Off site materials
It can sometimes be appropriate for the client to pay for items even though they remain ‘off-site’, for example, where a contractor has themselves made a large payment for plant or materials that have yet to be delivered to site, or if the client wishes to ‘reserve’ key items in order to protect the programme. Such items should be agreed in advance and listed in an annex to the contract bills.
Paying for off-site goods or materials can be useful, however, it does put the client at risk, for example if the contractor becomes insolvent and the items are then not delivered, even though payment has been made.
Several mechanisms are available to protect the client:
- The client should check the financial status of the contractor to assess the likelihood of insolvency.
- The client should require proof that the property in the items is vested in the contractor before payment is made. This may include a vesting certificate (certifying that property has passed to the contractor and that the materials will be properly identified, stored and insured), and checking that the suppliers terms and conditions do not include a retention of title clause.
- The items should be set aside, and clearly marked with the client’s details.
- The materials should be 'ready for incorporation'.
- The client should require proof that the materials are insured against specified perils for the period they remain off site.
- If the contractor is part of a larger group, then a guarantee might be required from the holding company.
- An on-demand bond might be required up to the value of the off-site items, with the value of the bond reducing as deliveries to site are made.
- The client might enter into a contract direct with the supplier.
However, none of these methods is fool proof. For example, a vesting certificate may be of limited value in practice, as it is difficult to sue an insolvent contractor. Furthermore, despite best endeavours, items may simply be removed or disappear in the event of insolvency, or if there is a rumour that insolvency might occur. This is particularly true for items that have yet to be fabricated, items that have still to be worked on, or items that are abroad.
In a perfect world, items would be delivered to the site and affixed to the property before payment is made, but where this is not possible, a judgement is necessary to assess the risk to the project, or the potential loss to the client versus the cost of ensuring absolute certainty in relation to off-site goods.
See also: Materials on site.
For legal issues, see Off-site goods and materials - legal issues.
[edit] Related articles on Designing Buildings Wiki
- Advance payment bond.
- Bonds and guarantees.
- BSRIA launches Offsite Construction for Building Services topic guide.
- Construction inventory management.
- Design for Manufacture and Assembly (DfMA).
- How to make projects off-site ready.
- Just in time manufacturing.
- Lead time.
- Logistics management.
- Long lead-time item.
- Materials.
- Materials on site.
- Off-site construction.
- Off-site goods and materials - legal issues.
- Off site, on track.
- On site.
- Platform approach to design for manufacture and assembly.
- Precast.
- Precast flat panel system.
- Protecting and storing rebar.
- Retention of title.
- Site storage.
- Vesting certificate.
Featured articles and news
Heat pump announcements, what homeowners need to know
An 'ultimate guide to heat pumps' from a heating company.
Construction contract awards reach £7.1bn in February
Their highest level in seven months.
The journey to sustainability in heritage
Research is the key to better understanding.
Heritage approaches to adaptation, mitigation and loss.
Bridging the gap between policy, finance and installation.
Development on brownfield land
Definition, background, policy and the latest consultation.
With the Design Framework for Building Services.
Retrofit of Buildings, a CIOB Technical Publication
Pertinent technical issues, measures and the roles involved.
ECA joins HSE campaign to support mental health
Working Minds’ five simple steps based on risk assessment.
Mental health in the construction industry
Mental health issues in brief with related articles.
Transitional arrangements, Building Control and the BSR.
For pre-October buildings with substantial progress by April.
How to write an inspection and test plan
ITPs for quality control and assurance particular elements.
Why quality counts in domestic ventilation systems
From products, to systems to the installation.
Empowering the Future with CIOB Academy
Lifelong learning, upscaling, and reskilling for the built environment.
Winners of the 2024 ASBP Awards
Project, Product and Initiative according to the 6 pillars.
Comments
To start a discussion about this article, click 'Add a comment' above and add your thoughts to this discussion page.