Completion
Contents |
[edit] Introduction
The term ‘completion’ is often used in the context of buildings and construction projects, but there is no precise legal definition, and its meaning is dependent on the situation in which it is being used.
[edit] Property sales
In the context of property, completion is the point at which the price of the property is paid and transfer documents are dated, thereby completing the final step in the legal process of transferring the ownership of property.
[edit] Construction works
In relation to construction, the situation is considerably more complex as 'completion' is generally not a single event, but takes place in stages.
Most construction contracts will set a date by which the works described in the contract must be completed. However, this is not the date by which all obligations under the contract have to be discharged, but only the date by which 'practical completion' must be certified.
There is no absolute definition of practical completion, but very broadly, practical completion is deemed to have occurred when all the construction works that are described in the contract have been carried out, and the contract administrator issues a certificate of practical completion. For more information see: Practical completion.
This is followed by a defects liability period during which the contractor may be recalled to rectify defects which appear. At the end of the defects liability period, the contract administrator prepares a schedule of defects, listing those defects that have not yet been rectified, and agrees with the contractor the date by which they will be rectified. When the contract administrator considers all the items on the schedule of defects have been rectified, they issue a certificate of making good defects.
In effect, this marks the completion of the works. There may still be latent defects, which do not appear for some time, however, the building owner no longer has a contractual right to insist that the contractor rectifies any defects, and they must instead seek redress in an action for damages, for breach of contract, or for negligence. In the case of dwellings there is a statutory remedy provided by the Defective Premises Act 1972.
NB: Sectional completion refers to a provision within construction contracts allowing different completion dates for different sections of the works. This is common on large projects that are completed in sections, allowing the client to take possession of the completed parts whilst construction continues on others. See Sectional completion for more information.
Partial possession clauses may permit the client or tenants to take possession of part of a building or site, even if the works are ongoing or there are defects that have not been rectified. See Partial possession for more information.
[edit] Other commercial contracts
Under other commercial contracts (i.e. those that relate to goods and services), the contract performance is not considered 'complete' until the obligations imposed by the contract have been fulfilled.
See also: Failure to complete construction works.
[edit] Related articles on Designing Buildings
- Building completion.
- Certificate of non completion.
- Completion date.
- Difference between practical completion and partial possession.
- Early use.
- Failure to complete construction works.
- Handover to client.
- Partial possession.
- Practical completion.
- Sectional completion.
- Substantial completion.
- Topping out.
- Work-to-complete list.
Featured articles and news
For the World Autism Awareness Month of April.
70+ experts appointed to public sector fire safety framework
The Fire Safety (FS2) Framework from LHC Procurement.
Project and programme management codes of practice
CIOB publications for built environment professionals.
Sustainable development concepts decade by decade.
The regenerative structural engineer
A call for design that will repair the natural world.
Buildings that mimic the restorative aspects found in nature.
CIAT publishes Principal Designer Competency Framework
For those considering applying for registration as a PD.
BSRIA Building Reg's guidance: The second staircase
An overview focusing on aspects which most affect the building services industry.
Design codes and pattern books
Harmonious proportions and golden sections.
Introducing or next Guest Editor Arun Baybars
Practising architect and design panel review member.
Quick summary by size, shape, test, material, use or bonding.
Types of rapidly renewable content
From forestry to agricultural crops and their by-products.
Terraced houses and the public realm
The discernible difference between the public realm of detached housing and of terraced housing.