First fix
First fix (sometimes described as shell and first fix ) is a short-hand term used to describe the processes that are undertaken during construction works up to the point of applying internal surfaces – typically plaster. It is normally used in relation to the work of specific trades such as carpenters, plumbers and electricians.
Generally first fix will include constructing the structure, cladding, flooring, doorframes, stairs and so on and installing cables for electrical and ICT distribution, pipework for water and gas distribution and heating ventilating and air-conditioning (HVAC) distribution. First fix is not normally visible when looking at the finished building. Where possible first fix should be tested before second fix (for example, plumbing riser stacks).
Second fix takes place after the internal surfaces have been applied. It comprises those items that are visible in a finished area and are held back to avoid damage, or sadly sometimes theft. This may include fitting internal doors, skirting, architraves, handrails, fixtures and fittings, including connection of appliances (such as electrical equipment, sanitaryware, radiators, and so on) testing and commissioning. For more information see: Second fix.
Typically there will be a change of trades operating on the site, and a break in activity for some trades between first and second fix.
In hotels and residential work there is sometimes a third fix of fixtures and fittings of high value that require fitting or service connections such as chandeliers, white goods, picture-lit artwork and fabrics.
As first fix, second fix and third fix do not have accurate standard definitions, it is very important that contract documentation sets out precisely what work is to be carried out and by who, rather than relying on ambiguous short-hand terms.
NB BG 87/2024, Useful Information Guide, written by Chin Hang “Kay” Lam and published by BSRIA in 2024, defines first fix as: ‘Work done in a new building up to the point that plaster is applied to walls, typically including (but not limited to) pipework, cable runs and back boxes. This term is typically used in housebuilding but may also be used in other types of project. While there is no universal definition, it generally relates to work done by plumbers, electricians and other trades on their first visit to a house.’
[edit] Related articles on Designing Buildings
Featured articles and news
What they are, how they work and why they are popular in many countries.
Plastic, recycling and its symbol
Student competition winning, M.C.Esher inspired Möbius strip design symbolising continuity within a finite entity.
Do you take the lead in a circular construction economy?
Help us develop and expand this wiki as a resource for academia and industry alike.
Warm Homes Plan Workforce Taskforce
Risks of undermining UK’s energy transition due to lack of electrotechnical industry representation, says ECA.
Cost Optimal Domestic Electrification CODE
Modelling retrofits only on costs that directly impact the consumer: upfront cost of equipment, energy costs and maintenance costs.
The Warm Homes Plan details released
What's new and what is not, with industry reactions.
Could AI and VR cause an increase the value of heritage?
The Orange book: 2026 Amendment 4 to BS 7671:2018
ECA welcomes IET and BSI content sign off.
How neural technologies could transform the design future
Enhancing legacy parametric engines, offering novel ways to explore solutions and generate geometry.
Key AI related terms to be aware of
With explanations from the UK government and other bodies.
From QS to further education teacher
Applying real world skills with the next generation.
A guide on how children can use LEGO to mirror real engineering processes.
Data infrastructure for next-generation materials science
Research Data Express to automate data processing and create AI-ready datasets for materials research.
Wired for the Future with ECA; powering skills and progress
ECA South Wales Business Day 2025, a day to remember.
AI for the conservation professional
A level of sophistication previously reserved for science fiction.
Biomass harvested in cycles of less than ten years.
An interview with the new CIAT President
Usman Yaqub BSc (Hons) PCIAT MFPWS.
Cost benefit model report of building safety regime in Wales
Proposed policy option costs for design and construction stage of the new building safety regime in Wales.
Do you receive our free biweekly newsletter?
If not you can sign up to receive it in your mailbox here.


























Comments
To take part in a discussion, click 'Add a comment' above.
Generally first fix is not visible when looking at the finished article. Where possible first fix should be tested prior to second fix such as plumbing riser stacks. Second fix comprises those items that are visible in a finished area and are held back to avoid damage, perhaps paintwork or sadly sometimes theft. In hotels and residential work there is sometimes a third fix of fixtures and fittings of high value that require fitting or service connections such as chandeliers, white goods, picture lit artwork and fabrics.