Escalation
Civil Engineering Procedure, 7th edition, published by the Institution of Civil Engineers (ICE) defines ‘escalation’ as an: 'Increases (or decreases) in the costs of labour or materials due to inflation (or recession and deflation).'
Some contracts make provisions for contract price adjustment to allow for the effects of escalation based on data about changes in the cost of commodities, labour, fuel and so on. Such allowances might be referred to as ‘fluctuations’ as there is a fluctuating price in the contract (although fluctuations generally also allow for changes in taxation and increases in head office or administrative costs).
On smaller projects of a short duration, the contractor may be expected to have taken the effects of escalation into account when calculating their price, and they may be able to hold sub-contractors and suppliers to agreed prices for the duration of the contract.
On larger projects, typically lasting more than a year, the contractor may be asked to tender based on prices at an agreed base date, and then the contract makes provisions for escalation to specified items over the duration of the project, such as fuel, steel and so on.
Determining the actual amount of escalation for each item would be very time consuming, and so calculations are generally based on agreed indices, such as public records, JCT bulletins and so on.
Escalation can be caused by issues such as:
- An overheating construction industry.
- Natural disasters.
- Exchange rate changes.
- Changes to regulations.
- Supply problems.
- Labour shortages.
- Inflation in the wider economy, such as fuel price increases or wage increases.
- Global economic conditions.
Escalation clauses put the client at risk, as the final price is not known when the contract is agreed. It is sensible therefore for clients to forecast likely escalation during the course of the project and to make allowances for this, with a contingency provision.
Significant escalation which has not been allowed for can result in the scope of projects being reduced, and can even bring projects to a halt.
However, if there were no escalation provisions, the contractor would have to bear all the risk of price changes, and this would be reflected in their tender.
NB ICMS: Global Consistency in Presenting Construction Life Cycle Costs and Carbon Emissions, 3rd edition, November 2021, published by the ICMS (International Cost Management Standard) Coalition, defines escalation as: ‘A positive or negative factor or rate reflecting an estimate of differential increase/decrease in the general price level for a particular commodity, or group of commodities, or resources (ISO 15686-5).’
See also: Escalation clause and Fluctuations.
[edit] Related articles on Designing Buildings
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
Building Safety Act implementation in Wales
CIAT to host industry panel on 26 June.
New and updated CLC building safety guidance.
New UK National Buildings Database.
Building Safety Wiki Interviews
Chief executive of the British Woodworking Federation.
Planning condition discharge in England and Wales
A brief explanation from a building compliance expert, with further links.
Overheating guidance and tools for building designers
Guidance for dealing with element of building fabric control that have increasing importance.
Shading for housing, a design guide
From the Good Homes Alliance and British Blind and Shutter Association.
UK Standard Skills Classification (SSC)
A shared framework for describing skills needs.
Social media ban consultation comes to close
CIOB urges UK Government to consider social media’s role in careers guidance in ban debate.
The latest of eight Skills England apprenticeship units
The addition of battery manufacturing welcomed by ECA with a warning about the risks of fast-tracked apprenticeship units.
Building Control Independent Panel final report
A precis of a key report led by Dame Hackitt with full recommendations and link to the government response.

















Comments
[edit] To make a comment about this article, or to suggest changes, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.