Electrical businesses brace for project delays in 2025
The latest quarterly Building Engineering Business Survey (BEBS) has revealed that close to two thirds (63%) of electrotechnical and engineering services businesses are worried about delays to projects and the impact this can have on cashflow.
The survey, conducted by ECA in partnership with BESA, SELECT, and SNIPEF and sponsored by Scolmore, also showed that almost a quarter (23%) of respondents expect their business’ performance to have worsened by the end of this year – a figure which has risen by 7% since the last survey, in August 2024.
ECA Director of Legal and business Rob Driscoll said:
“Whilst staff shortages remain a concern, in 2025 we may see a big impact from delays to projects, which invariably leads to claims and disputes over the cost of completion and final payments.
"In a market where SMEs are paid in arrears as projects progress, business owners should focus on their resilience and ability to withstand cashflow turbulence given the propensity of clients to store disputes up until the resolution of the final account.”
The survey suggests optimism about the number of direct employees in the sector, with 16% predicting this will go up in 2025. However, the same proportion of respondents felt the numbers of apprentices would fall in 2025, most likely reflecting the decline in confidence about future trading conditions following the budget announcements of increased costs for 2025.
ECA Chief Operating Officer Andrew Eldred said:
“Businesses are facing conflicting pressures. On the one hand, business leaders are less confident about the future. On the other, long-standing concerns about workforce availability and capability remain.
"Effective dialogue and collaboration between industry, national and regional governments are more necessary than ever to sustain employer investment in skills development through uncertain times. Achievement of key policy missions such as clean energy, housing and good jobs will depend on it.”
The number of respondents reporting vacancies in their businesses rose by 10% to nearly two in five respondents (36%). Trouble filling these vacancies was primarily blamed on a lack of sufficient knowledge or skills (49%), high pay expectations (46%), and a lack of sufficient qualifications (40%).
While most survey respondents felt payment behaviour would not change by the end of Q4 2024, over 20% felt it would deteriorate. Half (49%) said that their public sector clients paid them later than 30 days after completing work, including 10% saying this took over 60 days.
Three quarters (76%) said that their private sector clients paid later than 30 days, including 16% saying this took longer than 60 days. Over 40% of respondents reported that between 2.5-10% of their turnover was currently tied up in retentions.
This article appears on the ECA news and blogsite as "Survey: Electrical businesses brace for project delays in 2025" dated 4 December, 2024.
--ECA
[edit] Related articles on Designing Buildings
- Articles by the Electrical Contractors' Association (ECA).
- BESA - the Building Engineering Services Association.
- Construction Leadership Council CLC.
- Construction Talent Retention Scheme launched.
- Coronavirus and the construction industry.
- ECA Survey: Industry remains optimistic despite downturn.
- Furlough.
- Get ready for green jobs and upgrade projects.
- Retention in construction contracts.
- Survey records business projections after coronavirus storm.
- Tackling the construction skills shortage.
- The future of the coronavirus furlough.
Featured articles and news
HSE simplified advice for installers of stone worktops
After company fined for repeatedly failing to protect workers.
Co-located with 10th year of UK Construction Week.
How orchards can influence planning and development.
Time for knapping, no time for napping
Decorative split stone square patterns in facades.
A practical guide to the use of flint in design and architecture.
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from construction and 50 percent recorded as fall from height.
Solar PV company fined for health and safety failure
Work at height not properly planned and failure to take suitable steps to prevent a fall.
The term value when assessing the viability of developments
Consultation on the compulsory purchase process, compensation reforms and potential removal of hope value.
Trees are part of the history of how places have developed.