What hours are construction sites allowed to operate?
[edit] Introduction
Construction sites can be disruptive to the local community for long periods of time. Nuisance that can be caused be construction activities might include:
- Noise.
- Dust.
- Dirt and spillages.
- Damage to highways.
- Traffic congestion.
- Parking issues.
- Disruption to pedestrians.
- Waste accumulation.
- Vibration.
- Odours or smoke.
- Artificial lighting.
However, construction is a necessary activity and in the case of Andreae v. Selfridge & Co. Limited (1958) Sir Wilfred Green MR suggested that ‘...if they are reasonably carried on and all proper and reasonable steps are taken to ensure that no undue inconvenience is caused to neighbours, whether from noise, dust, or other reasons, the neighbours must put up with it.’
Such reasonable steps might include working at reasonable times and restricting disruptive activities to particular periods.
Generally, the hours during which construction sites are allowed to operate is determined by the local authority, in accordance with the Control of Pollution Act, and conditions can be applied to planning permissions in accordance with the Town and Country Planning Act.
In addition, there may be a requirement to comply with BS 5228 Code of Practice for Noise and Vibration Control on Construction and Open Sites, and the Control of Noise at Work Regulations limit the exposure of workers to noise (this is enforced by the Health and Safety Executive).
Typical restrictions might be:
- Monday to Friday: 8am to 6pm.
- Saturdays: 8am to 1pm.
- Sundays and bank holidays: No work permitted, or noisy work prohibited.
Examples of activities that might be prohibited outside of these hours could include:
- The use of hammers and saws.
- The use of drills and sanders.
- Pile driving.
- Erecting and dismantling of scaffolding.
Noise-related work taking place outside these hours will generally only be permitted if the contractor can make a case that it is necessary on the grounds of health and safety.
Different hours may apply, for example in business areas where noise or vibration during normal working hours would be disruptive.
The local authority may also set limits to the amount of noise or vibration that a construction site is permitted to generate and monitoring may be undertaken to ensure that these are not exceeded.
These restrictions do not always apply to civil engineering projects such as rail or highway works.
Steps that a contractor might take to reduce disruption might include:
- Keeping neighbours informed.
- Monitoring noise, vibration and dust.
- Providing a help line so that problems can be reported.
- Restricting disruptive activities to particular periods.
- Storing fine materials under cover.
- Damping fine materials and roadways.
- Minimising demolition or crushing dust.
- Washing down vehicles.
- Taking care when deciding transport routes.
- Providing hard-surfaced roadways.
- Implementing a waste management strategy.
- Avoiding burning waste materials.
- Limiting vibration.
- Using well-maintained, quiet machinery.
- Carefully selecting and managing sub-contractors.
- Using low disruption methods of work.
- Properly instructing and supervising staff.
- Providing acoustic screening.
- Very occasionally, offering temporary re-housing for residents.
Some construction sites, companies and suppliers may register with the Considerate Constructors Scheme and then must abide by its Code of Considerate Practice.
Some sites may also have to comply with a code of construction practice imposed by the local authority or by the client.
NB, NRM3: Order of cost estimating and cost planning for building maintenance works, suggests that normal working hours are typically 8.30 to 5.30 Monday to Friday (excluding statutory holidays), but also makes clear that working hours vary.
[edit]
In May 2020, a ‘Safe Working Charter’ was launched by the Government and the Home Builders Federation, enabling builders to return to work safely during the Coronavirus pandemic. This allowed builders to agree more flexible construction working hours with their local council, such as staggering arrival times. Ref https://www.gov.uk/government/news/housing-secretary-sets-out-plan-to-re-start-housing-market
In June 2020 the Business and Planning Bill was introduced, allowing local authorities to rule on extended working hours applications, and generally permitting site working until 9pm, Monday to Saturday, and 24 hour working in some circumstances in non-residential areas. https://www.gov.uk/government/collections/draft-planning-guidance-to-support-the-business-and-planning-bill
[edit] Related articles on Designing Buildings
- Code of construction practice.
- Complaining about construction sites.
- Considerate Constructors Scheme.
- Contractor's working schedule.
- Control of noise at work regulations 2005.
- Environmental health.
- Environmental impact assessment.
- Local authority.
- Noise at Work Assessment.
- Noise nuisance.
- Nuisance.
- Out of hours working.
- Permitted development.
- Planning condition.
- Quiet period.
- Working day.
Featured articles and news
Construction Skills Mission Board launch sector drive
Newly formed government and industry collaboration set strategy for recruiting an additional 100,000 construction workers a year.
New Architects Code comes into effect in September 2025
ARB Architects Code of Conduct and Practice available with ongoing consultation regarding guidance.
Welsh Skills Body (Medr) launches ambitious plan
The new skills body brings together funding and regulation of tertiary education and research for the devolved nation.
Paul Gandy FCIOB announced as next CIOB President
Former Tilbury Douglas CEO takes helm.
UK Infrastructure: A 10 Year Strategy. In brief with reactions
With the National Infrastructure and Service Transformation Authority (NISTA).
Ebenezer Howard: inventor of the garden city. Book review.
The Grenfell Tower fire, eight years on
A time to pause and reflect as Dubai tower block fire reported just before anniversary.
Airtightness Topic Guide BSRIA TG 27/2025
Explaining the basics of airtightness, what it is, why it's important, when it's required and how it's carried out.
Construction contract awards hit lowest point of 2025
Plummeting for second consecutive month, intensifying concerns for housing and infrastructure goals.
Understanding Mental Health in the Built Environment 2025
Examining the state of mental health in construction, shedding light on levels of stress, anxiety and depression.
The benefits of engaging with insulation manufacturers
When considering ground floor constructions.
Lighting Industry endorses Blueprint for Electrification
The Lighting Industry Association fully supports the ECA Blueprint as a timely, urgent call to action.
BSRIA Sentinel Clerk of Works Training Case Study
Strengthening expertise to enhance service delivery with integrated cutting-edge industry knowledge.
Impact report from the Supply Chain Sustainability School
Free sustainability skills, training and support delivered to thousands of UK companies to help cut carbon.
The Building Safety Forum at the Installershow 2025
With speakers confirmed for 24 June as part of Building Safety Week.
The UK’s largest air pollution campaign.
Future Homes Standard, now includes solar, but what else?
Will the new standard, due to in the Autumn, go far enough in terms of performance ?
BSRIA Briefing: Cleaner Air, Better tomorrow
A look back at issues relating to inside and outside air quality, discussed during the BSRIA briefing in 2023.
Restoring Abbotsford's hothouse
Bringing the writer Walter Scott's garden to life.
Reflections on the spending review with CIAT.
Comments