Prime contract
Contents |
[edit] Introduction
Prime contracting is a form of procurement in which the client enters into a relationship with a contractor who provides a single point of contact (prime contract) for a supply chain to deliver one or more projects.
This is one of the three procurement routes recommended by Government Construction Strategy for publicly-funded projects (where it is described as prime-type contracting), and came into favour in the late 1990s and 2000s following the recommendations of the Latham Report (Constructing the Team 1994) and particularly the Egan Report (Rethinking Construction 1998), which brought about a desire to reduce the number of suppliers that the government contracted directly. It was thought that simplifying the supply chain would result in better value for money.
[edit] Range of meanings
Beyond this very broad definition, prime contracting is an unhelpfully vague term that encompasses a wide range of contracting methods. On the one hand, it can be used to describe a form of design and build that includes an element of facilities management, whilst on the other, it can be used to describe a long-term relationship between a client and a contractor to deliver a range of new projects as well as maintain the new estate and sometimes maintaining the existing estate.
Still more unhelpfully, prime contracting can be used to describe a single point responsibility delivery contract where the contractor is reimbursed subcontractor costs (prime costs) and a fee for overheads and profit (i.e. a prime cost contract, cost plus contract or cost reimbursement contract). See Prime cost contract for more information.
Regional prime contracts (RPCs) are geographically-based prime contracts and are generally (although not exclusively) service contracts, such as maintenance contracts.
[edit] Ministry of Defence
According to Defence Estates, ‘…a Prime Contractor is one having single point responsibility for the management and delivery of a project using a system of incentivisation and collaboration working to integrate the activities of its supply chain members to achieve a project that is on time, within budget and is in accordance with the specified outputs and is fit for purpose'
(Ref. Prime contracting on the MOD estate now archived.)
The intention here is to allow long-term relationships to develop, so that effective collaborative working can evolve throughout a stable supply chain.
[edit] Government Construction Strategy
The Common Minimum Standards (referred to by the Government Construction Strategy) states that '...procurement routes should be limited to those which support integrated team working (PPP/PFI, Design & Build, the Prime-type Contracting approach and framework arrangements consistent with the Construction Strategy). Traditional, non-integrated procurement approaches should not be used unless it can be clearly shown that they offer best value for money – this means, in practice they will seldom be used..'.
… where a supply team is appointed with a single point lead who takes overall responsibility for the design and construction of the project and gives commitments on the operational costs of or takes responsibility for the operation and maintenance of the facility for a defined period' (ref. Common Minimum Standards P5).
This integration into the contract of operation and maintenance is intended to ensure better consideration of whole-life costs during design and construction.
[edit] CIOB
'A report exploring procurement in the construction industry', published by The Chartered Institute of Building in 2010 states: ‘Prime Contracting is an extension of the Design and Build system. The ‘prime contractor’ will be expected to have a well established supply chain, and will co-ordinate and project manage throughout the design and construction stages. The prime contractor is paid all actual costs, plus profits incurred in respect of measured work and design staff – the main risk lies in respect of staff and the supply chain, including subcontractors.'
[edit] Characteristics
Despite this confusion of definitions, different forms of prime contracting have certain common characteristics, benefits and difficulties.
[edit] Characteristics
Prime contracting is generally only appropriate for large clients (for example, the government, and in particular the Ministry of Defence).
Generally, prime contractors tend to be large construction companies with significant resources and access to the full supply chain, although in theory there is nothing to prevent a consultant or financing organisation from becoming a prime contractor.
Prime contracting requires early appointment of the contractor, before any designs have been prepared and so tender may be based on an output-based specification. Sub-contractors may be appointed by the contractor on long-term framework agreements.
[edit] Benefits
Prime contracting removes the need for client co-ordination of multiple supply chain contracts (such as separate design contracts, construction contracts, maintenance contracts and operational contracts for multiple projects), which could in itself require the appointment of external consultants.
Other benefits can include:
- Clear lines of communication and accountability.
- Improved supply chain management.
- Improved collaboration.
- Economies of scale.
- The ability to implement ongoing improvement programmes.
- The potential to build up long-term relationships throughout the supply chain.
- The potential for long-term partnering and incentivisation.
- The potential for continuous improvement.
- Better consideration of whole-life costs.
[edit] Criticisms
Prime contracts can be seen to exclude smaller companies and to stifle competition and innovation. They can become too ‘cosy’, simply adding another layer of overheads and profit, and there is even the danger of fraud. As a consequence, projects must be clearly defined at the outset, and carefully controlled throughout. Strategies might include:
- Open-book accounting.
- Clear measurable milestones.
- Clear, allocation of risks.
- Fraud detection and prevention.
- Ongoing performance measurement and continuous improvement.
[edit] Related articles on Designing Building Wiki
- Collaborative practices.
- Contract conditions.
- Construction contract.
- Prime cost contracts.
- Egan Report.
- Framework agreements.
- Government Construction Strategy.
- Integrated Project Team.
- Integrated Supply Team.
- Latham Report.
- OGC.
- Output-based specification.
- Partnering.
- Prime cost contract.
- Procurement route.
- Supply chain management.
[edit] External references
- Prime contracting on the MOD estate (now archived).
- MOD: Prime Contractor Handbook of Supply Chain Management (now archived).
- Government Construction Strategy.
Featured articles and news
Licensing construction in the UK
As the latest report and proposal to licence builders reaches Parliament.
Building Safety Alliance golden thread guidance
Extensive excel checklist of information with guidance document freely accessible.
Fair Payment Code and other payment initiatives
For fair and late payments, need to work together to add value.
Pre-planning delivery programmes and delay penalties
Proposed for housebuilders in government reform: Speeding Up Build Out.
High street health: converting a building for healthcare uses
The benefits of health centres acting as new anchor sites in the high street.
The Remarkable Pinwill Sisters: from ‘lady woodcarvers’ to professionals. Book review.
Skills gap and investment returns on apprenticeships
ECA welcomes new reports from JTL Training and The Electrotechnical Skills Partnership.
Committee report criticises UK retrofit schemes
CIOB responds to UK’s Energy Security and Net Zero Committee report.
Design and construction industry podcasts
Professional development, practice, the pandemic, platforms and podcasts. Have we missed anything?
C20 Society; Buildings at Risk List 2025
10 more buildings published with updates on the past decade of buildings featured.
Boiler Upgrade Scheme and certifications consultation
Summary of government consultation, closing 11 June 2025.
Deputy editor of AT, Tim Fraser, discusses the newly formed society with its current chair, Chris Halligan MCIAT.
Barratt Lo-E passivhaus standard homes planned enmasse
With an initial 728 Lo-E homes across two sites and many more planned for the future.
Government urged to uphold Warm Homes commitment
ECA and industry bodies write to Government concerning its 13.2 billion Warm Homes manifesto commitment.
From project managers to rising stars, sustainability pioneers and more.
Places of Worship in Britain and Ireland, 1929-1990. Book review.
The emancipation of women in art.