Planning permission - how long does it take
Local planning authorities are expected to make a decision on planning applications as quickly as possible.
The statutory determination period for validated planning applications, which local planning authorities should not exceed, is 8 weeks for straight-forward planning applications, 13 weeks for unusually large or complex applications, and 16 weeks if the application is subject to an Environmental Impact Assessment (EIA).
The determination period can be extended further by agreement in writing with the applicant.
If the determination period is exceeded without agreement, the applicant can appeal to the Secretary of State, although this in itself can take some time.
Where an extension has not been agreed, the Government’s ‘planning guarantee’ commits that no application should take more than a year, including any appeal. In practice this means the applications itself should be decided in no more than 26 weeks, allowing a further 26 weeks for any appeal.
Where an extension has not been agreed, the applicant does not appeal, and the application remains undetermined after 26 weeks, the planning fee will be refunded to the applicant.
The Growth and Infrastructure Act 2013 gives the Secretary of State power to 'designate' local planning authorities if their performance in handling major planning applications is below an acceptable standard. Local planning authorities under special measures have applications determined by the planning inspectorate and lose a proportion of the application fee. Special measures designation is reviewed annually to allow improving authorities to regain their determination powers.
Delays can be caused by incomplete applications, applications that are not in an appropriate form, payment of fees, the timing of planning committee meetings, and so on. To ensure that there are no such delays, it is wise to seek pre-application advice from the local planning authority who can clarify the form of the application required and the information expected. If it is necessary for the application to be determined by the local planning committee (rather than by planning officers under delegated authority), they will be able to advise about the timing of meetings and whether the applicant might make representations to the committee.
Planning performance agreements can be prepared for complex applications, or applications where the statutory timescale is likely to be exceeded. These are voluntary undertakings that enable local planning authorities and applicants for planning permission to agree the timescales, actions and resources necessary to process a planning application. They are not intended to be legally-binding contracts, but are in the spirit of a ‘memorandum of understanding’.
The government publishes development control statistics which provide historical data about how long local authorities take to make a decision once a planning application has been submitted.
See also: How long does planning permission last.
[edit] Related articles on Designing Buildings
- Approval of conditions on a planning permission.
- Avoiding planning permission pitfalls.
- Environmental Impact assessment.
- Growth and Infrastructure Act.
- Hope value.
- How long does planning permission last.
- Local planning authority.
- Planning appeal.
- Planning appeal.
- Planning guarantee.
- Planning performance agreement.
- Planning permission.
- Pre-application advice.
- Special measures designation for under-performing planning authorities.
- The difference between planning permission building regulations approval.
- What is a housing start?
Featured articles and news
Future Homes Standard Essentials launched
Future Homes Hub launches new campaign to help the homebuilding sector prepare for the implementation of new building standards.
Building Safety recap February, 2026
Our regular run-down of key building safety related events of the month.
Planning reform: draft NPPF and industry responses.
Last chance to comment on proposed changes to the NPPF.
A Regency palace of colour and sensation. Book review.
Delayed, derailed and devalued
How the UK’s planning crisis is undermining British manufacturing.
How much does it cost to build a house?
A brief run down of key considerations from a London based practice.
The need for a National construction careers campaign
Highlighted by CIOB to cut unemployment, reduce skills gap and deliver on housing and infrastructure ambitions.
AI-Driven automation; reducing time, enhancing compliance
Sustainability; not just compliance but rethinking design, material selection, and the supply chains to support them.
Climate Resilience and Adaptation In the Built Environment
New CIOB Technical Information Sheet by Colin Booth, Professor of Smart and Sustainable Infrastructure.
Turning Enquiries into Profitable Construction Projects
Founder of Develop Coaching and author of Building Your Future; Greg Wilkes shares his insights.
IHBC Signpost: Poetry from concrete
Scotland’s fascinating historic concrete and brutalist architecture with the Engine Shed.
Demonstrating that apprenticeships work for business, people and Scotland’s economy.
Scottish parents prioritise construction and apprenticeships
CIOB data released for Scottish Apprenticeship Week shows construction as top potential career path.
From a Green to a White Paper and the proposal of a General Safety Requirement for construction products.
Creativity, conservation and craft at Barley Studio. Book review.
The challenge as PFI agreements come to an end
How construction deals with inherited assets built under long-term contracts.
Skills plan for engineering and building services
Comprehensive industry report highlights persistent skills challenges across the sector.
Choosing the right design team for a D&B Contract
An architect explains the nature and needs of working within this common procurement route.
Statement from the Interim Chief Construction Advisor
Thouria Istephan; Architect and inquiry panel member outlines ongoing work, priorities and next steps.

























Comments