Activity schedules in construction contracts
The term ‘activity schedule’ appears in contracts such as the NEC (New Engineering Contract) Option A contract and in a number of standard lump sum contracts. In FIDIC contracts (Fédération Internationale des Ingénieurs-Conseils), it could be interpreted as fulfilling the requirements of the schedule of payments in a lump-sum contract.
In essence, it relates to a programme where each activity is allocated a price and interim payments are made against completion of each activity. Its advantage is that it simplifies the administration of the interim payment process.
The activity schedule on these types of project is submitted together with a contract programme as part of the tender. It is important that all the activities priced add up to the tender sum and that major sub-contractors participate in the allocation of prices against their programmed activities. This may include payments for off-site goods and materials.
The simplest way to prepare an activity schedule is to draw up a bar chart (Gantt chart) which covers all the main activities required, separating each element of work that is sub-contracted. Some preliminaries, such as site offices, need a separate price bar for set up, operational use and dismantling activities. Other preliminaries such as staff and electrical consumption will be part of a constant bar.
Bars that are longer than a month then have their bar line split by defining more accurately the piece of work completed in that period. A time-defined period is acceptable in the case of preliminaries. The price allocated to each total element of work is then proportionately split to match the more defined elements.
The client’s cost consultant must ensure that the pricing of the activity schedule is not unduly front-loaded and fairly reflects normal cash-flow curves associated with building projects.
The contract conditions normally allow the contractor a short period of time after appointment to re-visit the activity schedule to expand its detail. In addition, during the course of the project, the activity schedule can be adjusted to accommodate variations, extensions of time and compensation events.
The preparation of a monthly submission for interim payment is best achieved by the contractor's project manager walking the site with the client’s representative to agree progress in respect of completed activities. Here some judgement needs to be exercised by the client’s representative as to what is ‘complete’, otherwise, strictly speaking, on a 100% basis the contractor would suffer massive cash-flow problems due to the withholding of payment.
Once the progress chart against the programme has been agreed it becomes a simple mathematical calculation of the relative prices to arrive at the valuation and its certification.
NB: Within the NEC3 Engineering and Construction Contract (ECC), The 'accepted programme' shows how the activities on the activity schedule are programmed. The accepted programme and the activity schedule need not show exactly the same activities, but there should be correlation between them, and they should be kept up to date. See accepted programme for more information.
[edit] Related articles on Designing Buildings Wiki
- Acceleration of construction works.
- Accepted programme.
- Baseline programme.
- Conditions of contract.
- Construction contract.
- Contractor's working schedule.
- Gantt chart.
- How progress is agreed in construction.
- Interim payment.
- Line of balance (LOB).
- Milestones.
- NEC Option A: Priced contract with activity schedule.
- Off-site goods and materials.
- Preliminaries.
- Procurement route.
- Programme.
- Programme consultant.
- Progress in construction.
- Resource management.
- Schedule.
- Schedule performance index (SPI).
- Short period programme.
- Tender works programme.
- Time-location chart.
- Time management of construction projects.
- Topping out.
- Window and door schedules.
[edit] External references
Featured articles and news
AI and the challenges to intellectual property
The legal landscape of adopting AI now and in the future.
Worrying landscape for Welsh construction SMEs revealed.
In recent risk factor analysis report completed by CIOB.
Construction Sport survey highlights risks of dehydration
Supporting construction workers to avoid dangers.
Can your business afford to ignore mental well-being?
£70 - 100 billion annually in UK construction sector.
Mental health in the construction industry
World Mental Health Day 10 October.
Construction awards provide relief in wake of ISG collapse
Spike in major infrastructure awards, housing up but short of targets, are ISG collapse impacts yet to come.
Biodiversity net gain with related updates and terms
Only 0.5% of applications subject to BNG in the context significant proposed changes to planning.
As political power has shifted from blue to red
Has planning now moved from brown to green?
The role of construction in tackling the biodiversity crisis
New CIOB Nature of Building digital series available now.
The Nature Towns and Cities initiative
Grants of up to 1 million for local councils and partners.
The continued ISG fall out October updates
Where to look for answers to frequently asked questions.
Building safety remediation programme for Wales
With 2024 October progress updates.
In major support package for small businesses.
Conservation and transformation
Reading Ruskin’s cultural heritage. Book review.
Renovating Union Chain Bridge.
AI tools for planning, design, construction and management
A long, continually expanding list, any more to add?