First fix
First fix (sometimes described as shell and first fix ) is a short-hand term used to describe the processes that are undertaken during construction works up to the point of applying internal surfaces – typically plaster. It is normally used in relation to the work of specific trades such as carpenters, plumbers and electricians.
Generally first fix will include constructing the structure, cladding, flooring, doorframes, stairs and so on and installing cables for electrical and ICT distribution, pipework for water and gas distribution and heating ventilating and air-conditioning (HVAC) distribution. First fix is not normally visible when looking at the finished building. Where possible first fix should be tested before second fix (for example, plumbing riser stacks).
Second fix takes place after the internal surfaces have been applied. It comprises those items that are visible in a finished area and are held back to avoid damage, or sadly sometimes theft. This may include fitting internal doors, skirting, architraves, handrails, fixtures and fittings, including connection of appliances (such as electrical equipment, sanitaryware, radiators, and so on) testing and commissioning. For more information see: Second fix.
Typically there will be a change of trades operating on the site, and a break in activity for some trades between first and second fix.
In hotels and residential work there is sometimes a third fix of fixtures and fittings of high value that require fitting or service connections such as chandeliers, white goods, picture-lit artwork and fabrics.
As first fix, second fix and third fix do not have accurate standard definitions, it is very important that contract documentation sets out precisely what work is to be carried out and by who, rather than relying on ambiguous short-hand terms.
NB BG 87/2024, Useful Information Guide, written by Chin Hang “Kay” Lam and published by BSRIA in 2024, defines first fix as: ‘Work done in a new building up to the point that plaster is applied to walls, typically including (but not limited to) pipework, cable runs and back boxes. This term is typically used in housebuilding but may also be used in other types of project. While there is no universal definition, it generally relates to work done by plumbers, electricians and other trades on their first visit to a house.’
[edit] Related articles on Designing Buildings
Featured articles and news
The Association of Consultant Architects recap
A reintroduction and recap of ACA President; Patrick Inglis' Autumn update.
The Home Energy Model and its wrappers
From SAP to HEM, EPC for MEES and FHS assessment wrappers.
Future Homes Standard Essentials launched
Future Homes Hub launches new campaign to help sector prepare for the implementation of new building standards.
Building Safety recap February, 2026
Our regular run-down of key building safety related events of the month.
Planning reform: draft NPPF and industry responses.
Last chance to comment on proposed changes to the NPPF.
A Regency palace of colour and sensation. Book review.
Delayed, derailed and devalued
How the UK’s planning crisis is undermining British manufacturing.
How much does it cost to build a house?
A brief run down of key considerations from a London based practice.
The need for a National construction careers campaign
Highlighted by CIOB to cut unemployment, reduce skills gap and deliver on housing and infrastructure ambitions.
AI-Driven automation; reducing time, enhancing compliance
Sustainability; not just compliance but rethinking design, material selection, and the supply chains to support them.
Climate Resilience and Adaptation In the Built Environment
New CIOB Technical Information Sheet by Colin Booth, Professor of Smart and Sustainable Infrastructure.
Turning Enquiries into Profitable Construction Projects
Founder of Develop Coaching and author of Building Your Future; Greg Wilkes shares his insights.
IHBC Signpost: Poetry from concrete
Scotland’s fascinating historic concrete and brutalist architecture with the Engine Shed.
Demonstrating that apprenticeships work for business, people and Scotland’s economy.
Scottish parents prioritise construction and apprenticeships
CIOB data released for Scottish Apprenticeship Week shows construction as top potential career path.
From a Green to a White Paper and the proposal of a General Safety Requirement for construction products.
Creativity, conservation and craft at Barley Studio. Book review.
The challenge as PFI agreements come to an end
How construction deals with inherited assets built under long-term contracts.
Skills plan for engineering and building services
Comprehensive industry report highlights persistent skills challenges across the sector.
Choosing the right design team for a D&B Contract
An architect explains the nature and needs of working within this common procurement route.
Statement from the Interim Chief Construction Advisor
Thouria Istephan; Architect and inquiry panel member outlines ongoing work, priorities and next steps.




























Comments
To take part in a discussion, click 'Add a comment' above.
Generally first fix is not visible when looking at the finished article. Where possible first fix should be tested prior to second fix such as plumbing riser stacks. Second fix comprises those items that are visible in a finished area and are held back to avoid damage, perhaps paintwork or sadly sometimes theft. In hotels and residential work there is sometimes a third fix of fixtures and fittings of high value that require fitting or service connections such as chandeliers, white goods, picture lit artwork and fabrics.