Dredging
Contents |
[edit] Introduction
Dredging is the process of excavating and removing sediments and debris from below water level, typically from the bottom of lakes, rivers, harbours, and so on. Dredging is generally necessary because of sedimentation which is the process in which sand and silt washes downstream and accumulates over time in channels and harbours.
Dredging may be carried out for a number of reasons:
- To increase the depth of the bed to allow boats and ships to pass through.
- To obtain aggregates for manufacturing concrete.
- To obtain other materials for use in civil engineering projects.
- To excavate trenches for laying pipelines, cables, and so on.
- To increase channel capacity, thereby helping with flood prevention.
- To prevent the spread of contaminated sediments to other areas of the water body.
- For land reclamation. This is the process of forming areas of land by depositing dredged materials and building them up. One of the most famous projects of this kind was the construction of the Kansai International Airport in Japan, which involved the building of an artificial island in the middle of Osaka Bay.
[edit] Considerations and planning
Before commencing dredging, it is important that site investigations and hydrological surveys are undertaken to assess the likely consequences of removing the material. Likely material movements and the seabed characteristics can be analysed from these surveys.
Some of the main factors which are considered during the planning stages include:
- Site location.
- Depth required.
- Type of material to be dredged.
- Where the dredged material will be deposited.
- If hard rock is likely to be dredged, underwater explosives may need to be used to break them up before being removed by bucket or grab.
[edit] Plant and equipment
The plant used for dredging can be broadly categorised as either suction or digging dredgers.
[edit] Suction dredgers
These are the most commonly used types of dredger. Variations include:
[edit] Trailer suction hopper dredger
This is a self-propelled hull capable of loading its own hold using a centrifugal pump which drags along the bed. It is typically used for dredging sand, silt and some clays. Winches or cranes are used to raise and lower the suction pipes, which have a maximum dredging depth of around 35 m. Hydraulically-operated doors in the hopper’s bottom discharge the material.
The advantage of this dredger is that it can operate in poor sea and weather conditions, and can transport soil over long distances.
[edit] Cutter suction dredger
This is moored using anchor legs and combines suction with a powerful cutting action. It uses a revolving cutting head and is capable of breaking up and removing firmer materials, such as hard clay and soft rock. The material is sucked up a pipe and discharged into barges for disposal. They can be used at maximum depths of around 40 m, and have the advantage of being able to produce a fairly uniform and level bed.
[edit] Digging dredgers
[edit] Bucket chain dredger
This is the common type of dredger, where a chain of buckets continuously scoop material out and raise it above water level before tipping it out onto chutes. (See top image.)
[edit] Bucket dredger
This is also known as a backhoe dredger as it follows the same principles as the land-based backhoe excavator. The advantage of this type of plant is that it can be used to dredge a wide range of materials, including obstacles such as boulders.
[edit] Dragline dredger
This is also modelled on the land-based dragline, and is limited to shallow inland waterways. A bucket is lowered onto the material to be excavated and dragged along its surface by a dragline. Dredged material it typically deposited on the banks of the waterway.
[edit] Floating grab dredger
This uses a grab crane which is mounted on the deck of an anchored or spud-rigged pontoon. The grab is usually a 'clamshell' so as to retain mud and silt. Material is loaded into hopper barges.
[edit] Related articles on Designing Buildings Wiki
- Aggregate.
- Amphibious excavators.
- Caisson.
- Channel.
- Civil engineer.
- Coastal defences.
- Dam construction.
- Desilting.
- Difference between cofferdams and caissons.
- Excavating plant.
- Excavation.
- Land reclamation.
- Pontoon bridge.
- Reservoir construction.
- River engineering.
- Sewer construction.
- Trenching equipment.
- Tunneling.
- Underwater foundations.
- Watercourse.
- Water engineering.
[edit] External resources
- ‘Introduction to Civil Engineering Construction’ (3rd ed.), HOLMES, R., College of Estate Management (1994)
Featured articles and news
The UK's Modern Industrial Strategy: A 10 year plan
Previous consultation criticism, current key elements and general support with some persisting reservations.
Building Safety Regulator reforms
New roles, new staff and a new fast track service pave the way for a single construction regulator.
Architectural Technologist CPDs and Communications
CIAT CPD… and how you can do it!
Cooling centres and cool spaces
Managing extreme heat in cities by directing the public to places for heat stress relief and water sources.
Winter gardens: A brief history and warm variations
Extending the season with glass in different forms and terms.
Restoring Great Yarmouth's Winter Gardens
Transforming one of the least sustainable constructions imaginable.
Construction Skills Mission Board launch sector drive
Newly formed government and industry collaboration set strategy for recruiting an additional 100,000 construction workers a year.
New Architects Code comes into effect in September 2025
ARB Architects Code of Conduct and Practice available with ongoing consultation regarding guidance.
Welsh Skills Body (Medr) launches ambitious plan
The new skills body brings together funding and regulation of tertiary education and research for the devolved nation.
Paul Gandy FCIOB announced as next CIOB President
Former Tilbury Douglas CEO takes helm.
UK Infrastructure: A 10 Year Strategy. In brief with reactions
With the National Infrastructure and Service Transformation Authority (NISTA).
Ebenezer Howard: inventor of the garden city. Book review.
The Grenfell Tower fire, eight years on
A time to pause and reflect as Dubai tower block fire reported just before anniversary.
Airtightness Topic Guide BSRIA TG 27/2025
Explaining the basics of airtightness, what it is, why it's important, when it's required and how it's carried out.
Construction contract awards hit lowest point of 2025
Plummeting for second consecutive month, intensifying concerns for housing and infrastructure goals.
Understanding Mental Health in the Built Environment 2025
Examining the state of mental health in construction, shedding light on levels of stress, anxiety and depression.