Special measures designation for under-performing planning authorities
Section 62A of the Town and Country Planning Act 1990 allows certain applications to be made directly to the Secretary of State for Communities and Local Government where a local planning authority has been 'designated'.
The Growth and Infrastructure Act 2013 gave the Secretary of State power to 'designate' local planning authorities if their performance in handling major planning applications was below an acceptable standard.
Under the original provisions of the Act, local planning authorities could be designated as under-performing and placed under 'special measures' by the Secretary of State if:
- 30% or fewer of their decisions on major applications were made within the statutory determination period or such extended period agreed in writing with the applicant. The statutory period is 13 weeks, unless an application is subject to Environmental Impact Assessment, in which case it is 16 weeks. A major application is an application for 10 homes or more, or the equivalent commercial floorspace.
- More than 20% of major applications decisions were overturned on appeal.
Local planning authorities under special measures have applications determined by the planning inspectorate and lose a proportion of the application fee. Special measures designation is reviewed annually to allow improving authorities to regain their determination powers.
However, on 28 November 2014, in response to a consultation on the criteria for identifying under-performing planning authorities, the Department for Communities and Local Government (DCLG) announced its intention to raise the threshold for decisions on major applications from 30% to 40%. Ref Planning performance and planning contributions.
Then, on 24 August 2015, following publication of ‘Fixing the foundations’, the government formally revised the threshold again to 50 per cent. Ref Improving planning performance: criteria for designation. The government pointed out that up until that time, only three planning authorities had been subject to special measures and two of those had subsequently had their designation lifted.
In November 2016, the government published Improving planning performance Criteria for designation (revised 2016) Presented to Parliament pursuant to section 62B of the Town and Country Planning Act 1990. This will increase the threshold for major projects to 60% and for non-major projects of 70%, but will also introduce a quality threshold of 10%. The quality threshold relates to the percentage of the total number of decisions made by the authority on applications that are then subsequently overturned at appeal. The criteria have effect from the day following the end of the statutory 40 day period during which Parliament may consider the measures, provided neither House resolves not to approve it.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
[edit] External references
- DCLG, Improving planning performance Criteria for designation, June 2013.
- DCLG Planning performance and planning contributions 23 March 2014
Featured articles and news
Future Homes Standard Essentials launched
Future Homes Hub launches new campaign to help the homebuilding sector prepare for the implementation of new building standards.
Building Safety recap February, 2026
Our regular run-down of key building safety related events of the month.
Planning reform: draft NPPF and industry responses.
Last chance to comment on proposed changes to the NPPF.
A Regency palace of colour and sensation. Book review.
Delayed, derailed and devalued
How the UK’s planning crisis is undermining British manufacturing.
How much does it cost to build a house?
A brief run down of key considerations from a London based practice.
The need for a National construction careers campaign
Highlighted by CIOB to cut unemployment, reduce skills gap and deliver on housing and infrastructure ambitions.
AI-Driven automation; reducing time, enhancing compliance
Sustainability; not just compliance but rethinking design, material selection, and the supply chains to support them.
Climate Resilience and Adaptation In the Built Environment
New CIOB Technical Information Sheet by Colin Booth, Professor of Smart and Sustainable Infrastructure.
Turning Enquiries into Profitable Construction Projects
Founder of Develop Coaching and author of Building Your Future; Greg Wilkes shares his insights.
IHBC Signpost: Poetry from concrete
Scotland’s fascinating historic concrete and brutalist architecture with the Engine Shed.
Demonstrating that apprenticeships work for business, people and Scotland’s economy.
Scottish parents prioritise construction and apprenticeships
CIOB data released for Scottish Apprenticeship Week shows construction as top potential career path.
From a Green to a White Paper and the proposal of a General Safety Requirement for construction products.
Creativity, conservation and craft at Barley Studio. Book review.
The challenge as PFI agreements come to an end
How construction deals with inherited assets built under long-term contracts.
Skills plan for engineering and building services
Comprehensive industry report highlights persistent skills challenges across the sector.
Choosing the right design team for a D&B Contract
An architect explains the nature and needs of working within this common procurement route.
Statement from the Interim Chief Construction Advisor
Thouria Istephan; Architect and inquiry panel member outlines ongoing work, priorities and next steps.

























Comments
To start a discussion about this article, click 'Add a comment' above and add your thoughts to this discussion page.