Construction management: appointing the construction manager
Construction management is a procurement route in which the works are constructed by a number of different trade contractors who are managed by a construction manager but are contracted to the client. The construction manager is generally appointed early in the design process so their experience can be used to improve the cost and buildability of proposals as they develop as well as to advise on packaging and the selection of trade contractors. Within this plan we suggest the construction manager is appointed on completion of concept design. Earlier or later appointment might result in some activities being re-allocated between the consultant team and the construction manager (for example the role of cost consultant).
The construction manager might be an individual with limited responsibilities, or could be a large organisation taking full responsibility for cost planning, packaging and tendering trade contracts as well as managing construction. For a description of the services a construction manager might offer, see: Construction management.
Contents |
[edit] Agreeing the procedure that will be adopted
The client may decide that they require advice from independent client advisers or member of the consultant team to help them make the appointment. If this requires a new appointment, go to the work stage: Construction management: appointment .
The client determines the selection procedure that will be adopted. This might be a process of recommendation, research and interview, open competition, selective competition, or an existing relationship such as a framework agreement.
The client may have to follow a pre-determined procedure if; there are in-house rules governing appointments, if they are a local authority or other public body, or if the project will be publicly funded. Such procedures may include assessing whether OJEU procurement rules are likely to apply which can cause significant delays unless implemented early in the project.
[edit] Agreeing the nature of appointment required.
The client should agree the wording of any adverts that are required (such as OJEU adverts) and if appropriate prepare a pre-qualification questionnaire.
The client should prepare documents describing the nature of the development (if the construction manager is appointed very early in the project, this might simply be the strategic brief, whereas if they are appointed later, it could include the project brief and concept design).
The client should define the schedule of services that will be required (pre-construction and construction services), selection criteria, form of agreement and contract terms for the appointment.
Construction managers are likely to be paid based on reimbursable costs (such as site facilities, staff costs, statutory fees, offices and so on) and a management fee, comprising pre-construction and construction fees, which may be fixed, or calculated based on an agreed formula. It is important to establish what is included in the construction manager's price (for example insurance requirements or payment of statutory fees) and to agree the limit of the construction managers delegated authority in issuing instructions which affect the cost of the project. As construction managers tend to be appointed early in the project, their appointment is unlikely to include a completion date. Construction managers may be required to hold professional indemnity insurance and to provide collateral warranties for tenants, purchasers or funders. There is merit in incentivising the construction manager to achieve key performance objectives set by the client. Any such mechanism should be clearly set out in the appointment contract.
The client should agree the form of proposal that will be requested from candidates.
The client prepares the construction management appointment documents. These are likely to include: the construction manager's appointment; the trade contract; the construction manager's warranties (eg purchasers, tenants or funders) and the trade contractor's warranties (eg purchasers, tenants or funders).
The client prepares a formal request for proposals.
[edit] Preparing a list of possible candidates.
The client prepares a long list of possible candidates, either from recommendations, existing relationships or expressions of interest received in response to adverts.
The candidates may be required to complete a pre-qualification questionnaire, or there may be some other assessment procedure (such as interviews) that results in the preparation of a short list that will be invited to submit proposals. Such assessments may include assessing experience and capability, checking professional indemnity insurance, assessing CDM competence and BIM competence, checking references and so on.
The client should put in place procedures for responding to queries from candidates.
Short-listed candidates are invited to submit proposals in response to the client's request for proposals.
[edit] Selecting the preferred candidate and making the appointment.
The client collates responses to queries from candidates and issues these responses to all candidates.
The client receives and opens the candidates' proposals and makes a record of the fee proposals of each candidate. In some circumstances, fee proposals may be submitted in a sealed envelope and opened separately from the rest of the proposals so that the assessment procedure is not initially prejudiced by the fee (which it may be possible to negotiate down).
The client assesses the candidates' proposals (including the personnel the construction manager will use on the project). The client may seek advice from existing consultants or independent client advisers.
The client invites the candidates to interview, identifies the preferred candidate(s) and opens negotiations with the preferred candidate(s).
The client appoints the selected candidate and arranges a start-up meeting with the construction manager and the consultant team.
The client informs other candidates that they have been unsuccessful. It is best practice to give clearly thought-out, specific feedback to unsuccessful candidates as they have take the time to prepare proposals often for no fee. Candidates greatly appreciate this feedback and will be more likely to express interest in future projects.
Featured articles and news
Boiler Upgrade Scheme and certifications consultation
Summary of government consultation which closes 11 June 2025.
Deputy editor of AT, Tim Fraser, discusses the newly formed society with its current chair, Chris Halligan MCIAT.
Barratt Lo-E passivhaus standard homes planned enmasse
With an initial 728 Lo-E homes across two sites and many more planned for the future.
Government urged to uphold Warm Homes commitment
ECA and industry bodies write to Government concerning its 13.2 billion Warm Homes manifesto commitment.
Places of Worship in Britain and Ireland, 1929-1990. Book review.
The emancipation of women in art.
CIOB Construction Manager of the Year 2025
Just one of the winners at the CIOB Awards 2025.
Call for independent National Grenfell oversight mechanism
MHCLG share findings of Building Safety Inquiry in letter to Secretary of State and Minister for Building Safety.
The Architectural Technology Awards
AT Awards now open for this the sixth decade of CIAT.
50th Golden anniversary ECA Edmundson awards
Deadline for submissions Friday 30 May 2025.
The benefits of precast, off-site foundation systems
Top ten benefits of this notable innovation.
Encouraging individuals to take action saving water at home, work, and in their communities.
Takes a community to support mental health and wellbeing
The why of becoming a Mental Health Instructor explained.
Mental health awareness week 13-18 May
The theme is communities, they can provide a sense of belonging, safety, support in hard times, and a sense purpose.
Mental health support on the rise but workers still struggling
CIOB Understanding Mental Health in the Built Environment 2025 shows.
Design and construction material libraries
Material, sample, product or detail libraries a key component of any architectural design practice.
Construction Products Reform Green Paper and Consultation
Still time to respond as consultation closes on 21 May 2025.
Resilient façade systems for smog reduction in Shanghai
A technical approach using computer simulation and analysis of solar radiation, wind patterns, and ventilation.