Measured quantity
Quantity is a measurement of a physical entity in units that depend on the nature of that entity. Therefore, quantity indicates how much of something exists, existed or will exist.
In construction, ‘measured quantities’ typically form part of a bill of quantities (BoQ) and indicate how much of something will be required to construct a building or part of a building.
Usually prepared by a quantity surveyor (QS), the BoQ provides project-specific, measured quantities of the items of work identified by the drawings and specifications (which form part of the tender documentation). For example, in a traditional building, the BoQ will contain measured quantities for each item that goes to make up the final construction e.g bricks, doors, ironmongery, floor tiles, roof slates, etc. This means that potential tenderers know exactly how much of a given quantity will be required for the work and so they can price for it. This creates a level playing field as all tenderers are pricing for the same measured quantities which allows the client to make easy comparisons between the bids.
Measured quantities are typically expressed in number (e.g door handles), length (e.g handrails, kerbs), area (e.g floor tiles, plaster), volume (e.g concrete) or weight (e.g gravel).
When prices have been entered by a tenderer beside each measured quantity in a BoQ, this constitutes the tenderer’s offer.
Not providing measured quantities would require that the various tenderers on a project ‘take off’ the quantities themselves. With numerous tenderers with possibly different methodologies, as well as human error creeping in, the quantities taken off would vary, thus making the client’s job in comparing the tenders that much harder.
The New Rules of Measurement (NRM) are published by the Royal Institution of Chartered Surveyors' (RICS) Quantity Surveying and Construction Professional Group. They provide a standard set of measurement rules for estimating, cost planning, procurement and whole-life costing for construction projects. Adopting a standard methodology such as NRM facilitates consistency and benchmarking and helps avoid disputes.
NRM is a suite of documents, comprising three volumes; NRM1, NRM2 and NRM3.
Fore more information see: New rules of measurement.
In some circumstances, it may be difficult to determine exact quantities, for example early in the development of a project. In this case approximate quantities may be estimated. These should be accompanied by a schedule of the assumptions made in determining the approximate quantities.
For more information see: Approximate quantities.
[edit] Related articles on Designing Buildings Wiki
- Approximate quantities.
- Bill.
- Taking off construction works
- Bill of quantities breakdown structures BQBS
- Types of bill of quantities
- Standard Method of Measurement SMM7
- Preliminaries in construction
- Schedule of rates for construction
- Bill of quantities software
- Tender documentation for construction projects
- Approximate bill of quantities
- How to take off construction works
- Specification for construction
- Advantages of a bill of quantities
- New Rules of Measurement
- Typical tender process for construction projects
- Priced bill of quantities
- All-in rates
- Common mistakes in bill of quantities
- Bill of quantities v Schedule of rates
Featured articles and news
Costs and insolvencies mount for SMEs, despite growth
Construction sector under insolvency and wage bill pressure in part linked to National Insurance, says report.
The place for vitrified clay pipes in modern infrastructure
Why vitrified clay pipes are reclaiming their role in built projects.
Research by construction PR consultancy LMC published.
Roles and responsibilities of domestic clients
ACA Safety in Construction guide for domestic clients.
Fire door compliance in UK commercial buildings
Architect and manufacturer gives their low down.
Plumbing and heating for sustainability in new properties
Technical Engineer runs through changes in regulations, innovations in materials, and product systems.
Awareness of the Carbon Border Adjustment Mechanism
What CBAM is and what to do about it.
The new towns and strategic environmental assessments
12 locations of the New Towns Taskforce reduced to 7 within the new towns draft programme and open consultation.
Buildings that changed the future of architecture. Book review.
The Sustainability Pathfinder© Handbook
Built environment agency launches free Pathfinder© tool to help businesses progress sustainability strategies.
Government outcome to the late payment consultation, ECA reacts.
IHBC 2025 Gus Astley Student Award winners
Work on the role of hewing in UK historic conservation a win for Jack Parker of Oxford Brookes University.
Future Homes Building Standards and plug-in solar
Parts F and L amendments, the availability of solar panels and industry responses.
How later living housing can help solve the housing crisis
Unlocking homes, unlocking lives.
Preparing safety case reports for HRBs under the BSA
A new practical guide to preparing structural inputs for safety cases and safety case reports published by IStructE.
Male construction workers and prostate cancer
CIOB and Prostate Cancer UK encourage awareness of prostate cancer risks, and what to do about it.