Submittals
Contents |
[edit] Introduction
In the general sense, submittals are associated with the act of sending some type of information for consideration. Submittals are intended for studying and evaluating information to reach a decision or proceed with an action.
Submittals in construction are sometimes referred to as construction submittals. These are broadly defined as documents submitted by the responsible supplier to the appropriate design professional fto obtain approvals.
[edit] Purpose of submittals
There are submittals that can take place during preconstruction, construction and maintenance of a built asset.
Information for submittals is generally provided by subcontractors and suppliers to the main contractor who then presents this information to the designated recipient (whether that be the designer, architect, engineer or some other person tasked with granting approvals). The intention of this process is to ensure that properly specified items (and quantities of items) are delivered to the project.
[edit] Types of submittals
The information presented in a submittal can be provided in several different forms including things such as meeting minutes. However, the most commonly requested submittals are provided both in written format (as shop drawings and product data) and as physical objects (as product and material samples).
[edit] Shop drawings
Shop drawings, blueprints, diagrams and schedules generally relate to pre-fabricated components, showing how they should be manufactured or installed. They take design intent drawings and specifications prepared by the project design team and develop them to show in detail how the component will actually be manufactured, fabricated, assembled or installed.
They may be reviewed by the project design team prior to fabrication to verify that they comply with design drawings and specifications and to ensure that different packages of work and components are properly coordinated. This means that they need to contain relevant information to enable this to be done, which might include the provision of samples for approval.
For more information, see Shop drawings.
[edit] Product data
Product data (such as technical data, test data and operations and maintenance data) is information including things such as dimensions, materials and characteristics, about products and materials that may be used on the project. This can be used to confirm whether the product will meet the requirements of the project.
Product data may be provided in the form of product data sheets that summarise the performance and other technical characteristics of a product, material or component according to specific regulatory, market or client-specific requirements.
For more information, see Product Data Sheet.
Product data may also be included in cut sheets on equipment, warranty and manual documentation.
[edit] Product and material samples and mock-ups
Product and material samples and mock-ups have become more common requirements on construction projects as the number and complexity of goods and materials that are available and that are required for a single project has increased.
Product samples might include simple items such as paint, tiles, bricks or carpets. In some instances, a sample of a certain type of material in the fabrication process may be offered to designers to evaluate before a final decision is made on its suitability for the project.
Mock-ups are scaled-down or full-size assemblies, such as sections of cladding, window assemblies, masonry and so on.
For more information, see Samples and mock-ups for construction.
[edit] Steps in the submittal process
These kinds of submittals - sometimes referred to as action submittals - generally require some type of response. This may come in the form of an approval, a request for revision and resubmission or a rejection.
Once approved, the submittal will then release the authorised materials for production and delivery.
Timing of submittals should take into consideration several key aspects, including:
- Preconstruction. The submittal process should be clarified during preconstruction meetings.
- Scheduling. A submittal schedule should be defeined early in the project to keep everything - and everyone - on track.
- Preparation. Gathering documentation for the submittal process can take a significant amount of time.
- Review. This process will be handled by the decision makers who will be looking at the submittal samples and documentation to determine how the components will impact each other. Again, this can take time and this should be factored into the project programme.
If handled effectively, submittals can become part of the permanent record of the project. This can be used by facilities and operations professionals who are responsible for the management of the project once completed.
[edit] Related articles on Designing Buildings
Featured articles and news
Guide to ISO 19650 for Architecture Firms (2026)
A user gives their low down.
A UK training and membership provider for mould remediation professionals.
Building Safety recap April, 2026
A short and longer run-through of the month, with links to further information and sources.
CIAT May 2026 briefing.
Independent NSI and BAFE study exploring how organisations are changing the way they buy fire safety services.
From medieval scribes to modern word art.
ECA welcomes crackdown on late payment and push for clean energy, whilst CIOB seek fixed cladding removal timeframes.
Cyber Security in the Built Environment
Protecting projects, data, and digital assets: A CIOB Academy TIS.
Managing competence in the built environment
ITFG publishes new industry guide on how to meet the ICC principles.
The UK's campaign to reduce noise pollution: Mythbusting, articles and topic guides.
Setting Expectations on Competence Management
Industry Competence Committee.
New Scottish and Welsh governments
CIOB stresses importance of construction after new parliament elections.
The sad story of Derby Hippodrome
An historic building left to decay.
ECA, JIB and JTL back Fabian Society call to invest in skills for a stronger built environment workforce.
Women's Contributions to the Built Environment.
Calls for the delayed Circular Economy Strategy
Over 50 leading businesses, trade associations and professional bodies, including CIAT, and UKGBC sign open letter.
The future workforce: culture change and skill
Under the spotlight at UK Construction Week London.
A landmark moment for postmodern heritage.























