What hours are construction sites allowed to operate?
[edit] Introduction
Construction sites can be disruptive to the local community for long periods of time. Nuisance that can be caused be construction activities might include:
- Noise.
- Dust.
- Dirt and spillages.
- Damage to highways.
- Traffic congestion.
- Parking issues.
- Disruption to pedestrians.
- Waste accumulation.
- Vibration.
- Odours or smoke.
- Artificial lighting.
However, construction is a necessary activity and in the case of Andreae v. Selfridge & Co. Limited (1958) Sir Wilfred Green MR suggested that ‘...if they are reasonably carried on and all proper and reasonable steps are taken to ensure that no undue inconvenience is caused to neighbours, whether from noise, dust, or other reasons, the neighbours must put up with it.’
Such reasonable steps might include working at reasonable times and restricting disruptive activities to particular periods.
Generally, the hours during which construction sites are allowed to operate is determined by the local authority, in accordance with the Control of Pollution Act, and conditions can be applied to planning permissions in accordance with the Town and Country Planning Act.
In addition, there may be a requirement to comply with BS 5228 Code of Practice for Noise and Vibration Control on Construction and Open Sites, and the Control of Noise at Work Regulations limit the exposure of workers to noise (this is enforced by the Health and Safety Executive).
Typical restrictions might be:
- Monday to Friday: 8am to 6pm.
- Saturdays: 8am to 1pm.
- Sundays and bank holidays: No work permitted, or noisy work prohibited.
Examples of activities that might be prohibited outside of these hours could include:
- The use of hammers and saws.
- The use of drills and sanders.
- Pile driving.
- Erecting and dismantling of scaffolding.
Noise-related work taking place outside these hours will generally only be permitted if the contractor can make a case that it is necessary on the grounds of health and safety.
Different hours may apply, for example in business areas where noise or vibration during normal working hours would be disruptive.
The local authority may also set limits to the amount of noise or vibration that a construction site is permitted to generate and monitoring may be undertaken to ensure that these are not exceeded.
These restrictions do not always apply to civil engineering projects such as rail or highway works.
Steps that a contractor might take to reduce disruption might include:
- Keeping neighbours informed.
- Monitoring noise, vibration and dust.
- Providing a help line so that problems can be reported.
- Restricting disruptive activities to particular periods.
- Storing fine materials under cover.
- Damping fine materials and roadways.
- Minimising demolition or crushing dust.
- Washing down vehicles.
- Taking care when deciding transport routes.
- Providing hard-surfaced roadways.
- Implementing a waste management strategy.
- Avoiding burning waste materials.
- Limiting vibration.
- Using well-maintained, quiet machinery.
- Carefully selecting and managing sub-contractors.
- Using low disruption methods of work.
- Properly instructing and supervising staff.
- Providing acoustic screening.
- Very occasionally, offering temporary re-housing for residents.
Some construction sites, companies and suppliers may register with the Considerate Constructors Scheme and then must abide by its Code of Considerate Practice.
Some sites may also have to comply with a code of construction practice imposed by the local authority or by the client.
NB, NRM3: Order of cost estimating and cost planning for building maintenance works, suggests that normal working hours are typically 8.30 to 5.30 Monday to Friday (excluding statutory holidays), but also makes clear that working hours vary.
[edit]
In May 2020, a ‘Safe Working Charter’ was launched by the Government and the Home Builders Federation, enabling builders to return to work safely during the Coronavirus pandemic. This allowed builders to agree more flexible construction working hours with their local council, such as staggering arrival times. Ref https://www.gov.uk/government/news/housing-secretary-sets-out-plan-to-re-start-housing-market
In June 2020 the Business and Planning Bill was introduced, allowing local authorities to rule on extended working hours applications, and generally permitting site working until 9pm, Monday to Saturday, and 24 hour working in some circumstances in non-residential areas. https://www.gov.uk/government/collections/draft-planning-guidance-to-support-the-business-and-planning-bill
[edit] Related articles on Designing Buildings
- Code of construction practice.
- Complaining about construction sites.
- Considerate Constructors Scheme.
- Contractor's working schedule.
- Control of noise at work regulations 2005.
- Environmental health.
- Environmental impact assessment.
- Local authority.
- Noise at Work Assessment.
- Noise nuisance.
- Nuisance.
- Out of hours working.
- Permitted development.
- Planning condition.
- Quiet period.
- Working day.
Featured articles and news
Statement from the Interim Chief Construction Advisor
Thouria Istephan; Architect and inquiry panel member outlines ongoing work, priorities and next steps.
The 2025 draft NPPF in brief with indicative responses
Local verses National and suitable verses sustainable: Consultation open for just over one week.
Increased vigilance on VAT Domestic Reverse Charge
HMRC bearing down with increasing force on construction consultant says.
Call for greater recognition of professional standards
Chartered bodies representing more than 1.5 million individuals have written to the UK Government.
Cutting carbon, cost and risk in estate management
Lessons from Cardiff Met’s “Halve the Half” initiative.
Inspiring the next generation to fulfil an electrified future
Technical Manager at ECA on the importance of engagement between industry and education.
Repairing historic stone and slate roofs
The need for a code of practice and technical advice note.
Environmental compliance; a checklist for 2026
Legislative changes, policy shifts, phased rollouts, and compliance updates to be aware of.
UKCW London to tackle sector’s most pressing issues
AI and skills development, ecology and the environment, policy and planning and more.
Managing building safety risks
Across an existing residential portfolio; a client's perspective.
ECA support for Gate Safe’s Safe School Gates Campaign.
Core construction skills explained
Preparing for a career in construction.
Retrofitting for resilience with the Leicester Resilience Hub
Community-serving facilities, enhanced as support and essential services for climate-related disruptions.
Some of the articles relating to water, here to browse. Any missing?
Recognisable Gothic characters, designed to dramatically spout water away from buildings.
A case study and a warning to would-be developers
Creating four dwellings... after half a century of doing this job, why, oh why, is it so difficult?
Reform of the fire engineering profession
Fire Engineers Advisory Panel: Authoritative Statement, reactions and next steps.
Restoration and renewal of the Palace of Westminster
A complex project of cultural significance from full decant to EMI, opportunities and a potential a way forward.
Apprenticeships and the responsibility we share
Perspectives from the CIOB President as National Apprentice Week comes to a close.



























Comments