First fix
First fix (sometimes described as shell and first fix ) is a short-hand term used to describe the processes that are undertaken during construction works up to the point of applying internal surfaces – typically plaster. It is normally used in relation to the work of specific trades such as carpenters, plumbers and electricians.
Generally first fix will include constructing the structure, cladding, flooring, doorframes, stairs and so on and installing cables for electrical and ICT distribution, pipework for water and gas distribution and heating ventilating and air-conditioning (HVAC) distribution. First fix is not normally visible when looking at the finished building. Where possible first fix should be tested before second fix (for example, plumbing riser stacks).
Second fix takes place after the internal surfaces have been applied. It comprises those items that are visible in a finished area and are held back to avoid damage, or sadly sometimes theft. This may include fitting internal doors, skirting, architraves, handrails, fixtures and fittings, including connection of appliances (such as electrical equipment, sanitaryware, radiators, and so on) testing and commissioning. For more information see: Second fix.
Typically there will be a change of trades operating on the site, and a break in activity for some trades between first and second fix.
In hotels and residential work there is sometimes a third fix of fixtures and fittings of high value that require fitting or service connections such as chandeliers, white goods, picture-lit artwork and fabrics.
As first fix, second fix and third fix do not have accurate standard definitions, it is very important that contract documentation sets out precisely what work is to be carried out and by who, rather than relying on ambiguous short-hand terms.
NB BG 87/2024, Useful Information Guide, written by Chin Hang “Kay” Lam and published by BSRIA in 2024, defines first fix as: ‘Work done in a new building up to the point that plaster is applied to walls, typically including (but not limited to) pipework, cable runs and back boxes. This term is typically used in housebuilding but may also be used in other types of project. While there is no universal definition, it generally relates to work done by plumbers, electricians and other trades on their first visit to a house.’
[edit] Related articles on Designing Buildings
Featured articles and news
Building Control Independent Panel final report
A precis of a key report lead by Dame Hackitt with full recomendations and link to the government response.
Guide to ISO 19650 for Architecture Firms (2026)
A user gives their low down.
A UK training and membership provider for mould remediation professionals.
Building Safety recap April, 2026
A short and longer run-through of the month, with links to further information and sources.
CIAT May 2026 briefing.
Independent NSI and BAFE study exploring how organisations are changing the way they buy fire safety services.
From medieval scribes to modern word art.
ECA welcomes crackdown on late payment and push for clean energy, whilst CIOB seek fixed cladding removal timeframes.
Cyber Security in the Built Environment
Protecting projects, data, and digital assets: A CIOB Academy TIS.
Managing competence in the built environment
ITFG publishes new industry guide on how to meet the ICC principles.
The UK's campaign to reduce noise pollution: Mythbusting, articles and topic guides.
Setting Expectations on Competence Management
Industry Competence Committee.
New Scottish and Welsh governments
CIOB stresses importance of construction after new parliament elections.
The sad story of Derby Hippodrome
An historic building left to decay.
ECA, JIB and JTL back Fabian Society call to invest in skills for a stronger built environment workforce.





















Comments
To take part in a discussion, click 'Add a comment' above.
Generally first fix is not visible when looking at the finished article. Where possible first fix should be tested prior to second fix such as plumbing riser stacks. Second fix comprises those items that are visible in a finished area and are held back to avoid damage, perhaps paintwork or sadly sometimes theft. In hotels and residential work there is sometimes a third fix of fixtures and fittings of high value that require fitting or service connections such as chandeliers, white goods, picture lit artwork and fabrics.