Subcontract procurement
The classic 19th-century definition of a contract is 'a promise or set of promises which the law will enforce' (ref. Pollock, Principles of Contract 13th edition). That is, there is reciprocity of undertaking passing between the promisor and the promisee.
In the construction industry, the main contract is typically the tier 1 contract between the client and the main contractor.
A subcontract is a contract that involves a subcontractor undertaking part of the main contract on behalf of the main contractor. This is generally a tier 2 contract.
Subcontracts normally involve work of a specialist nature carried out by specialist subcontractors Subcontracts on a project can encompass many trades but commonly include:
- Bricklayers.
- Cladding installers.
- Concrete installers.
- Drainlayers.
- Electricians.
- Joiners.
- Scaffolders.
- Steel erectors.
- ICT installers.
- Building services.
Procurement is the process of purchasing goods or services. Procuring subcontractors is the process by which these various specialist trades are brought into a project.
Traditionally there have been three main types of subcontractor:
- Domestic subcontractor. A subcontractor selected and appointed by the main contractor.
- Nominated subcontractor. A subcontractor selected by the client to carry out an element of the works.
- Named subcontractor. A subcontractor selected from a list of acceptable sub-contractors provided by the client.
However, on large or complex projects, the work will cascade down the supply chain to a plethora of subcontractors, sub-subcontractors, and so on.
One of the problems in the construction industry is that the first and second tier of the supply chain sign up to fairly onerous agreements but as the chain develops, so the contractual liabilities decrease until suppliers at the end of the chain are often not locked in at all.
In recent years larger companies offering continuity in construction have taken an increasing interest in establishing relationships beyond direct, first tier suppliers. Framework contracts and partnering agreements have pioneered this approach, encouraging the involvement of selected suppliers at relatively early stages of projects while offering continuity of work.
An integrated supply team is one that involves the integration of the complete supply chain involved in the delivery of a project. Under this route, the entire supply team may be appointed after the project brief has been prepared, often under just one contract rather than separate contracts with each individual company.
[edit] Related articles on Designing Buildings Wiki
- Collaborative practices.
- Construction supply chain payment charter.
- Contract sum.
- Contractor.
- Domestic sub-contractor.
- Named specialist work.
- Named sub-contractor.
- Nominated subcontractor v named subcontractor.
- Nominated supplier.
- OJEU.
- Payments to nominated sub-contractors.
- Preliminaries.
- Prime cost sum.
- Procurement route.
- Selected subcontractor.
- Sub contractor.
Featured articles and news
CIAT responds to the updated National Planning Policy Framework
With key changes in the revised NPPF outlined.
Councils and communities highlighted for delivery of common-sense housing in planning overhaul
As government follows up with mandatory housing targets.
CIOB photographic competition final images revealed
Art of Building produces stunning images for another year.
HSE prosecutes company for putting workers at risk
Roofing company fined and its director sentenced.
Strategic restructure to transform industry competence
EBSSA becomes part of a new industry competence structure.
Major overhaul of planning committees proposed by government
Planning decisions set to be fast-tracked to tackle the housing crisis.
Industry Competence Steering Group restructure
ICSG transitions to the Industry Competence Committee (ICC) under the Building Safety Regulator (BSR).
Principal Contractor Competency Certification Scheme
CIOB PCCCS competence framework for Principal Contractors.
The CIAT Principal Designer register
Issues explained via a series of FAQs.
Conservation in the age of the fourth (digital) industrial revolution.
Shaping the future of heritage
Embracing the evolution of economic thinking.
Ministers to unleash biggest building boom in half a century
50 major infrastructure projects, 5 billion for housing and 1.5 million homes.
RIBA Principal Designer Practice Note published
With key descriptions, best practice examples and FAQs, with supporting template resources.
Electrical businesses brace for project delays in 2025
BEB survey reveals over half worried about impact of delays.
Accelerating the remediation of buildings with unsafe cladding in England
The government publishes its Remediation Acceleration Plan.
Airtightness in raised access plenum floors
New testing guidance from BSRIA out now.