Why the lowest price isn't sustainable
Contents |
[edit] Introduction
The Institute of Chartered Accountants in England and Wales (ICAEW) warned in its Audit Insight report into construction earlier this year that the ‘race to the bottom’ in construction contracting could lead to more major firms collapsing. It will also damage their supply chains, forcing more smaller firms out of business.
In preparing its report, ICAEW collaborated with auditors with many years' experience of independently examining and auditing construction firms. These included KPMG, PwC, EY, Deloitte and The Orange Partnership.
The construction sector is a key driver of growth for the UK economy, but it is a fragile one with low margins and high risks.
When construction companies and clients get it right − through project selection based on their ability to deliver, responsible tendering, diligent monitoring, and a proactive attitude to deal with issues such as cost and timetable overruns – they create contracts that are more profitable and provide more enduring value.
The report examines four key areas that need to be addressed by construction firms if they are to run sound, well-managed businesses.
[edit] Bidding for lasting value
If construction businesses want to generate sustainable profits, they need to get the price right at the tendering stage.
Some companies have become better at pricing their services realistically to reflect their true cost. But we are also seeing businesses bidding at too low a price for large complex contracts in the expectation that they will improve their profit margins because some aspect of the project will change. This is a risky strategy as unforeseen changes can quickly turn small profits into losses, and make it difficult to return to profitability.
[edit] Delivering for success
In construction, it is especially important that financial rigour is applied to key estimates and judgements throughout a project’s lifecycle. Competition is so fierce and margins so thin that reliable financial information and analysis can determine a project’s success. One way to achieve this objective is to form strong delivery teams where project managers work closely with finance and commercial teams. We do not see enough evidence of this in practice and urge firms to remedy any lack of collaboration.
[edit] Increasing transparency
The UK construction sector continues to suffer from a reputation that it lacks enough transparency, particularly on cost and performance. In many cases, poor or unexpected results are caused by a lack of internal transparency.
Executive management and boards need to ensure the tone from the top encourages and supports employees early reporting when problems occur. Without early reporting, projects are less likely to remain on track and management may be unaware of a problem until it becomes significant.
[edit] Getting fit for the future
The highly fragmented nature of the sector and lack of training and innovation have been contributing to low productivity. Government can help to build confidence in the construction sector by showing more ambition and urgency in facilitating a commitment to a reliable pipeline of major infrastructure projects with guaranteed timings.
Businesses need to form partnerships with their local schools, colleges and universities to educate young men and women about the wide range of career opportunities available, creating a pipeline of future young talent.The stereotype of the hard hat-wearing construction worker needs to be retired and replaced with the image of the planner, architect, surveyor, engineer and skilled trades person.
[edit] About this article
This article was written by ice.org.uk Phil Joyce, The Orange Partnership and is based on the author's briefing article in the 172 CE4 issue of the ICE Civil Engineering Journal. The article previously appeared on the ICE website in October 2019 and can be accessed HERE.
More articles by ICA on Designing Buildings Wiki can be accessed HERE.
[edit] Related articles on Designing Buildings Wiki
- Auction theory.
- Best value.
- Bid writer.
- Competitive tender.
- E-tendering.
- Estimator.
- Form of tender.
- Game theory.
- Initial cost appraisal.
- Invitation to tender.
- Pre-tender estimate.
- Procurement route.
- Relationship management.
- Tender documentation.
- Tender evaluation.
- Tender process.
- Winning work in the construction industry.
- Zone of possible agreement.
Featured articles and news
The first line of defence against rain, wind and snow.
Building Safety recap January, 2026
What we missed at the end of last year, and at the start of this...
National Apprenticeship Week 2026, 9-15 Feb
Shining a light on the positive impacts for businesses, their apprentices and the wider economy alike.
Applications and benefits of acoustic flooring
From commercial to retail.
From solid to sprung and ribbed to raised.
Strengthening industry collaboration in Hong Kong
Hong Kong Institute of Construction and The Chartered Institute of Building sign Memorandum of Understanding.
A detailed description from the experts at Cornish Lime.
IHBC planning for growth with corporate plan development
Grow with the Institute by volunteering and CP25 consultation.
Connecting ambition and action for designers and specifiers.
Electrical skills gap deepens as apprenticeship starts fall despite surging demand says ECA.
Built environment bodies deepen joint action on EDI
B.E.Inclusive initiative agree next phase of joint equity, diversity and inclusion (EDI) action plan.
Recognising culture as key to sustainable economic growth
Creative UK Provocation paper: Culture as Growth Infrastructure.
Futurebuild and UK Construction Week London Unite
Creating the UK’s Built Environment Super Event and over 25 other key partnerships.
Welsh and Scottish 2026 elections
Manifestos for the built environment for upcoming same May day elections.
Advancing BIM education with a competency framework
“We don’t need people who can just draw in 3D. We need people who can think in data.”























Comments
Specifying sustainable requirements.
Designers determine quality and sustainability initially through their specifications. The most efficient contractor at fulfilling those specifications exactly delivers the best value and is also the most sustainable. So, least cost equates to best value if the designers specify correctly.