Work breakdown structure
Contents |
[edit] Introduction
Work breakdown structures are used mainly in project management and systems engineering. They were first developed by the US Defense department in 1957 as part of the development of the Polaris missile programme and further developed by NASA in 1962.
A work breakdown structure (WBS) is a system of breaking down a project or programme into manageable tasks, phases, deliverables or work packages (subdivision of effort). However, it is not a recipe for how a project should be constructed nor is it just a list of tasks, a schedule or an organisation chart - although it provides a basis from which a schedule or task list can be created. The benefit of a WBS is that it allows detailed thinking at the micro level without losing sight of the macro picture.
An example is the building of a house which represents the top-level deliverable. Starting with this end objective, WBS determines a hierarchy by subdividing the project into manageable components (or sub-deliverables, eg systems, subsystems, components, tasks and subtasks), thereby defining all the necessary steps to achieve the end goal (ie the finished building) in increasing levels of detail.
For example, this may mean:
- Level 1 Top-level deliverable or project (the finished building).
- Level 2: Sub-dividing the project into main components, eg substructure and superstructure.
- Level 3: Breaking down each component into smaller components (eg substructure > excavation).
- Level 4: breaking down each component into more components. (eg excavation > place reinforcement)
- Level n: Final breakdown into smallest component (eg place reinforcement > pour concrete)
The process is broken down until a point is reached at which sufficient detail exists to allow precise planning and management. This lowest level is known as Level n (see above). At this level, the work is assigned to a specific department or unit to undertake the work. Furthermore, each of the Level n components can have its own cost account and allocated its own budget to produce the deliverable. In this way, integrating cost with the WBS allows the tracking of financial performance in addition to project performance.
There should be no scope overlap between the different elements of a WBS. If this was the case, there could be ambiguity and possible duplication of work, as well as cost-accounting confusion.
In terms of representation, a WBS can be shown vertically as a tree or horizontally in outline form.
The 100 per cent rule is a central tenet of WBS that guides its development, composition and evaluation. It holds that a WBS will contain 100% of the work defined by the project scope and will account for all deliverables (whether internal, external or interim work to be completed). The WBS can only include 100% of the work of the project and should not include any work that falls outside the project scope. All the work in each work package must add up to 100% of the work necessary to complete that work package and all work packages must add up to 100% of the top-level deliverable. This is analogous to a pie chart in which the total area of all segments (irrespective of how many segments there are) must be equal to the total area of the circle.
[edit] Breakdown structures for bill of quantities
According to NRM2, RICS new rules of measurement, Detailed measurement for building work, there are three main breakdown structures for bill of quantities (BQBS):
- Elemental
- Work section
- Work package
For more information see: Bill of quantities breakdown structures
[edit] Cost breakdown structure
According to NRM2, in the context of bill of quantities, a cost breakdown structure (CBS) ‘…represents the financial breakdown of a building project into cost targets for elements or work packages.’
For more information see: Cost breakdown structure
[edit] Work breakdown structure dictionary
Earned Value Management Handbook, Published by the Association for Project Management in March 2013 suggests that:
|
Projects may use a work breakdown structure dictionary (WBSD), the purpose of which is to describe the entire scope of work to be undertaken within the project. It For each element of the WBS, the dictionary should contain:
The WBS dictionary should include all elements to be sub-contracted and should specifically identify the sub-contractor undertaking the WBS element. |
See also: Breakdown structure.
[edit] Related articles on Designing Buildings
- Bill of quantities breakdown structures
- Breakdown structure.
- Contractor's master programme.
- Cost breakdown structure.
- Design web.
- Earned value.
- Fast-track construction.
- Key performance indicators.
- Line of balance (LOB).
- Logic links.
- Milestones.
- Organisation breakdown structure.
- Pareto analysis.
- Precedence diagram method.
- Product breakdown structure.
- Project crashing.
- Resource leveling.
- Scheduling construction activities.
Featured articles and news
Guidance notes to prepare for April ERA changes
From the Electrical Contractors' Association Employee Relations team.
Significant changes to be seen from the new ERA in 2026 and 2027, starting on 6 April 2026.
First aid in the modern workplace with St John Ambulance.
Ireland's National Residential Retrofit Plan
Staged initiatives introduced step by step.
Solar panels, pitched roofs and risk of fire spread
60% increase in solar panel fires prompts tests and installation warnings.
Modernising heat networks with Heat interface unit
Why HIUs hold the key to efficiency upgrades.
Reflecting on the work of the CIOB Academy
Looking back on 2025 and where it's going next.
Procurement in construction: Knowledge hub
Brief, overview, key articles and over 1000 more covering procurement.
Sir John Betjeman’s love of Victorian church architecture.
Exchange for Change for UK deposit return scheme
The UK Deposit Management Organisation established to deliver Deposit Return Scheme unveils trading name.
A guide to integrating heat pumps
As the Future Homes Standard approaches Future Homes Hub publishes hints and tips for Architects and Architectural Technologists.
BSR as a standalone body; statements, key roles, context
Statements from key figures in key and changing roles.
ECA launches Welsh Election Manifesto
ECA calls on political parties at 100 day milestone to the Senedd elections.
Resident engagement as the key to successful retrofits
Retrofit is about people, not just buildings, from early starts to beyond handover.
Plastic, recycling and its symbol
Student competition winning, M.C.Esher inspired Möbius strip design symbolising continuity within a finite entity.
Do you take the lead in a circular construction economy?
Help us develop and expand this wiki as a resource for academia and industry alike.
Warm Homes Plan Workforce Taskforce
Risks of undermining UK’s energy transition due to lack of electrotechnical industry representation, says ECA.
Cost Optimal Domestic Electrification CODE
Modelling retrofits only on costs that directly impact the consumer: upfront cost of equipment, energy costs and maintenance costs.
























