Taking off construction works
The term ‘taking off’ refers to the process of identifying elements of construction works that can be measured and priced. This is necessary to produce bills of quantities and requires that the design is complete and a specification has been prepared.
Analysis of drawings and specifications allows the cost consultant (usually a quantity surveyor) to prepare a taking off list, which lists all of the individual elements that comprise the works.
These elements can then be measured in number, length, area, volume, weight or time then collated and structured to produce an unpriced bill of quantities. This process is sometimes referred to as ‘working up’.
Where there may be uncertainty about some elements, they may be entered onto a query sheet that can be issued to the appropriate members of the consultant team for clarification.
The unpriced bill of quantities will have price and rate columns for tenderers to complete.
The bill of quantities is issued to tenderers for them to prepare a price for carrying out the works. The bill of quantities assists tenderers in the calculation of construction costs for their tender, and, as it means all tendering contractors will be pricing the same quantities (rather than taking off quantities from the drawings and specifications themselves), it also provides a fair and accurate system for tendering.
Best practice for the preparation of bills of quantities is set out in the New Rules of Measurement (NRM) published by the Royal Institute of Chartered Surveyors and replacing Standard Method of Measurement, seventh edition (SMM7). Adopting the New Rules of Measurement means that all projects are taken off in the same way and in the same order following consistent rules.
Increasingly, software packages are available to assist in the preparation of preparation of bills of quantities, and building information modelling systems can be used to produce bills of quantities from information already contained within the model. The process in Building Information Modelling (BIM) is often referred to as material or quantity takeoff, which uses the underlying 3D parametric model to calculate materials takeoff for cost estimation, as well as in some cases embodied carbon calculations by adding the density factor and CO2 e per kg or volume of material.
In this process care must be taken that digital models are a fair representation of the actual product or component, for examples metal window frames being modelled as hollow extrusions rather than solid elements, the later can impact the material take-off dramatically increasing for example the assumed aluminium used by weight.
Bills of quantities are normally only prepared on larger projects. On smaller projects, or for alteration work, the contractor can be expected to measure their own quantities from drawings and schedules of work. Schedules of work are 'without quantities' instructional lists that allow the contractor to identify significant work and materials that will be needed to complete the works and to calculate the quantities that will be required.
For more information, see How to take off construction works.
[edit] Related articles on Designing Buildings
- Approximate bill of quantities.
- Approximate quantities cost plan.
- Bill of quantities.
- Common Arrangement of Work Sections (CAWS).
- Common mistakes in bill of quantities.
- Comparison of SMM7 with NRM2.
- Computers in tendering.
- Construction work packaging.
- Contract documents
- Cost plans.
- Elemental cost plan.
- Extra over (EO).
- How to take off construction works.
- Measured quantity.
- New Rules of Measurement.
- Spot items.
- Standard Method of Measurement (SMM7).
- Tender.
- Tender documentation.
- Tender pricing document.
- Uniclass.
- Working up construction works.
Featured articles and news
A case study and a warning to would-be developers
Creating four dwellings for people to come home to... after half a century of doing this job, why, oh why, is it so difficult?
Reform of the fire engineering profession
Fire Engineers Advisory Panel: Authoritative Statement, reactions and next steps.
Restoration and renewal of the Palace of Westminster
A complex project of cultural significance from full decant to EMI, opportunities and a potential a way forward.
Apprenticeships and the responsibility we share
Perspectives from the CIOB President as National Apprentice Week comes to a close.
The first line of defence against rain, wind and snow.
Building Safety recap January, 2026
What we missed at the end of last year, and at the start of this...
National Apprenticeship Week 2026, 9-15 Feb
Shining a light on the positive impacts for businesses, their apprentices and the wider economy alike.
Applications and benefits of acoustic flooring
From commercial to retail.
From solid to sprung and ribbed to raised.
Strengthening industry collaboration in Hong Kong
Hong Kong Institute of Construction and The Chartered Institute of Building sign Memorandum of Understanding.
A detailed description from the experts at Cornish Lime.
IHBC planning for growth with corporate plan development
Grow with the Institute by volunteering and CP25 consultation.
Connecting ambition and action for designers and specifiers.
Electrical skills gap deepens as apprenticeship starts fall despite surging demand says ECA.
Built environment bodies deepen joint action on EDI
B.E.Inclusive initiative agree next phase of joint equity, diversity and inclusion (EDI) action plan.
Recognising culture as key to sustainable economic growth
Creative UK Provocation paper: Culture as Growth Infrastructure.
Futurebuild and UK Construction Week London Unite
Creating the UK’s Built Environment Super Event and over 25 other key partnerships.
Welsh and Scottish 2026 elections
Manifestos for the built environment for upcoming same May day elections.
Advancing BIM education with a competency framework
“We don’t need people who can just draw in 3D. We need people who can think in data.”

























Comments
[edit] To make a comment about this article, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.
There is a detailed description of the traditional paper-based technique here: https://www.designingbuildings.co.uk/wiki/How_to_take_off_construction_works