Compliant bids in the construction industry
A tender (or bid) is a submission made by a prospective supplier (such as a contractor) in response to an invitation to tender (ITT) from a client. It makes an offer for the supply of goods or services.
If a prospective contractor or supplier submits a tender which meets the client's stipulated requirements, (ie the mandatory elements of the Invitation to Tender (ITT) have been satisfied) then that bidder is said to have submitted a compliant bid.
Guidance to prospective bidders is usually clear about the requirements, in terms of precise information required, word length, presentation format, requirement for images, etc. Simply put, full compliance means all material conditions of a tender must be complied with and the price submitted should be based on the client’s tender specification documents.
If a tender is not compliant it may be rejected.
The precise content of a tender will vary considerably, depending on the procurement route, however it might include:
- A tender return slip, with details of the contract, including information such as return address and tender checklist;
- A completed tender pricing document (or contract sum analysis on design and build projects);
- Schedules of rates;
- An initial construction phase plan;
- Any design proposals or method statements that have been requested;
- Programme;
- Procedures to be adopted, such as procurement procedures and cost management procedures;
- Demonstration of capability, for example design capability, systems used etc;
- A BIM execution plan - if building information modelling is being used;
- Key project personnel, which may require submission of CVs;
- Management organisation;
- Plant and labour resources and availability;
- Prior experience, and
- References
However, some circumstances may allow a tender to be accepted even if it does not comply. A non-compliant proposal, sometimes referred to as a variant bid, may be submitted if the tenderer believes that an alternative could offer better value for money. However, non-compliant proposals should only be submitted if they have been requested or are explicitly permitted by the client, and they may need to be accompanied by a compliant bid.
[edit] Ways to create a compliant tender:
- Answer the question i.e. state what is required under each question;
- Answer all the question(s);
- Do not exceed the required word length;
- Do not supply information that is not required, e.g if a tender requires brief personal profiles, do not submit full CVs unless these are explicitly asked for;
- Do not leave sections blank;
- Submit in the correct format, e.g PDF, Excel, Word etc where required;
- Submit on time, and to the correct person;
- Ensure that proposals satisfy the client's requirements.
- Ensure works are packaged in the way the client requires.
- Visit the site, and if permitted, ask questions to avoid misunderstandings.
- Provide pricing information in the format and breakdown requested.
See also: Common mistakes in construction tenders.
[edit] Related articles on Designing Buildings Wiki
- Best value.
- Bidder.
- Bid writer.
- Competitive tender.
- Contract award.
- Contract conditions.
- Contract documents.
- Due diligence when selecting contractors or subcontractors.
- Invitation to tender.
- Letter of award.
- Mid-tender interview.
- Most Economically Advantageous Tender (MEAT).
- Pre-tender interview.
- Procurement route.
- Selection criteria.
- Tender documentation.
- Tender evaluation.
- Tender processes.
Featured articles and news
How much does it cost to build a house?
A brief run down of key considerations from a London based practice.
The need for a National construction careers campaign
Highlighted by CIOB to cut unemployment, reduce skills gap and deliver on housing and infrastructure ambitions.
AI-Driven automation; reducing time, enhancing compliance
Sustainability; not just compliance but rethinking design, material selection, and the supply chains to support them.
Climate Resilience and Adaptation In the Built Environment
New CIOB Technical Information Sheet by Colin Booth, Professor of Smart and Sustainable Infrastructure.
Turning Enquiries into Profitable Construction Projects
Founder of Develop Coaching and author of Building Your Future; Greg Wilkes shares his insights.
IHBC Signpost: Poetry from concrete
Scotland’s fascinating historic concrete and brutalist architecture with the Engine Shed.
Demonstrating that apprenticeships work for business, people and Scotland’s economy.
Scottish parents prioritise construction and apprenticeships
CIOB data released for Scottish Apprenticeship Week shows construction as top potential career path.
From a Green to a White Paper and the proposal of a General Safety Requirement for construction products.
Creativity, conservation and craft at Barley Studio. Book review.
The challenge as PFI agreements come to an end
How construction deals with inherited assets built under long-term contracts.
Skills plan for engineering and building services
Comprehensive industry report highlights persistent skills challenges across the sector.
Choosing the right design team for a D&B Contract
An architect explains the nature and needs of working within this common procurement route.
Statement from the Interim Chief Construction Advisor
Thouria Istephan; Architect and inquiry panel member outlines ongoing work, priorities and next steps.
The 2025 draft NPPF in brief with indicative responses
Local verses National and suitable verses sustainable: Consultation open for just over one week.
Increased vigilance on VAT Domestic Reverse Charge
HMRC bearing down with increasing force on construction consultant says.
Call for greater recognition of professional standards
Chartered bodies representing more than 1.5 million individuals have written to the UK Government.