Holme Gardens: a case study and a warning to would-be developers
Our client owned a piece of waste ground at the rear of a commercial building, which for 30 years plus had served no purpose to anyone, except fly tippers.
Back in 2004, we tried to get planning permission for additional parking, which was refused because of concerns over additional traffic. In 2005, we applied for planning permission for two houses, which were refused because of a shortage of parking. Following several consultations with the planning department, we applied for and received planning permission for four flats in 2017.
The reasons for the earlier refusals were never aesthetic but always traffic generation, lack of parking, or the removal of a tree (the Planning Department had put a preservation order on a silver birch soon after the car park refusal). Funding now was the next issue, and it took three years to get the land ownership legally split and then funding in place. This now took us up to the COVID pandemic, which was helpful in that we could make use of the extended time given beyond the stipulated three years to commence building.
The next aspect was to ask the Planning Department to approve the intended bricks. The planners made full use, and beyond, of the two months to give the approval of the bricks, leaving us three days for the builder to get the foundations in the ground, or we would default on the planning condition and so lose the planning approval that was so hard won.
In the meantime, we dealt with the contaminated soil that had to be removed, the Party Wall Notice, getting electricity and the internet connected, and all items that had to be organised and paid for prior to commencement. We were lucky in that the more recent onerous requirements regarding flooding and net diversity had not yet come into effect.
Our client asked us at this point to get a modified planning approval, separating it from the existing Victorian terrace, to simplify the foundation design – fat chance! The planners refused the modification. Never mind; we found a technical solution to the foundation issue, and work on site commenced.
The project took 18 months to build; quite long for such a project. Apparently, the builder trusted only one bricklayer, and this bricklayer laid every single brick; meticulously, though, I might add. So, it took an inordinate amount of time to get up to plate level. By now, the builder had taken on other jobs to work on in the meantime, so the following activities were pretty slow. On reflection, we should have set a completion date backed up by financial implications for the builder. Still, after waiting so many years to get the project out of the ground, a few extra months to guarantee a good quality build and good client/ builder relations didn’t seem important. Sadly, the workmanship and this relationship weren’t that good either, in the end.
The four flats that make up Holme Gardens were completed in 2023, and if by now you might be thinking, was it worth it? Well, yes, it was.
The project sum was £370k, with extras, demolition (including asbestos removal) and landscaping costs of £25k (amounting to 7%), bringing the total build cost to £395k without professional and statutory fees. Building Tectonics fees are not going to be disclosed here, but when you think of the effort we put in to getting this project built, it was never enough. But that is what we do, and if we were not so diligent, steadfast, and enduring, the development may not have been built. Or it may not have received so many accolades from locals on how the development fits in with the street scene (it fits in so well that many passersby assume they have always been there). We are not the type of practice that wants to set the world on fire with some egotistical design; we are perfectly happy to design four flats that look like two Victorian terrace houses (although it is a bit galling to an architectural practice when many passersby assume that this building has always been there. New flats? What new flats?).
Even with the stonework detailing on the façade, the triple glazing, the passive stack ventilation system, and other energy saving technology, in a building that looks over a century old, the cost works out at just over £2,000 per square metre. For those not in the know, the norm for flats would be at least £2,400 in this location, at this time, and for a small development.
More important perhaps than the monetary numbers to us is the knowledge that we have produced four dwellings for people to come home to. What I did not understand and still do not understand, after half a century of doing this job, is why, oh why, is it so difficult?
This article appeaers in the AT Journal issue AT Journal ISSUE 156 – WINTER 2025 as "Holme Gardens: a case study and a warning to would-be developers" written by Tony Keller FCIAT, Director and Owner, Building Tectonics Ltd.
--CIAT
Featured articles and news
A case study and a warning to would-be developers
Creating four dwellings for people to come home to... after half a century of doing this job, why, oh why, is it so difficult?
Reform of the fire engineering profession
Fire Engineers Advisory Panel: Authoritative Statement, reactions and next steps.
Restoration and renewal of the Palace of Westminster
A complex project of cultural significance from full decant to EMI, opportunities and a potential a way forward.
Apprenticeships and the responsibility we share
Perspectives from the CIOB President as National Apprentice Week comes to a close.
The first line of defence against rain, wind and snow.
Building Safety recap January, 2026
What we missed at the end of last year, and at the start of this...
National Apprenticeship Week 2026, 9-15 Feb
Shining a light on the positive impacts for businesses, their apprentices and the wider economy alike.
Applications and benefits of acoustic flooring
From commercial to retail.
From solid to sprung and ribbed to raised.
Strengthening industry collaboration in Hong Kong
Hong Kong Institute of Construction and The Chartered Institute of Building sign Memorandum of Understanding.
A detailed description from the experts at Cornish Lime.
IHBC planning for growth with corporate plan development
Grow with the Institute by volunteering and CP25 consultation.
Connecting ambition and action for designers and specifiers.
Electrical skills gap deepens as apprenticeship starts fall despite surging demand says ECA.
Built environment bodies deepen joint action on EDI
B.E.Inclusive initiative agree next phase of joint equity, diversity and inclusion (EDI) action plan.
Recognising culture as key to sustainable economic growth
Creative UK Provocation paper: Culture as Growth Infrastructure.
Futurebuild and UK Construction Week London Unite
Creating the UK’s Built Environment Super Event and over 25 other key partnerships.
Welsh and Scottish 2026 elections
Manifestos for the built environment for upcoming same May day elections.
Advancing BIM education with a competency framework
“We don’t need people who can just draw in 3D. We need people who can think in data.”



























