Reliance data in EPC contracts
The starting point of many engineering procurement and construction (EPC) tenders and contract negotiations is as follows: the owner/employer provides the contractor with the data they have in their possession regarding the project together with a specific statement that 'the employer does not give any warranty as to the completeness, accuracy or fitness for purpose' of that information.
They do this to avoid any claim by the contractor during the project execution on the basis that the provided information is inaccurate or incorrect. Sometimes the situation is even worse and the owner/employer simply tries to avoid giving any information.
In practice, withholding information is counterproductive as it does not enable the EPC contractor to quote properly, with reasonable efforts. Contractors may walk away from the tender, overprice or underestimate the project’s cost. In the latter case, contractors often create trouble during the execution phase in an attempt to limit their losses.
FIDIC 1999 Silver Book (Clause 5.1) requires the contractor to scrutinise the employer’s requirements prior to the bid submittal. The employer shall not be responsible for any error, inaccuracy or omission of any kind in the employer’s requirements except for data and information which are stated as immutable or the responsibility of the employer and also except for data and information which cannot be verified by the contractor. Having some data on which the contractor may rely (reliance data) is therefore good industry practice and in line with the contract standards.
The difficulty starts when identifying precisely the 'reliance data', 'baseline data' or whatever word is defined in the contract to introduce the same concept. The data is usually parked in an appendix containing a limited list of data for which the employer takes responsibility. An objective methodology to establish 'reliance data' is to look at the project (to be executed) as a 'black box':
- Whatever is in the box are the works to be executed. These are defined in a functional, not detailed, not prescriptive specification. The reliance data should not include any information from within the project 'black box'.
- The project 'black box' is somehow connected to, and interacting with, its surroundings/environment. It is physically attached to/founded on the outside world. It also receives some inflow. The 'black box' can be impacted/shaken-up by the outside environment. The quality, magnitude and characteristics of these foundations, inflows, connections and impacts are data that can, and often should, become reliance data.
In case of building a hydro power plant for example, the following can be reliance data:
- Geo-technical baseline data: reference characteristics of subsurface conditions like rock classes ('foundations').
- Water quality: chemical composition of water quality for which the penstocks and turbine equipment should be designed; maximum water temperature to be taken into consideration for the design of the cooling system; hydrological data ('inflow').
- Grid connection information: data related to the transmission line and grid characteristics (voltage, frequency). The electric grid often still has to be expanded under a separate contract ('connections').
- Maximum wind speed or seismic acceleration coefficient: design requirements that the 'black box' will have to withstand ('impacts').
Some concept of reliance data is healthy for a balanced EPC contract. It is necessary to minimise the information to those design inputs that are essential and cannot reasonably be verified by the contractor during the tender stage. This includes information that is the result of long-term data series or unaccessible or needing unreasonable efforts and resources to obtain during the tender stage (when the contractor is not sure to be awarded the contract).
--JFJ Afitac 18:29, 03 Jun 2018 (BST)
[edit] Related articles on Designing Buildings
Featured articles and news
Professional practical experience for Architects in training
The long process to transform the nature of education and professional practical experience in the Architecture profession following recent reports.
A people-first approach to retrofit
Moving away from the destructive paradigm of fabric-first.
International Electrician Day, 10 June 2025
Celebrating the role of electrical engineers from André-Marie Amperè, today and for the future.
New guide for clients launched at Houses of Parliament
'There has never been a more important time for clients to step up and ...ask the right questions'
The impact of recycled slate tiles
Innovation across the decades.
EPC changes for existing buildings
Changes and their context as the new RdSAP methodology comes into use from 15 June.
Skills England publishes Sector skills needs assessments
Priority areas relating to the built environment highlighted and described in brief.
BSRIA HVAC Market Watch - May 2025 Edition
Heat Pump Market Outlook: Policy, Performance & Refrigerant Trends for 2025–2028.
Committing to EDI in construction with CIOB
Built Environment professional bodies deepen commitment to EDI with two new signatories: CIAT and CICES.
Government Grenfell progress report at a glance
Line by line recomendation overview, with links to more details.
An engaging and lively review of his professional life.
Sustainable heating for listed buildings
A problem that needs to be approached intelligently.
50th Golden anniversary ECA Edmundson apprentice award
Deadline for entries has been extended to Friday 27 June, so don't miss out!
CIAT at the London Festival of Architecture
Designing for Everyone: Breaking Barriers in Inclusive Architecture.
Mixed reactions to apprenticeship and skills reform 2025
A 'welcome shift' for some and a 'backwards step' for others.