Buildability in construction
![]() |
Buildability is a pre-construction exercise that assesses designs from the perspective of those that will manufacture, install components and carry out the construction works. It should not be confused with value engineering (which is used to solve problems and identify and eliminate unwanted costs) though some processes are common to both activities.
In very broad terms, buildability should assess elements of the design in relation to:
- Achieving the desired final quality;
- Meeting the programme requirements;
- De-risking perceived problems, and
- Achieving optimum value for money.
Buildability involves careful study and consideration of:
- The sequence of activities that will take place on- and off-site, taking into account the state of the building and its weatherproof environment at any time;
- Dimensional criteria, setting out and space allowances;
- Use of plant and equipment to save labour and time and prevent possible damage;
- Practicality, flexibility and tolerances;
- Standardisation of components and processes;
- Reduction in complexity to shorten learning curves;
- Identification of appropriate suppliers;
- Prefabrication opportunities;
- Packaging the works and allocation of scope in relation to trade and specialist contracts;
- Ease and order of interface connections and abutments;
- Installation and maintenance access arrangements including long-term replacement;
- Health and safety;
- Temporary works such as propping, facade retention, retaining facilities and trench support, crane supports, formwork, falsework and scaffolding, including gantries;
- Susceptibility to damage and protective procedures in-transit and in-situ;
- Weight and lifting requirements;
- Unloading operations;
- Spare parts, and
- Storage and waste management.
Advances in computer-aided design (CAD) and computer-aided manufacturing (CAM) as well as the introduction of building information modelling (BIM) are immensely helpful in visualising many aspects of buildability. However, the availability of technology does not remove the need for engaging practitioners who have hard-won experience and awareness of on-site practicalities and potential pitfalls.
The contractor is often best placed to advise on issues of buildability. And some procurement methods, such as construction management, management contracting and design and build allow early appointment of the contractor to offer advice and feedback on design proposals as they develop.
[edit] Related articles on Designing Buildings Wiki
- CDM.
- CDM planning period.
- Construction manager.
- Construction phase plan.
- Construction strategy.
- Design and build.
- Management contractor.
- Method statements.
- Modular building.
- Offsite manufacturing.
- Packaging.
- Pre-construction information.
- Prefabrication.
- Samples and mock-ups.
- Site layout plan.
- Site Waste Management Plan.
- Structural systems for offices.
- Temporary works.
- Tolerances.
- Value management.
Featured articles and news
Landownership in England in 1909
A national valuation to fund old-age pensions.
The world’s largest Commonwealth memorial to the missing.
Long after the end of the defects liability period.
BSRIA Occupant Wellbeing survey BOW
Occupant satisfaction and wellbeing in buildings.
Geometric form and buildings in brief
From the simple to the complex.
Understanding the changing nature of insulation
And the UK Government guidelines.
Three year action plan to improve equity, diversity and inclusion
Commitment agreed to by major built environment bodies.
The Construction Route – what needs to change?
Electrical skills, low carbon, high-tech and the building services revolution.
Deep geothermal power possibilities
Ultra-deep drilling with millimeter-wave beam technology.
BSRIA Briefing 2022- From the outside looking in
Looking at the built environment from space.
Competence requirements for principal contractors and designers
BSI standards 8671, 8672 and 8673.
Bringing life to burial grounds.
From failed modernism to twenty-minute neighbourhoods.
Design chill and design freeze
The gates process and change control.
Neuroscience for project success
Why people behave as they do. APM book.
Comments
To start a discussion about this article, click 'Add a comment' above and add your thoughts to this discussion page.