Demand for Off-Site Construction Continues to Increase in the UK’s Manufacturing Sector
Contents |
[edit] Introduction
The Portakabin Group is seeing a significant rise in demand for buildings in the manufacturing sector as more organisations look to expand their facilities using off-site construction. Here Steve Newell, General Manager at Portakabin, looks at their latest industrial project and the drivers which moved construction off site.
Whether the requirement is for offices, support facilities, process areas, control centres or laboratories, off-site construction and its standardised designs for modular buildings can provide significantly shorter construction periods, allowing manufacturers to make investment decisions at a later stage and achieve faster project implementation and return on capital spend.
A scheme for Totally Wicked has been constructed using Yorkon off-site solutions from the Portakabin Group to create the first purpose-designed fluid production and technical facility for e-cigarettes to be built in the UK. The project has increased the company’s capacity to over 10 million bottles of premium quality e-liquid every year for the UK, USA and worldwide markets.
The facility was constructed off site to radically shorten the programme time and reduce disruption to the local community and to the company’s operations on the Totally Wicked site in Blackburn.
Finished in anthracite grey with striking chilli red stripes to reflect Totally Wicked’s strong corporate image, the scheme accommodates a new production facility, complete with test room, fluid mixing area, bottling plant and a highly insulated cold room. Offices are located on the upper floor.
[edit] An Off-site Solution to Reduce the Build Time
The use of a Yorkon off-site solution reduced the build time for the facility to just four months to give Totally Wicked the benefit of earlier occupation. This also allowed production capacity to be increased and facilitated the company’s expansion at an earlier stage.
Portakabin was principal contractor for the project and managed design, foundations, building manufacture and installation, and landscaping.
The building has a high performance pre-installed concrete floor at ground floor level to provide a robust, lasting and clean finish for the production areas. The landscaping included tree planting and an external break-out space for staff.
[edit] Project Challenges
- This was a challenging, sloping site which required complex excavations and the construction of a 5m high gabion stone retaining wall to meet planning restrictions for the building height.
- The building has a cold room which had to meet stringent standards for the storage of nicotine solutions, including a high level of insulation.
- The site was very constrained and immediately adjacent to a main road requiring detailed logistical planning for the building installation phase.
- Ensuring as little disruption as possible to Totally Wicked’s operations and the surrounding residential community were key project requirements.
[edit] The Client’s Perspective
Stuart Mercer, Operations Director at Totally Wicked, said, “We needed this building to help us meet the growing demand for our products both in the UK and for export markets. It is a cutting edge facility for e-liquid production.”
“We chose an off-site solution because the brownfield site we wanted to develop is very constrained and it was critical to have as little interruption to our operations and to neighbouring properties as possible. The benefits of off-site construction far exceeded those of site-based construction – we could have much less plant and equipment on site, the programme was much shorter, and disruption was minimised.”
“Following completion we are now ideally placed to take the business to the next level, increasing production in a very clean, modern environment. The finished building fits in really well with our corporate image and we would definitely recommend the approach and the Portakabin Group to other businesses looking to expand their facilities.”
[edit] Related articles on Designing Buildings Wiki
- Design for deconstruction, BRE modular show house
- Design for Manufacture and Assembly (DfMA).
- Kit house.
- How to Develop the Most Constrained Hospital Sites to Reduce Waiting Times and Improve Patient Care
- Modular buildings
- Modular buildings for education
- Modular construction
- Modular Solutions to Place Planning Issues
- Modular vs traditional construction
- Off-site prefabrication of buildings: A guide to connection choices.
- Recycling Modular Buildings – Taking Sustainable Construction to New Heights
- Structure relocation.
- The myths of modular construction
- WikiHouse.
- Y:Cube.
Featured articles and news
Key takeaways from the BSRIA Briefing 2024
Not just waiting for Net Zero, but driving it.
The ISO answer to what is a digital twin
Talking about digital twins in a more consistent manner.
Top tips and risks to look out for.
New Code of Practice for fire and escape door hardware
Published by GAI and DHF.
Retrofit of Buildings, a CIOB Technical Publication
Pertinent technical issues, retrofit measures and the roles involved.
New alliance will tackle skills shortage in greater Manchester
The pioneering Electrotechnical Training and Careers Alliance.
Drone data at the edge: three steps to better AI insights
Offering greater accuracy and quicker access to insights.
From fit-out to higher-risk buildings.
Heritage conservation in Calgary
The triple bottom line.
College of West Anglia apprentice wins SkillELECTRIC gold.
Scottish government launch delivery plan
To strengthen planning and tackle the housing emergency.
How people react in ways which tend to restore their comfort.
Comfort is a crucial missing piece of the puzzle.
ECA launches Recharging Electrical Skills Charter in Wales
Best solutions for the industry and electrical skills in Wales.
New homebuilding skills hub launch and industry response
Working with CITB and NHBC to launch fast track training.