Structural engineers' fees
Fees are generally payments to consultants to cover work they have undertaken for clients under the terms of an agreement. They are generally paid in instalments, either on regular dates or at pre-agreed stages of completed work.
Structural engineers fees may be calcuated based on time charges, as a fixed lump sum or as a percentage of the overall project cost. Fees are entirely dependent on the nature of the project and the circumstances of the appointment. Large new-build projects may attract lower percentage fees than small works to existing buildings (see table below), commercial work may attract lower fees than private residential work, and works to historic or listed buildings may attract higher fees.
The examples given below are indicative only and apply mainly to small projects. Fee calculation may be based on:
- Charging a lump sum, particularly for small projects (eg £1,000 for a standard domestic extension, plus extra for structural details or special foundations; or £750 for a loft conversion inclusive of calculations and structural details);
- Flat-rate fees: site visits (eg starting at £150 per visit); design of steel beams and bearing details (eg, £75 for a single beam and £50 for each beam thereafter); masonry check (eg £100); goal-post frame (eg £200 - £300); and steel connections (eg £50 per connection).
- Hourly or daily rates (eg £80-£100/hour; £400-£500 per half day, etc);
- A percentage of the project’s total cost (see table below).
The fee percentage will depend on the size of the project (in project cost terms). The following table gives the fees a structural engineer might charge (at 2013 prices) for work undertaken on commercial office developments in London of varying costs.
Construction cost (excl. contingencies and VAT) | Under £1.5m | £1.5m - £3m | £3m - £10m | £10m - £25m | £25m –£50m | £50m+ |
Struct'al engineer % and actual fee |
2% £30k max |
2% £30k – £60k |
1.8% £54k– £180k |
1.5% £150k – £375k |
1% £250k – £500k |
1% £500k+ |
Other things that might affect the fees charged include:
- Type and complexity of project (eg hospital v industrial shed);
- Scope of services. For example, full design and site inspection will attract a higher fee than a preliminary design that is then developed by the contractor;
- Anticipated repeat and/or bespoke elements of the design;
- Location of site and other consultant practices;
- Reputation of practice. For example, an accomplished engineering firm may charge more than one that is newly qualified;
- Client organisation and track record. This may affect how much support is required and the risk perceived by the engineers;
- Conditions of engagement. For example, the requirement for collateral warranties and partnering arrangements;
- Anticipated programme and resources required.
- Economic climate. Fees may be lower during recessions and higher during booms;
- Consultant workload, and
- Assessment of the competencies of other consultants.
When agreeing fees, it is important to be clear exactly what services are being provided, for example, do the fees include travel, printing costs, outline and detailed planning applications and so on. For more information see: Scope of services.
Professional institutes used to publish recommended fee scales expressed as a percentage of construction costs for a range of different building types. However, legislation aimed at preventing anti-competitive behaviour forced the institutes to abolish these scales, leaving little guidance for clients about what is normal.
Consequently, bidding for consultancy work has become a free-for-all in a highly competitive market. Some commentators argue that this has driven down fees, however, it may also have driven down standards and led to much design work being transferred from consultants to specialist contractors and suppliers who include design costs in their building agreements.
It is important therefore to obtain several quotes for fees, to be clear what is being provided and to be wary of just assuming the lowest quote provides the best value.
[edit] Related articles on Designing Buildings Wiki
- Appointing consultants.
- Architects fees.
- Base date.
- Charge-out rate.
- Compensation.
- Consideration.
- Construction organisations and strategy.
- Consultant team.
- Contractual obligation.
- Design team.
- Disbursement.
- Hourly rate.
- Invoice.
- Letter of appointment.
- Planning fees.
- Quantity surveyor’s fees.
- Rates.
- Schedule of services.
- Scope of services.
- Sub-consultant.
- Winning work.
Featured articles and news
Welsh Skills Body (Medr) launches ambitious plan
The new skills body brings together funding and regulation of tertiary education and research for the devolved nation.
Paul Gandy FCIOB announced as next CIOB President
Former Tilbury Douglas CEO takes helm.
UK Infrastructure: A 10 Year Strategy. In brief with reactions
With the National Infrastructure and Service Transformation Authority (NISTA).
Ebenezer Howard: inventor of the garden city. Book review.
The Grenfell Tower fire, eight years on
A time to pause and reflect as Dubai tower block fire reported just before anniversary.
Airtightness Topic Guide BSRIA TG 27/2025
Explaining the basics of airtightness, what it is, why it's important, when it's required and how it's carried out.
Construction contract awards hit lowest point of 2025
Plummeting for second consecutive month, intensifying concerns for housing and infrastructure goals.
Understanding Mental Health in the Built Environment 2025
Examining the state of mental health in construction, shedding light on levels of stress, anxiety and depression.
The benefits of engaging with insulation manufacturers
When considering ground floor constructions.
Lighting Industry endorses Blueprint for Electrification
The Lighting Industry Association fully supports the ECA Blueprint as a timely, urgent call to action.
BSRIA Sentinel Clerk of Works Training Case Study
Strengthening expertise to enhance service delivery with integrated cutting-edge industry knowledge.
Impact report from the Supply Chain Sustainability School
Free sustainability skills, training and support delivered to thousands of UK companies to help cut carbon.
The Building Safety Forum at the Installershow 2025
With speakers confirmed for 24 June as part of Building Safety Week.
The UK’s largest air pollution campaign.
Future Homes Standard, now includes solar, but what else?
Will the new standard, due to in the Autumn, go far enough in terms of performance ?
BSRIA Briefing: Cleaner Air, Better tomorrow
A look back at issues relating to inside and outside air quality, discussed during the BSRIA briefing in 2023.
Restoring Abbotsford's hothouse
Bringing the writer Walter Scott's garden to life.
Reflections on the spending review with CIAT.
Comments
It would be nice if you could update the table to show a more realistic (current for 2021) percentage of fee.
These numbers are quite a way off what the market is currently.
This is a WIki site - if you have better information, please click 'Edit this article' and add it.