Party walls, rights of light and permitted development rights
![]() |
Contents |
[edit] Introduction
Many landlords are putting in place plans to add additional storeys to properties in town centre locations following changes to Permitted Development Rights. This replaces the need for landlords to apply for planning consent to build upwards.
However, these new planning rights do not provide complete freedom and landlords tempted by the financial rewards of increased lettable space are advised to familiarise themselves with other relevant legislation.
[edit] Party walls and PDR
Would-be developers should be aware that although planning consent may no longer be required, party wall legislation remains in place.
Any upwards extension has the potential to impact on the structure and fabric of a neighbouring property and therefore, a building owner must serve notice to affected neighbours under the Party Wall etc. Act 1996. The Act requires two months’ notice to enable the neighbouring owners (freehold and/or leasehold) to either agree or dissent to the works. At this point an appointed party wall surveyor must undertake a schedule of condition of the neighbouring properties to provide effective dispute resolution.
Importantly, landlords should clarify the technical aspects of an extension. For example, if the building works result in alterations to a leaseholder’s ceiling (such as to embed a steel structure) their rights will be affected. If the extension is built onto a parapet, party wall rights may not be an issue but other issues – such as rights to light, the impact on services and any disruption caused during construction – may require consideration.
Many residents of top floor flats assume that they have rights over roofs. But while they may have access, they do not necessarily have protected rights. Skylights may be similarly affected.
For more information see: Party Wall Act.
[edit] Rights of light and PDR
In the absence of a planning process to scrutinise projects that will add to building heights, the issue of rights of light becomes a very serious consideration, and one with significant consequences.
Because daylight and sunlight assessments are a component of a planning application, they are currently required at an early stage in the process. The planning system also necessitates that local residents are consulted on a planning application, allowing those with legitimate concerns to assert their point of view. With this step removed, developers could potentially proceed unaware of any objections – resulting in building works then being halted through an injunction either during the process or post-completion.
For more information see: Rights to light.
So while developers might look set to gain from the opportunity to create additional storeys, in reality the situation is precarious. Without the stringent procedures and ultimately the reassurance that the planning system offers, developers could potentially embark on building works and only on completion suffer significant consequences.
There are many examples of developers of extensions being ordered to reverse changes, not because of planning issues, but because of the sometimes more opaque requirement of party wall and rights of light legislation.
An inevitable consequence of the extension of Permitted Development Rights will be an increase in the number of both investigations and claims. Developers are advised to seek professional advice at an early stage to avoid the significant expense of having to pull down an extension and begin again.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
RTPI leader to become new CIOB Chief Executive Officer
Dr Victoria Hills MRTPI, FICE to take over after Caroline Gumble’s departure.
Social and affordable housing, a long term plan for delivery
The “Delivering a Decade of Renewal for Social and Affordable Housing” strategy sets out future path.
A change to adoptive architecture
Effects of global weather warming on architectural detailing, material choice and human interaction.
The proposed publicly owned and backed subsidiary of Homes England, to facilitate new homes.
How big is the problem and what can we do to mitigate the effects?
Overheating guidance and tools for building designers
A number of cool guides to help with the heat.
The UK's Modern Industrial Strategy: A 10 year plan
Previous consultation criticism, current key elements and general support with some persisting reservations.
Building Safety Regulator reforms
New roles, new staff and a new fast track service pave the way for a single construction regulator.
Architectural Technologist CPDs and Communications
CIAT CPD… and how you can do it!
Cooling centres and cool spaces
Managing extreme heat in cities by directing the public to places for heat stress relief and water sources.
Winter gardens: A brief history and warm variations
Extending the season with glass in different forms and terms.
Restoring Great Yarmouth's Winter Gardens
Transforming one of the least sustainable constructions imaginable.
Construction Skills Mission Board launch sector drive
Newly formed government and industry collaboration set strategy for recruiting an additional 100,000 construction workers a year.
New Architects Code comes into effect in September 2025
ARB Architects Code of Conduct and Practice available with ongoing consultation regarding guidance.
Welsh Skills Body (Medr) launches ambitious plan
The new skills body brings together funding and regulation of tertiary education and research for the devolved nation.
Paul Gandy FCIOB announced as next CIOB President
Former Tilbury Douglas CEO takes helm.
UK Infrastructure: A 10 Year Strategy. In brief with reactions
With the National Infrastructure and Service Transformation Authority (NISTA).