National Infrastructure Planning Reform Programme
This article was written by Jenny Preece - Deputy Director for Planning - Infrastructure, in Planning Directorate within Department for Levelling Up, Housing and Communities (DLUHC), formerly the Ministry for Housing, Communities and Local Government.
[edit] Introduction
What do Thames Tideway and Hinkley Point have in common? For one, they were major projects of great importance to the UK. Secondly, they were infrastructure projects that were approved under the Nationally Significant Infrastructure Projects (NSIP) regime – and that process is now under review.
[edit] What is the Nationally Significant Infrastructure Projects (NSIP) regime?
The NSIP regime was established in 2008 and has now seen approximately 100 important energy, transport, water, wastewater and waste developments determined, with a 95% approval rate. It has a strong record for offering high quality consents, robust to legal challenge and with certainty of timescales for investors.
Practice has evolved quickly and the NSIP process has become recognised for the way in which it's able to deliver timely consents in the national interest, as the growth of offshore wind has powerfully demonstrated.
The process has also enabled highly complex projects such as Hinkley C new nuclear power station, Thames Tideway Tunnel Waste Water, and the Tilbury2 Port facility to be consented within the statutory time limits.
[edit] Why does the process for consenting NSIPs need reforming?
The context in which the regime was established is changing constantly. New and novel types of projects are using the process, some communities are experiencing clusters of NSIPs, and each NSIP brings with it increasingly significant volumes of information to interrogate.
The overall recent pattern for NSIPs is one of longer timescales and greater complexity (as recent offshore wind decisions have demonstrated) and looking ahead, the regime will need to continue to navigate global challenges such as climate change and rapid technological change.
It is important that the planning process responds to these challenges and is able to play its full role in driving our economic recovery, and progress towards net zero.
[edit] What is the government’s goal for the new NSIP process?
This government believes that it's possible and necessary for the UK’s global competitiveness to deliver infrastructure more quickly, and we have set an ambition that, by September 2023, some projects will be able to go through the NSIP process in up to half the time than at present. We believe this can be achieved while also improving the quality and fairness of the process, and with better and greener outcomes.
The National Infrastructure Planning Reform Programme will refresh how the NSIP regime operates, making it more effective and bringing government departments together to deliver more certainty in the process and better and faster outcomes.
[edit] How you can get involved with the government’s Operational Review
Fundamental to the success of the reform programme is first establishing a holistic and robust understanding of how the NSIP process currently operates, allowing us to carefully target improvements.
We are therefore undertaking a comprehensive end-to-end review of the NSIP process and all its interactions – our Operational Review.
This Operational Review was launched at the National Infrastructure Planning Association (NIPA) summer conference in July. In advance of that meeting, Minister Chris Pincher wrote to NIPA members on 21 June to introduce the reform programme and launch our Operational Review. In the annex to this letter, he posed the following questions which he wants those who interact with the regime to carefully consider:
- What the government, its arms-length bodies and other statutory bodies could do to accelerate NSIP applications.
- Aspects of the examination and decision process which might be enhanced.
- Impediments to physically implementing NSIP projects.
- Digital improvements to the regime.
- Cross-government co-ordination including government departments and arms-length bodies.
- Interactions with other consenting and regulatory processes and the wider context within which infrastructure projects operate.
- Potential limits in the capacity or capability of NSIP applicants, interested parties and other participants.
The government is keen to hear from all those who engage with the NSIP regime, including but not limited to local authorities, statutory consultees, specialists such as engineers, environmental experts and project managers, and the communities affected by development.
We want to understand what they see as the main issues affecting it, and what potential solutions might be deployed to remedy these.
[edit] Have your say
To help inform our review of the NSIP process, we invite you to respond to this survey, which poses the questions set out in Minister Pincher’s letter to NIPA members.
This survey forms an important part of our first phase of evidence gathering and will be kept open until 17 December 2021.
This article originally appeared as: ‘How civil engineers can help improve how nationally significant infrastructure is approved in the UK’ on the ICE Infrastructure Blog on 6 October, 2021. It was written by Jenny Preece, deputy director at the Department for Levelling Up, Housing and Communities.
--The Institution of Civil Engineers
[edit] Related articles on Designing Buildings
- Breaking Barriers in Infrastructure - perspectives from the profession
- Crossrail 2.
- Development consent order.
- Generation nuclear.
- ICE articles.
- Instrumentation operated in the national interest.
- Major Projects Authority.
- National Infrastructure Plan.
- Nationally Significant Infrastructure Project initiatives reach milestone.
- Planning Act 2008.
- Planning permission.
- Safeguarding land.
- The Institution of Civil Engineers.
- Wind farm.
Featured articles and news
Boiler Upgrade Scheme and certifications consultation
Summary of government consultation which closes 11 June 2025.
Deputy editor of AT, Tim Fraser, discusses the newly formed society with its current chair, Chris Halligan MCIAT.
Barratt Lo-E passivhaus standard homes planned enmasse
With an initial 728 Lo-E homes across two sites and many more planned for the future.
Government urged to uphold Warm Homes commitment
ECA and industry bodies write to Government concerning its 13.2 billion Warm Homes manifesto commitment.
Places of Worship in Britain and Ireland, 1929-1990. Book review.
The emancipation of women in art.
CIOB Construction Manager of the Year 2025
Just one of the winners at the CIOB Awards 2025.
Call for independent National Grenfell oversight mechanism
MHCLG share findings of Building Safety Inquiry in letter to Secretary of State and Minister for Building Safety.
The Architectural Technology Awards
AT Awards now open for this the sixth decade of CIAT.
50th Golden anniversary ECA Edmundson awards
Deadline for submissions Friday 30 May 2025.
The benefits of precast, off-site foundation systems
Top ten benefits of this notable innovation.
Encouraging individuals to take action saving water at home, work, and in their communities.
Takes a community to support mental health and wellbeing
The why of becoming a Mental Health Instructor explained.
Mental health awareness week 13-18 May
The theme is communities, they can provide a sense of belonging, safety, support in hard times, and a sense purpose.
Mental health support on the rise but workers still struggling
CIOB Understanding Mental Health in the Built Environment 2025 shows.
Design and construction material libraries
Material, sample, product or detail libraries a key component of any architectural design practice.
Construction Products Reform Green Paper and Consultation
Still time to respond as consultation closes on 21 May 2025.
Resilient façade systems for smog reduction in Shanghai
A technical approach using computer simulation and analysis of solar radiation, wind patterns, and ventilation.