark up for specific services it has to provide for individual sub-contractors. This might include items such as material handling, scaffolding and rubbish clearance. Attendance can be 'general attendance' describing items available site wide to all subcontractors, or 'special attendance' where items are specific to a particular contractor/subcontractor.
NB: On management contracts the works will be carried out by 'works contractors' and on construction management contracts the works will be carried out by 'trade contractors', although technically trade contractors are not sub-contractors as they are contracted by the client, and only managed by the construction manager.
[edit] Related articles on Designing Buildings
- CIS contractors and CIS sub-contractors.
- Construction Industry Scheme or IR35?
- Contractor vs supplier.
- Domestic sub-contractor.
- Fragmentation of the UK construction industry.
- Main contractor.
- Named specialist work.
- Named sub-contractor.
- Negotiated contract.
- Nominated sub-contractor.
- Nominated subcontractor v named subcontractor.
- Procurement route.
- Reasonable objection.
- Selected subcontractor.
- Specialist contractors.
- Specialist subcontractor.
- Status determination statement SDS.
- Suppliers.
- Supply chain.
- Top seven trends that will dominate the future of the construction industry
- Trade contractor.
- TUPE considerations and bidding.
- Types of contractor.
- Works contractor.
[edit] External references
Featured articles and news
Do you take the lead in a circular construction economy?
Help us develop and expand this wiki as a resource for academia and industry alike.
Warm Homes Plan Workforce Taskforce
Risks of undermining UK’s energy transition due to lack of electrotechnical industry representation, says ECA.
Cost Optimal Domestic Electrification CODE
Modelling retrofits only on costs that directly impact the consumer: upfront cost of equipment, energy costs and maintenance costs.
The Warm Homes Plan details released
What's new and what is not, with industry reactions.
Could AI and VR cause an increase the value of heritage?
The Orange book: 2026 Amendment 4 to BS 7671:2018
ECA welcomes IET and BSI content sign off.
How neural technologies could transform the design future
Enhancing legacy parametric engines, offering novel ways to explore solutions and generate geometry.
Key AI related terms to be aware of
With explanations from the UK government and other bodies.
From QS to further education teacher
Applying real world skills with the next generation.
A guide on how children can use LEGO to mirror real engineering processes.
Data infrastructure for next-generation materials science
Research Data Express to automate data processing and create AI-ready datasets for materials research.
Wired for the Future with ECA; powering skills and progress
ECA South Wales Business Day 2025, a day to remember.
AI for the conservation professional
A level of sophistication previously reserved for science fiction.
Biomass harvested in cycles of less than ten years.
An interview with the new CIAT President
Usman Yaqub BSc (Hons) PCIAT MFPWS.
Cost benefit model report of building safety regime in Wales
Proposed policy option costs for design and construction stage of the new building safety regime in Wales.
Do you receive our free biweekly newsletter?
If not you can sign up to receive it in your mailbox here.
























Comments
To start a discussion about this article, click 'Add a comment' above and add your thoughts to this discussion page.