Contractor's Site Layout Planning
[edit] Introduction
A site layout plan can help the contractor to safely and efficiently carry out the site operations as stipulated in the contract during the whole period of working.
[edit] Components
Depending on the site constraints the contractor’s site layout plan might include:
[edit] Hoarding
Construction of a site fence is primarily for the control of the site, safety and it acts as a demarcation of the boundaries of the site. Hoarding can be erected from timber or steel framing finished with the sheeting of either corrugated iron sheets, flat sheets plywood and so on.
Hoarding must be made in such a way as to allow for privacy for the workers inside, protecting the site facilities from the theft and allow for proofing from extreme weather such as wind.
[edit] Entrance gates
Entrance gates are placed where vehicles bringing materials and plant to the site can easily turn around without difficulties or disturbance to public traffic. Entrance gates are commonly made of sliding steel gates or grilled gates depending on the space available and the budget allocated.
[edit] Watch towers
Watch towers enable security guards to look from elevated heights over large distances hence increasing the degree of security at the site. Watch towers are allocated at the corners along the site fence, constructed as steel or timber framed temporary structures.
[edit] Parking
Parking is essential for vehicles coming to the site bringing materials and other goods waiting to be unloaded. Parking is also required for light vehicles that support site works and should be reserved and allocated properly.
Parking should be located to allow for easy access.
[edit] Site offices
Site offices are sometimes located close to the precious goods storage facilities and the entrance gates in an area that can allow for easy view of the progressing site works.
Site offices can be a single room comprising tables and chairs for all staff, or offices including different rooms Eg. Site engineer’s office, clerk of works office and store keeper office.
[edit] Tower cranes
Tower cranes should be located adjacent to buildings being constructed. Critical analysis should be undertaken regarding the exact area that tower cranes should be erected.
[edit] Sand piling
Sand piles are placed close to mixing plant. Sand might be piled on a single spread or there might be several piles in an area.
[edit] Aggregate
Aggregate piles should also be placed close to the mixing area, but care should be taken that no oil leakages would be allowed to flow towards the piling area. Piling should allow for constant and uniform moisture content of the aggregates that will not affect the mixing process in concrete production.
[edit] Mixing area
Depending on the mixing method whether it is hand mixing or machinery mixing the choice for locating a mixing area should consider that it is adjacent to the cement storage area, sand and aggregate piling area. Also the area should be such that concrete dumpers are able to turn and load the concrete.
[edit] Canteen
An area where site workers can sit and eat their food during tea, lunch or supper breaks; the canteen should be located away from working areas that produces noise, smoke or where there is a risk of objects falling. They should be close to the site offices and not far away from the toilets.
[edit] Precious goods storage
Storage facility for precious goods might include ironmongery, plumbing fixtures such as wash basins, faucets, floor traps; lighting fixtures, HVAC components, ICT fixtures and any other good of high value. They should be stored in a locked area with strict access and security. Such a facility should be placed close to the offices and adjacent to a guard post.
[edit] Reinforcement storage
A facility for storing reinforcement should be covered to protect the bars from the action of rain and bad weather that may cause rust and early aging. The facility should be located adjacent to the steel works workshop to enable easy and fast handling of the material to the workshop for cutting, bending and fixing.
[edit] Timber storage
The timber storage facility should be located close to the site carpentry workshop. Timber should be stacked properly to avoid damage, and stored in a covered facility to prevent the action of sun that can cause loss of moisture causing warping and bending.
[edit] Carpentry workshop
Site carpentry workshops should be placed adjacent to the timber storage facility. Carpentry workshops consist of all tools, machines and equipments essential for carry out carpentry works therefore it should be at a secured zone comprising of lockable shelves. It should be located in an area which would not cause too much noise to the other site working areas.
[edit] Toilets
Site toilets should be built close to working areas readily seen and easily accessed by all the site workers. It should be located where the desludging work can easily be done where the site is not connected to public sewer.
[edit] Emergency assembly
Emergency assembly areas allow for workers to gather quickly if emergency situations arise. It should be located in an open space easily accessed and well seen. It should be well marked, not surrounded with works operations and close to the entrance gate.
[edit] Meeting area
There should be an area where the site and technical meetings or any other managerial meetings can be conducted efficiently without disturbances. The facility should be well covered with chairs and a table accommodating a reasonable number of people for usual meetings.
[edit] Wet storage
A water reservoir and storage facilities should be located close to the mixing area and at the highest level of the site and in an area where the pipe connection to the water supply will be easily carried out. Care should be taken that the area will not allow for water to be contaminated with oils or with other impurities.
See also: Site layout plan.
[edit] Related articles on Designing Buildings Wiki
- Bay.
- Construction phase plan.
- Haul road.
- Laydown area.
- Lighting of construction sites.
- Main construction compound.
- Mobilisation to site: a quality perspective.
- Pre-construction information.
- Safety signs.
- Site area,
- Site facilities.
- Site layout plan.
- Site office.
- Site plan.
- Site storage.
- Temporary site services.
- Temporary works.
- Virtual construction model.
- Welfare facilities.
- Wheel washing system.
Featured articles and news
Future Homes Standard Essentials launched
Future Homes Hub launches new campaign to help the homebuilding sector prepare for the implementation of new building standards.
Building Safety recap February, 2026
Our regular run-down of key building safety related events of the month.
Planning reform: draft NPPF and industry responses.
Last chance to comment on proposed changes to the NPPF.
A Regency palace of colour and sensation. Book review.
Delayed, derailed and devalued
How the UK’s planning crisis is undermining British manufacturing.
How much does it cost to build a house?
A brief run down of key considerations from a London based practice.
The need for a National construction careers campaign
Highlighted by CIOB to cut unemployment, reduce skills gap and deliver on housing and infrastructure ambitions.
AI-Driven automation; reducing time, enhancing compliance
Sustainability; not just compliance but rethinking design, material selection, and the supply chains to support them.
Climate Resilience and Adaptation In the Built Environment
New CIOB Technical Information Sheet by Colin Booth, Professor of Smart and Sustainable Infrastructure.
Turning Enquiries into Profitable Construction Projects
Founder of Develop Coaching and author of Building Your Future; Greg Wilkes shares his insights.
IHBC Signpost: Poetry from concrete
Scotland’s fascinating historic concrete and brutalist architecture with the Engine Shed.
Demonstrating that apprenticeships work for business, people and Scotland’s economy.
Scottish parents prioritise construction and apprenticeships
CIOB data released for Scottish Apprenticeship Week shows construction as top potential career path.
From a Green to a White Paper and the proposal of a General Safety Requirement for construction products.
Creativity, conservation and craft at Barley Studio. Book review.
The challenge as PFI agreements come to an end
How construction deals with inherited assets built under long-term contracts.
Skills plan for engineering and building services
Comprehensive industry report highlights persistent skills challenges across the sector.
Choosing the right design team for a D&B Contract
An architect explains the nature and needs of working within this common procurement route.
Statement from the Interim Chief Construction Advisor
Thouria Istephan; Architect and inquiry panel member outlines ongoing work, priorities and next steps.
























