Construction contractor
Contents |
[edit] Introduction
In very broad terms, contractors are the organisations appointed by clients to carry out construction works. However, this apparently simple relationship is complicated by the fact that contractors tend not to have all the trades required to construct a building in their direct employment.
This means that a contractor is likely to appoint a range of sub-contractors to build the works for which they have been contracted.
[edit] Contractor appointments
Contractors can be appointed in a number of different ways, with varying degrees of risk and reward:
[edit] General contractor, prime contractor or main contractor
These are often appointed under a traditional contract to construct a development for which the design is complete.
Civil Engineering Procedure, 7th edition, published by the Institution of Civil Engineers defines a 'general contractor' as '...a contractor who undertakes the whole of the construction of a project, but usually in turn sub-letting parts of his work to specialist or trades contractors and others as sub-contractors'.
It defines 'main contractor' in the same way but with the qualification that this is distinct from a managing contractor or construction manager.
NRM2, RICS new rules of measurement, Detailed measurement for building work, defines the main contractor (or prime contractor) as '...the contractor responsible for the total construction and completion process of the building project. The term ‘prime contractor’ is often used in central civil government and the defence sector to mean ‘main contractor’.' (see also Prime contractor below).
[edit] Construction manager
The construction manager manages trade contractors, but the trade contracts themselves are placed with the client. This generally requires an experienced client. A construction manager is generally appointed early in the design process so that their experience can be used to improve the buildability and packaging of proposals as they develop.
A construction manager may also programme construction to begin before the design is completed. This requires careful planning of information release so that the construction process is not delayed by lack of production information.
For more information, see Construction manager.
[edit] Management contractor
This is similar to the role of the construction manager but the trade contracts (or works contracts) are placed with the management contractor rather than with the client.
For more information, see Management contractor.
[edit] Design and build contractor
Responsible for the completion of the design as well as construction.
[edit] Prime contractors
The client enters into a long-term multi-project relationship with a contractor in which competition is introduced at the sub-contract level. Prime contracting is generally only appropriate for very large clients such as the Ministry of Defence which is continually commissioning new buildings and refurbishment work.
For more information, see Prime contract.
NB: NRM2: Detailed measurement for building works suggest that; 'The term ‘prime contractor’ is often used in central civil government and the defence sector to mean ‘main contractor’', that is; 'the contractor responsible for the total construction and completion process of the building project.'
[edit] Integrated supply team
This is favoured by the government, and involves appointment of a full project team (including contractors, suppliers, designers and sometimes facilities managers) to design and construct the works.
For more information, see Integrated supply team.
[edit] Design, build and manage contractors
The contractor is appointed not only to design and build the works, but also to manage them during operation, sometimes providing operational services over and above building maintenance, such as supplying prison staff or sterilisation of hospital instruments.
[edit] Principal contractor
The contractor may also be designated the principal contractor under the CDM regulations to plan, manage and co-ordinate health and safety while construction work is being undertaken.
For more information, see Principal contractor.
Other terms used to describe contractors and sub-contractors include:
- Specialist contractors.
- Domestic sub-contractors.
- Nominated sub-contractors.
- Named sub-contractors.
- Trade contractors.
- Trades contractors.
- Work package contractor.
- Works contractors.
[edit] Related articles on Designing Buildings
- Approved contractor.
- Builder vs contractor.
- Constructor.
- Construction Industry Scheme.
- Construction manager.
- Construction contract.
- Construction strategy.
- Contracting.
- Contractor vs supplier.
- Contractor's working schedule.
- Due diligence when selecting contractors or subcontractors.
- Housebuilder.
- Job order contracting.
- Management contractor.
- Master builder.
- Principal contractor.
- Procurement route.
- Sub-contractor.
- Supplier.
- Trade contractor.
- Trades contractor.
- Types of contractor.
- Traditional procurement method.
- Work package contractor.
- Works contractor.
Featured articles and news
CIAT responds to the updated National Planning Policy Framework
With key changes in the revised NPPF outlined.
Councils and communities highlighted for delivery of common-sense housing in planning overhaul
As government follows up with mandatory housing targets.
CIOB photographic competition final images revealed
Art of Building produces stunning images for another year.
HSE prosecutes company for putting workers at risk
Roofing company fined and its director sentenced.
Strategic restructure to transform industry competence
EBSSA becomes part of a new industry competence structure.
Major overhaul of planning committees proposed by government
Planning decisions set to be fast-tracked to tackle the housing crisis.
Industry Competence Steering Group restructure
ICSG transitions to the Industry Competence Committee (ICC) under the Building Safety Regulator (BSR).
Principal Contractor Competency Certification Scheme
CIOB PCCCS competence framework for Principal Contractors.
The CIAT Principal Designer register
Issues explained via a series of FAQs.
Conservation in the age of the fourth (digital) industrial revolution.
Shaping the future of heritage
Embracing the evolution of economic thinking.
Ministers to unleash biggest building boom in half a century
50 major infrastructure projects, 5 billion for housing and 1.5 million homes.
RIBA Principal Designer Practice Note published
With key descriptions, best practice examples and FAQs, with supporting template resources.
Electrical businesses brace for project delays in 2025
BEB survey reveals over half worried about impact of delays.
Accelerating the remediation of buildings with unsafe cladding in England
The government publishes its Remediation Acceleration Plan.
Airtightness in raised access plenum floors
New testing guidance from BSRIA out now.
Comments