Compliant bids in the construction industry
A tender (or bid) is a submission made by a prospective supplier (such as a contractor) in response to an invitation to tender (ITT) from a client. It makes an offer for the supply of goods or services.
If a prospective contractor or supplier submits a tender which meets the client's stipulated requirements, (ie the mandatory elements of the Invitation to Tender (ITT) have been satisfied) then that bidder is said to have submitted a compliant bid.
Guidance to prospective bidders is usually clear about the requirements, in terms of precise information required, word length, presentation format, requirement for images, etc. Simply put, full compliance means all material conditions of a tender must be complied with and the price submitted should be based on the client’s tender specification documents.
If a tender is not compliant it may be rejected.
The precise content of a tender will vary considerably, depending on the procurement route, however it might include:
- A tender return slip, with details of the contract, including information such as return address and tender checklist;
- A completed tender pricing document (or contract sum analysis on design and build projects);
- Schedules of rates;
- An initial construction phase plan;
- Any design proposals or method statements that have been requested;
- Programme;
- Procedures to be adopted, such as procurement procedures and cost management procedures;
- Demonstration of capability, for example design capability, systems used etc;
- A BIM execution plan - if building information modelling is being used;
- Key project personnel, which may require submission of CVs;
- Management organisation;
- Plant and labour resources and availability;
- Prior experience, and
- References
However, some circumstances may allow a tender to be accepted even if it does not comply. A non-compliant proposal, sometimes referred to as a variant bid, may be submitted if the tenderer believes that an alternative could offer better value for money. However, non-compliant proposals should only be submitted if they have been requested or are explicitly permitted by the client, and they may need to be accompanied by a compliant bid.
[edit] Ways to create a compliant tender:
- Answer the question i.e. state what is required under each question;
- Answer all the question(s);
- Do not exceed the required word length;
- Do not supply information that is not required, e.g if a tender requires brief personal profiles, do not submit full CVs unless these are explicitly asked for;
- Do not leave sections blank;
- Submit in the correct format, e.g PDF, Excel, Word etc where required;
- Submit on time, and to the correct person;
- Ensure that proposals satisfy the client's requirements.
- Ensure works are packaged in the way the client requires.
- Visit the site, and if permitted, ask questions to avoid misunderstandings.
- Provide pricing information in the format and breakdown requested.
See also: Common mistakes in construction tenders.
[edit] Related articles on Designing Buildings Wiki
- Best value.
- Bidder.
- Bid writer.
- Competitive tender.
- Contract award.
- Contract conditions.
- Contract documents.
- Due diligence when selecting contractors or subcontractors.
- Invitation to tender.
- Letter of award.
- Mid-tender interview.
- Most Economically Advantageous Tender (MEAT).
- Pre-tender interview.
- Procurement route.
- Selection criteria.
- Tender documentation.
- Tender evaluation.
- Tender processes.
Featured articles and news
Futurebuild and UK Construction Week London Unite
Creating the UK’s Built Environment Super Event and over 25 other key partnerships.
Welsh and Scottish 2026 elections
Manifestos for the built environment for upcoming same May day elections.
Advancing BIM education with a competency framework
“We don’t need people who can just draw in 3D. We need people who can think in data.”
Guidance notes to prepare for April ERA changes
From the Electrical Contractors' Association Employee Relations team.
Significant changes to be seen from the new ERA in 2026 and 2027, starting on 6 April 2026.
First aid in the modern workplace with St John Ambulance.
Ireland's National Residential Retrofit Plan
Staged initiatives introduced step by step.
Solar panels, pitched roofs and risk of fire spread
60% increase in solar panel fires prompts tests and installation warnings.
Modernising heat networks with Heat interface unit
Why HIUs hold the key to efficiency upgrades.
Reflecting on the work of the CIOB Academy
Looking back on 2025 and where it's going next.
Procurement in construction: Knowledge hub
Brief, overview, key articles and over 1000 more covering procurement.
Sir John Betjeman’s love of Victorian church architecture.
Exchange for Change for UK deposit return scheme
The UK Deposit Management Organisation established to deliver Deposit Return Scheme unveils trading name.
A guide to integrating heat pumps
As the Future Homes Standard approaches Future Homes Hub publishes hints and tips for Architects and Architectural Technologists.
BSR as a standalone body; statements, key roles, context
Statements from key figures in key and changing roles.
Resident engagement as the key to successful retrofits
Retrofit is about people, not just buildings, from early starts to beyond handover.