Utilities' connections
Water, gas, electricity, sewerage and telecommunications are collectively referred to as utilities. Utilities’ connections are those points at which incoming utilities are connected to allow them to serve a user, whether in a house, apartment, commercial or other property.
Services such as water, electricity and gas typically enter a building below ground; those leaving a building (such as drainage) typically either pass through a wall below ground or through the foundation itself if it is of the vertical strip variety. It is therefore important at the design stage to ensure provision is made for these pass-through points eg using precast concrete lintels or brick arches over openings in walls and so on. The process can be simplified if the service pipe can be positioned as the below-ground wall is being built. When passing through foundations, these service supply pipe openings must be formed at the precise locations before concreting takes place, either by using open-ended timber boxes or plastic pipe.
Connection points vary depending on the utility in question. Water connections between supplier and user tend to be close to the boundary of the property. The water company’s stop valve (or stop cock) is usually located on the site perimeter and is connected to the stop valve located within the property and accessible by the customer. From here, the rising main serves the building’s drinking, heating and other facilities and cold-water storage tank (if there is one).
Gas and electricity connections tend to be inside the property at accessible points: the first point of connection for both gas and electricity will be at their respective meter which will be in a position that allows easy reading, both by the user and by utility personnel.
To avoid the risk of explosion, fire and electrocution, electrical services should be well separated from gas and water services. Gas and electricity should not enter the building through the same duct.
The infrastructure necessary to supply utilities may be provided by the network operator, or increasingly, by an independent provider (to an agreed design that is then ‘adopted’ by the network operator). Installing connecting pipes and cabling from the respective gas and electricity metres is usually undertaken by specialist subcontractors and should be carried out before the building’s finishes are applied. Once installed, gas and electrical services should be inspected by representatives of the respective utilities to ensure the work complies with requirements.
In a bid to ensure ongoing safety and efficiency, public utility service organisations may periodically check for possible damage to existing installations.
[edit] Related articles on Designing Buildings Wiki
- Building services.
- Electrical control systems.
- External works.
- Renewable energy.
- Statutory undertakers.
- Sustainable urban drainage systems.
- Third party dependencies.
- Types of building services.
- Utilities.
- Utilities cost.
- Water conservation.
[edit] External references
Featured articles and news
Reform of the fire engineering profession
Fire Engineers Advisory Panel: Authoritative Statement, reactions and next steps.
Restoration and renewal of the Palace of Westminster
A complex project of cultural significance from full decant to EMI, opportunities and a potential a way forward.
Apprenticeships and the responsibility we share
Perspectives from the CIOB President as National Apprentice Week comes to a close.
The first line of defence against rain, wind and snow.
Building Safety recap January, 2026
What we missed at the end of last year, and at the start of this...
National Apprenticeship Week 2026, 9-15 Feb
Shining a light on the positive impacts for businesses, their apprentices and the wider economy alike.
Applications and benefits of acoustic flooring
From commercial to retail.
From solid to sprung and ribbed to raised.
Strengthening industry collaboration in Hong Kong
Hong Kong Institute of Construction and The Chartered Institute of Building sign Memorandum of Understanding.
A detailed description from the experts at Cornish Lime.
IHBC planning for growth with corporate plan development
Grow with the Institute by volunteering and CP25 consultation.
Connecting ambition and action for designers and specifiers.
Electrical skills gap deepens as apprenticeship starts fall despite surging demand says ECA.
Built environment bodies deepen joint action on EDI
B.E.Inclusive initiative agree next phase of joint equity, diversity and inclusion (EDI) action plan.
Recognising culture as key to sustainable economic growth
Creative UK Provocation paper: Culture as Growth Infrastructure.
Futurebuild and UK Construction Week London Unite
Creating the UK’s Built Environment Super Event and over 25 other key partnerships.
Welsh and Scottish 2026 elections
Manifestos for the built environment for upcoming same May day elections.
Advancing BIM education with a competency framework
“We don’t need people who can just draw in 3D. We need people who can think in data.”