Submittals
Contents |
[edit] Introduction
In the general sense, submittals are associated with the act of sending some type of information for consideration. Submittals are intended for studying and evaluating information to reach a decision or proceed with an action.
Submittals in construction are sometimes referred to as construction submittals. These are broadly defined as documents submitted by the responsible supplier to the appropriate design professional fto obtain approvals.
[edit] Purpose of submittals
There are submittals that can take place during preconstruction, construction and maintenance of a built asset.
Information for submittals is generally provided by subcontractors and suppliers to the main contractor who then presents this information to the designated recipient (whether that be the designer, architect, engineer or some other person tasked with granting approvals). The intention of this process is to ensure that properly specified items (and quantities of items) are delivered to the project.
[edit] Types of submittals
The information presented in a submittal can be provided in several different forms including things such as meeting minutes. However, the most commonly requested submittals are provided both in written format (as shop drawings and product data) and as physical objects (as product and material samples).
[edit] Shop drawings
Shop drawings, blueprints, diagrams and schedules generally relate to pre-fabricated components, showing how they should be manufactured or installed. They take design intent drawings and specifications prepared by the project design team and develop them to show in detail how the component will actually be manufactured, fabricated, assembled or installed.
They may be reviewed by the project design team prior to fabrication to verify that they comply with design drawings and specifications and to ensure that different packages of work and components are properly coordinated. This means that they need to contain relevant information to enable this to be done, which might include the provision of samples for approval.
For more information, see Shop drawings.
[edit] Product data
Product data (such as technical data, test data and operations and maintenance data) is information including things such as dimensions, materials and characteristics, about products and materials that may be used on the project. This can be used to confirm whether the product will meet the requirements of the project.
Product data may be provided in the form of product data sheets that summarise the performance and other technical characteristics of a product, material or component according to specific regulatory, market or client-specific requirements.
For more information, see Product Data Sheet.
Product data may also be included in cut sheets on equipment, warranty and manual documentation.
[edit] Product and material samples and mock-ups
Product and material samples and mock-ups have become more common requirements on construction projects as the number and complexity of goods and materials that are available and that are required for a single project has increased.
Product samples might include simple items such as paint, tiles, bricks or carpets. In some instances, a sample of a certain type of material in the fabrication process may be offered to designers to evaluate before a final decision is made on its suitability for the project.
Mock-ups are scaled-down or full-size assemblies, such as sections of cladding, window assemblies, masonry and so on.
For more information, see Samples and mock-ups for construction.
[edit] Steps in the submittal process
These kinds of submittals - sometimes referred to as action submittals - generally require some type of response. This may come in the form of an approval, a request for revision and resubmission or a rejection.
Once approved, the submittal will then release the authorised materials for production and delivery.
Timing of submittals should take into consideration several key aspects, including:
- Preconstruction. The submittal process should be clarified during preconstruction meetings.
- Scheduling. A submittal schedule should be defeined early in the project to keep everything - and everyone - on track.
- Preparation. Gathering documentation for the submittal process can take a significant amount of time.
- Review. This process will be handled by the decision makers who will be looking at the submittal samples and documentation to determine how the components will impact each other. Again, this can take time and this should be factored into the project programme.
If handled effectively, submittals can become part of the permanent record of the project. This can be used by facilities and operations professionals who are responsible for the management of the project once completed.
[edit] Related articles on Designing Buildings
Featured articles and news
Level 6 Design, Construction and Management BSc
CIOB launches first-ever degree programme to develop the next generation of construction leaders.
Open for business as of April, with its 2026 prospectus and new pipeline of housing schemes.
The operational value of workforce health
Keeping projects moving. ECA on better incorporation of unplanned absence and the importance of health in operations.
A carbon case for indigenous slate
UK slate can offer clear embodied carbon advantages.
Costs and insolvencies mount for SMEs, despite growth
Construction sector under insolvency and wage bill pressure in part linked to National Insurance, says report.
The place for vitrified clay pipes in modern infrastructure
Why vitrified clay pipes are reclaiming their role in built projects.
Research by construction PR consultancy LMC published.
Roles and responsibilities of domestic clients
ACA Safety in Construction guide for domestic clients.
Fire door compliance in UK commercial buildings
Architect and manufacturer gives their low down.
Plumbing and heating for sustainability in new properties
Technical Engineer runs through changes in regulations, innovations in materials, and product systems.
Awareness of the Carbon Border Adjustment Mechanism
What CBAM is and what to do about it.
The new towns and strategic environmental assessments
12 locations of the New Towns Taskforce reduced to 7 within the new towns draft programme and open consultation.
Buildings that changed the future of architecture. Book review.
The Sustainability Pathfinder© Handbook
Built environment agency launches free Pathfinder© tool to help businesses progress sustainability strategies.
Government outcome to the late payment consultation, ECA reacts.
IHBC 2025 Gus Astley Student Award winners
Work on the role of hewing in UK historic conservation a win for Jack Parker of Oxford Brookes University.






















