Migration strategy
Once the client is certain that the project will proceed, they should appoint a senior director responsible for moving, who can stand their ground under pressure from various elements of management who may fight their corner during the stress and upheaval of moving. The job is one that requires the skillful co-ordination of a multitude of time consuming tasks. On larger projects this is likely to require a team of people working under the director, including an accommodation manager and perhaps a facilities manager.
After preparing a policy for occupation, setting out how the facility will be used (see article on occupation), the director and their team should prepare a migration strategy (or move in programme) setting out the procedures for moving in such a way as to minimise disruption whilst allowing the efficient re-use of assets from any existing facilities.
This migration strategy might include:
- A detailed, phased, logistical programme for purchasing or moving of furniture and equipment.
- A detailed, programme for moving or recruiting staff.
- Requirements for the hire of temporary equipment.
- Removal contracts.
- Setting up a help desk with a rapid response team.
- Postal and information and communications technology (ICT) arrangements to ensure continuity of communication (including transfer of hardware).
- Setting up 'goods in' and 'dispatch' rooms, a post room and an information and communications technology support centre.
- Catastrophe planning for fire or flood.
- Staff transportation strategy.
- Parking allocation.
- Access by consultants, contractors and suppliers for summer and winter checks of building services systems and environmental conditions (which can only be properly carried out in a fully operational building).
- Room allocation.
- Signage.
- Catering facilities and environmental health approval of kitchen areas.
- Liaison with emergency services.
- Stocking and storage of goods and consumables.
- Communications between facilities during the move.
- Installation of existing equipment requiring electrical, drainage, extract or cooling services such as vending machines or fume cupboards.
- A risk schedule with mitigation measures (for example; the absence of key personnel, late building handover, alarm activation, interruption of power or water supply and so on).
The client may also need to put procedures in place to move some of its staff and equipment so that it can continue to operate effectively during construction.
If the soft landings framework is adopted, there may be additional requirements to ensure a smooth transition from construction to occupation, and these should be included in appointment documents and contracts. See soft landings for more information.
[edit] Related articles on Designing Buildings
Featured articles and news
Costs and insolvencies mount for SMEs, despite growth
Construction sector under insolvency and wage bill pressure in part linked to National Insurance, says report.
The place for vitrified clay pipes in modern infrastructure
Why vitrified clay pipes are reclaiming their role in built projects.
Research by construction PR consultancy LMC published.
Roles and responsibilities of domestic clients
ACA Safety in Construction guide for domestic clients.
Fire door compliance in UK commercial buildings
Architect and manufacturer gives their low down.
Plumbing and heating for sustainability in new properties
Technical Engineer runs through changes in regulations, innovations in materials, and product systems.
Awareness of the Carbon Border Adjustment Mechanism
What CBAM is and what to do about it.
The new towns and strategic environmental assessments
12 locations of the New Towns Taskforce reduced to 7 within the new towns draft programme and open consultation.
Buildings that changed the future of architecture. Book review.
The Sustainability Pathfinder© Handbook
Built environment agency launches free Pathfinder© tool to help businesses progress sustainability strategies.
Government outcome to the late payment consultation, ECA reacts.
IHBC 2025 Gus Astley Student Award winners
Work on the role of hewing in UK historic conservation a win for Jack Parker of Oxford Brookes University.
Future Homes Building Standards and plug-in solar
Parts F and L amendments, the availability of solar panels and industry responses.
How later living housing can help solve the housing crisis
Unlocking homes, unlocking lives.
Preparing safety case reports for HRBs under the BSA
A new practical guide to preparing structural inputs for safety cases and safety case reports published by IStructE.
Male construction workers and prostate cancer
CIOB and Prostate Cancer UK encourage awareness of prostate cancer risks, and what to do about it.