Control account
Control accounts (CAs) are management control points at which budgets and actual costs are compared to earned value. Control accounts will be located at key management points in the work breakdown structure.
Earned Value Management Handbook, Published by the Association for Project Management in March 2013 suggests that a control account:
‘…will normally comprise a number of WPs (work packages), although in some cases a control account may be a single work package. Each work package should have the following attributes:
- a defined scope of work;
- information on measure of achievement;
- traceability up through the WBS;
- a budget;
- details of assignment of responsibility;
- start and finish dates.’
[edit] Related articles on Designing Buildings Wiki
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
CIAT calls for retrofit to be a priority.
Version 6 is now available, along with guidance for ECA members.
Post-War Homes: mid-century British architecture. Book review.
CIAT reflects on the party conferences.
CIOB announce the winners of the Art of Building photography competition.
National Scheme of Delegation introduced.
The cost of employing people remains a concern.
Code of Practice for Electrical Energy Storage Systems.
ECA calls on members to comment on draft 4th edition.
Bringing together expertise and creating cultural benefits.
CIOB celebrates positive Ofsted report.
The Building Safety Regulator announces a call for evidence.
Government approach could undermine delivery and regeneration.