Construction consolidation centre CCC
Contents |
[edit] Introduction
A construction consolidation centre (CCC) is a distribution facility that can be used in the process of managing project logistics, channelling material deliveries to a large, single construction site or a number of different sites. It facilitates the efficient flow of materials through the supply chain, reducing waste and other issues such as congestion.
Construction materials are delivered from suppliers to the CCC where they are stored until call-off from the site, at which point the CCC operator makes up and delivers a consolidated load. This is done on a ‘just in time’ basis, for enhanced efficiency.
Usually, the main contractor takes the decision to use a CCC and so carries the cost. However, subcontractors, suppliers and hauliers all see the benefit and so there can be an effort to spread the costs.
While distribution centres have been commonly used in other sectors in the UK, currently there are only a few examples of CCCs. The Heathrow Consolidation Centre (HCC) was established in 2001 for the ongoing work at Heathrow airport. In 2005, the London Construction Consolidation Centre (LCCC) was set up as a pilot study. Subsequently, Wilson James took over the LCCC and relocated it to Silvertown, near City Airport. The house builder Taylor Wimpey has set up Taylor Wimpey Logistics which consolidates materials in a Newmarket facility that then provides for its sites across England and Wales.
[edit] Specifications
[edit] Project size
The use of a CCC is not necessarily dependent on the size of a project, but rather whether there is an ongoing business volume to make it worthwhile. Shared user CCCs can be an option as opposed to single users, which allows the operating costs to be spread between users.
[edit] Location
As a general rule, CCCs are located close to a motorway or major road network. This is so that the impact on local roads is kept to a minimum and to minimise the turnaround times of hauliers.
Sometimes a CCC is situated where several different sites can be reached in 30-45 minutes, but it can be more sensible, if there are a reasonable number of sites, to have two smaller CCCs, each of which are closer to the respective sites, than one large CCC.
[edit] Advantages
There are several advantages associated with using CCCs. Studies looking into their general impact have found:
- Up to 70% reduction in freight traffic to site.
- A 6% productivity gain based on increased workforce productivity of 30 minutes per day.
- A 7-15% reduction in waste.
- More efficient utilisation of delivery vehicles.
- Reduced carbon emissions and traffic congestion.
- Noise and pollution reductions.
- Reverse logistics means that journeys from the site can be used for waste removal, return of unused materials, and so on.
- Cost savings associated with fewer and more efficient vehicle journeys.
- Improved programme certainty.
- Better storage facilities than are often available on site.
- Excess packaging can be removed at the CCC rather than creating clutter on site.
- Materials delivery can be sequenced.
- Manufacturer errors or damage can be detected at the CCC rather than when delivered to site.
[edit] Related articles on Designing Buildings
- Circular economy.
- Construction logistics manager.
- Design for Manufacture and Assembly (DfMA).
- Forklift.
- Lean construction.
- Logistics management.
- Materials on site.
- Mean lean green.
- Off site materials.
- Site storage.
- Site Waste Management Plan.
- Waste and Resources Action Plan WRAP.
- Warehouse.
[edit] External resources
Featured articles and news
A case study and a warning to would-be developers
Creating four dwellings... after half a century of doing this job, why, oh why, is it so difficult?
Reform of the fire engineering profession
Fire Engineers Advisory Panel: Authoritative Statement, reactions and next steps.
Restoration and renewal of the Palace of Westminster
A complex project of cultural significance from full decant to EMI, opportunities and a potential a way forward.
Apprenticeships and the responsibility we share
Perspectives from the CIOB President as National Apprentice Week comes to a close.
The first line of defence against rain, wind and snow.
Building Safety recap January, 2026
What we missed at the end of last year, and at the start of this...
National Apprenticeship Week 2026, 9-15 Feb
Shining a light on the positive impacts for businesses, their apprentices and the wider economy alike.
Applications and benefits of acoustic flooring
From commercial to retail.
From solid to sprung and ribbed to raised.
Strengthening industry collaboration in Hong Kong
Hong Kong Institute of Construction and The Chartered Institute of Building sign Memorandum of Understanding.
A detailed description from the experts at Cornish Lime.
IHBC planning for growth with corporate plan development
Grow with the Institute by volunteering and CP25 consultation.
Connecting ambition and action for designers and specifiers.
Electrical skills gap deepens as apprenticeship starts fall despite surging demand says ECA.
Built environment bodies deepen joint action on EDI
B.E.Inclusive initiative agree next phase of joint equity, diversity and inclusion (EDI) action plan.
Recognising culture as key to sustainable economic growth
Creative UK Provocation paper: Culture as Growth Infrastructure.