Scaffolding provides a temporary, safe working platform for activities such as:
It is formed from individual tubes and joints or, proprietary components. For more information, see: Scaffolding.
High-quality workmanship and careful inspection is vital for the erection and dismantling of scaffolding, which must be undertaken by competent personal under supervision. For more information, see: Scaffold register.
Construction workers sometimes rush when dismantling scaffolding in an effort to finish on site quickly, involving workers without adequate training, and proceeding during unsuitable conditions. But the safe and efficient dismantling of scaffolding demands as much training and careful consideration as its erection. Unless it is unavoidable, scaffolding should not be taken down in potentially hazardous conditions such as high winds, rain, snow, and so on.
The first step in the dismantling process is to clear a space where the scaffolding components can be set down and stacked in an organised and safe manner. Access for a vehicle to transport the components to a loading area should be provided wherever possible with a clear path to carry them from the structure.
Workers should have all the necessary personal protective equipment (PPE), including safety boots, hard hats, gloves and protective eyewear to guard against the risk of falling materials. When on the scaffold itself, safety harnesses may be necessary. Particualr care should be taken, as during the course of the scaffold being used, edges can become sharp and pose risks to those dismantling.
The scaffold structure should then be examined from the base to the top for any visible hazards, loose items on the working platforms, or hung items on the piping. Ties, braces or timber that has been loosened or removed should be put back in place before dismantling begins.
The process of dismantling proceeds in the reverse order of erection, beginning at the top with the piping and guardrail before proceeding to the platform planking. The components can be passed down from person-to-person, or lowered to the ground using a rope system or hoist. They should not be stacked or left on the structure temporarily but brought to the ground straight away. Care should be taken to ensure that no one is stood directly below where the components are being dismantled, and they should never be thrown off the structure to the ground.
Part of the platform planking will need to be removed while still being used, and the remainder removed from the section beneath. Only once the entire platform being supported has been removed should the ties securing the structure to the building be removed.
The scaffolding components should be inspected when they have been dismantled and those that need to be disposed of set to one side away from those that are fit for re-use.
A partially-dismantled scaffold should not be left standing for any longer than is necessary, but if it cannot be avoided then clear warning signs should be provided at access points.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Restoring Great Yarmouth's Winter Gardens
Transforming one of the least sustainable constructions imaginable.
Construction Skills Mission Board launch sector drive
Newly formed government and industry collaboration set strategy for recruiting an additional 100,000 construction workers a year.
New Architects Code comes into effect in September 2025
ARB Architects Code of Conduct and Practice available with ongoing consultation regarding guidance.
Welsh Skills Body (Medr) launches ambitious plan
The new skills body brings together funding and regulation of tertiary education and research for the devolved nation.
Paul Gandy FCIOB announced as next CIOB President
Former Tilbury Douglas CEO takes helm.
UK Infrastructure: A 10 Year Strategy. In brief with reactions
With the National Infrastructure and Service Transformation Authority (NISTA).
Ebenezer Howard: inventor of the garden city. Book review.
The Grenfell Tower fire, eight years on
A time to pause and reflect as Dubai tower block fire reported just before anniversary.
Airtightness Topic Guide BSRIA TG 27/2025
Explaining the basics of airtightness, what it is, why it's important, when it's required and how it's carried out.
Construction contract awards hit lowest point of 2025
Plummeting for second consecutive month, intensifying concerns for housing and infrastructure goals.
Understanding Mental Health in the Built Environment 2025
Examining the state of mental health in construction, shedding light on levels of stress, anxiety and depression.
The benefits of engaging with insulation manufacturers
When considering ground floor constructions.
Lighting Industry endorses Blueprint for Electrification
The Lighting Industry Association fully supports the ECA Blueprint as a timely, urgent call to action.
Comments
¡Good Morning!
I've been reading this article about How to remove scaffolding, and I really want to thank for this information, because I consider this topic is very important, as much as the scaffolding Assembly. Follow the instructions and try to maintain the security of all is fundamental in every project! this article is quite complete and useful! thanks again... ¡¡¡I recommend it!!