How long does planning permission last
Before 1968, there was no limit on the duration of planning permissions. Between 1968 and 2009, the duration of a permission was generally set out in the conditions to the permission, often limited to 5 years within which time construction had to begin, although it was sometimes possible to extend this by applying to vary the condition.
However, since 2009, unless the permission states otherwise, development should begin within 3 years of the date permission was granted.
The development is considered to have begun ‘…on the earliest date that a "material operation" in connection with the development is started’, that is:
- Any work of construction in the course of the erection of a building.
- Any work of demolition of a building.
- The digging of a trench which is to contain the foundations, or part of the foundations, of a building.
- The laying of any underground main or pipe to the foundations, or part of the foundations, of a building or to any such trench as is mentioned (above).
- Any operation in the course of laying out or constructing a road or part of a road.
- Any change in the use of any land which constitutes material development.
Ref Town and Country Planning Act 1990, Section 56.
Lawfully commencing the development works may first involve satisfying conditions applied to the permission.
If the development has not commenced within three years, the permission will be considered to have expired, and if the applicant still wished to proceed with the development, they will need to renew the application. Renewal is generally less onerous than making a fresh application, but a fee is payable. If however, the conditions under which the original permission was granted have changed, it may be necessary to make a fresh application.
Once the development has commenced, the permission remains in place unless the local authority serve a completion notice. If such a notice is served, the development must then be completed within 12 months.
If an outline planning application has been made, then the relevant reserved matters applications must be made within three years. The permission will then last for a further 2 years.
See also: How long does it take to get planning permission.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
- Approval of conditions on a planning permission.
- Avoiding planning permission pitfalls.
- Community Infrastructure Levy.
- Design and access statements.
- Detailed planning application.
- Environmental impact assessment.
- Extensions to time limits for implementing existing planning permissions.
- How long does it take to get planning permission.
- National Planning Policy Framework.
- National Planning Practice Guidance.
- Neighbourhood planning.
- Outline planning application.
- Permitted development.
- Planning appeal.
- Planning authority.
- Planning conditions.
- Planning enforcement.
- Planning fees.
- Planning objection.
- Planning obligations.
- Planning performance agreement.
- Planning permission.
- Pre-application advice.
- The difference between planning permission building regulations approval.
Featured articles and news
Deputy editor of AT, Tim Fraser, discusses the newly formed society with its current chair, Chris Halligan MCIAT.
Barratt Lo-E passivhaus standard homes planned enmasse
With an initial 728 Lo-E homes across two sites and many more planned for the future.
Government urged to uphold Warm Homes commitment
ECA and industry bodies write to Government concerning its 13.2 billion Warm Homes manifesto commitment.
Places of Worship in Britain and Ireland, 1929-1990. Book review.
The emancipation of women in art.
CIOB Construction Manager of the Year 2025
Just one of the winners at the CIOB Awards 2025.
Call for independent National Grenfell oversight mechanism
MHCLG share findings of Building Safety Inquiry in letter to Secretary of State and Minister for Building Safety.
The Architectural Technology Awards
AT Awards now open for this the sixth decade of CIAT.
50th Golden anniversary ECA Edmundson awards
Deadline for submissions Friday 30 May 2025.
The benefits of precast, off-site foundation systems
Top ten benefits of this notable innovation.
Encouraging individuals to take action saving water at home, work, and in their communities.
Takes a community to support mental health and wellbeing
The why of becoming a Mental Health Instructor explained.
Mental health awareness week 13-18 May
The theme is communities, they can provide a sense of belonging, safety, support in hard times, and a sense purpose.
Mental health support on the rise but workers still struggling
CIOB Understanding Mental Health in the Built Environment 2025 shows.
Design and construction material libraries
Material, sample, product or detail libraries a key component of any architectural design practice.
Construction Products Reform Green Paper and Consultation
Still time to respond as consultation closes on 21 May 2025.
Resilient façade systems for smog reduction in Shanghai
A technical approach using computer simulation and analysis of solar radiation, wind patterns, and ventilation.
Comments