Invitation to tender for construction contracts
[edit] What is an invitation to tender?
An invitation to tender (ITT - or sometimes 'invitation to treat') is a formal invitation to make an offer for the supply of goods or services. It might be issued for a range of suppliers, including:
- Equipment or plant supply.
- Product supply.
- Design.
- Trade contractors or works contractors.
- Specialist contractors or suppliers.
- Main construction contractors.
- Demolition or enabling works contractors.
[edit] What happens before an invitation to tender?
Before an invitation to tender is issued, tender documentation needs to be prepared describing what is required, and a list of prospective tenderers compiled who will be invited to tender. This might include an assessment of pre-qualification questionnaires (PQQs) received by the client in response to an advert they have posted, and perhaps a pre-tender interview with prospective tenderers.
The purpose of pre-qualification questionnaires and pre-tender interviews is to produce a shortlist of suppliers who are considered most appropriate for the project and who will then be invited to tender. This avoids time being wasted on both sides, preparing and assessing inappropriate tenders.
[edit] What should an invitation to tender include?
An invitation to tender will include information describing the goods or services required in sufficient detail to enable the tenderer to prepare an accurate tender. It should also describe a standard format for tender submissions so that they are easy to compare.
An invitation to tender might include:
- Letter of invitation to tender.
- Form of tender.
- Preliminaries (including pre-construction information and site waste management plan).
- Form of contract, contract conditions and amendments.
- Employer's information requirements and BIM protocol.
- Tender pricing document (or form of contract sum analysis on design and build projects)
- Drawing schedule.
- Design drawings.
- Prescriptive or performance specifications (on public projects, tender documentation may include an output-based specification rather than prescriptive or performance specifications and drawings).
- Instructions to tenderers explaining the tender process.
- The timescale for the tender process (including the address and time for the return of tenders).
- An explanation of how queries will be dealt with.
- The evaluation process and any evaluation criteria.
- The submission required in response to the invitation to tender.
- Policy in relation to alternative or non-compliant bids.
- Policy for providing feedback to unsuccessful tenderers.
[edit] How should tenderers respond to an invitation to tender?
In response to an invitation to tender, invited tenderers (bidders) will submit their tender, which will include their price for supplying the goods or services along with proposals for how the clients requirements will be satisfied.
The precise content of tenders will vary considerably depending on the procurement route, however they might include:
- A tender return slip, with details of the contract, including information such as return address and tender checklist;
- A completed tender pricing document (or contract sum analysis on design and build projects);
- Schedules of rates;
- An initial construction phase plan;
- Any design proposals or method statements that have been requested;
- Programme;
- Procedures to be adopted, such as procurement procedures and cost management procedures;
- Demonstration of capability, for example design capability, systems used etc;
- A BIM execution plan - if building information modelling is being used;
- Key project personnel, which may require submission of CVs;
- Management organisation;
- Plant and labour resources and availability;
- Prior experience, and
- References.
See also: Common mistakes in construction tenders.
[edit] What are non-compliant tenders?
Alternative or non-compliant proposals, sometimes referred to as 'variant bids' may be submitted if the tenderer believes that what they are proposing offers better value for money. However, non-compliant proposals should only be submitted if they have been requested and should be accompanied by a compliant proposal.
For more information, see Variant bid.
[edit] What happens after tenders are submitted?
Once tenders have been received, a careful process of assessment must be undertaken to identify the preferred tenderer. This is known as tender evaluation (or sometimes, tender adjudication).
Typically, assessments might consider some of the following criteria:
- Price.
- Relevant experience.
- Understanding of the requirements.
- Past performance.
- Technical skills.
- Resource availability.
- Management skills and systems.
- Proposed methodology (this might include mobilisation plans, design proposals, and non-compliant proposals if these have been allowed).
- Compliance with the requirements set out in the invitation to tender.
For more information see: Tender evaluation.
This may be followed by a period of negotiation, before final terms of the contract are agreed.
For more information see: Tender negotiation.
[edit] Related articles on Designing Buildings
- Bid evaluation.
- Bid writer.
- Common mistakes in construction tenders.
- Compliant bid.
- Contract sum analysis.
- E-procurement.
- How to prepare tender documents.
- Invitation to negotiate.
- Mid-tender interviews.
- Most Economically Advantageous Tender (MEAT).
- Non-compliant tender.
- Pre-qualification questionnaire.
- Pre qualification questionnaires and PAS 91.
- Preferred tenderer.
- Pre-tender interviews.
- Procurement route.
- Selection criteria.
- Tender.
- Tender documentation.
- Tender evaluation.
- Tender price appraisal.
- Tender pricing document.
- Tender settlement meeting.
- The benefits of e-procurement in construction.
- Things to avoid when tendering.
[edit] External references
- OGC guidance provides a range of standard documents for obtaining and processing tenders on public projects. (now archived)
- A description of the contents of an invitation to tender for public projects can be found in PACE Guidance on the Appointment of Consultants and Contracotrs P486 and 487. (Now archived)
- OGC guide to EU procurement rules. (now archived)
- The Public Contracts Regulations.
Featured articles and news
International Electrician Day, 10 June 2025
Celebrating the role of electrical engineers from André-Marie Amperè, today and for the future.
New guide for clients launched at Houses of Parliament
'There has never been a more important time for clients to step up and ...ask the right questions'
The impact of recycled slate tiles
Innovation across the decades.
EPC changes for existing buildings
Changes and their context as the new RdSAP methodology comes into use from 15 June.
Skills England publishes Sector skills needs assessments
Priority areas relating to the built environment highlighted and described in brief.
BSRIA HVAC Market Watch - May 2025 Edition
Heat Pump Market Outlook: Policy, Performance & Refrigerant Trends for 2025–2028.
Committing to EDI in construction with CIOB
Built Environment professional bodies deepen commitment to EDI with two new signatories: CIAT and CICES.
Government Grenfell progress report at a glance
Line by line recomendation overview, with links to more details.
An engaging and lively review of his professional life.
Sustainable heating for listed buildings
A problem that needs to be approached intelligently.
50th Golden anniversary ECA Edmundson apprentice award
Deadline for entries has been extended to Friday 27 June, so don't miss out!
CIAT at the London Festival of Architecture
Designing for Everyone: Breaking Barriers in Inclusive Architecture.
Mixed reactions to apprenticeship and skills reform 2025
A 'welcome shift' for some and a 'backwards step' for others.
Licensing construction in the UK
As the latest report and proposal to licence builders reaches Parliament.
Building Safety Alliance golden thread guidance
Extensive excel checklist of information with guidance document freely accessible.
Fair Payment Code and other payment initiatives
For fair and late payments, need to work together to add value.
Pre-planning delivery programmes and delay penalties
Proposed for housebuilders in government reform: Speeding Up Build Out.
High street health: converting a building for healthcare uses
The benefits of health centres acting as new anchor sites in the high street.