Seeley Library
Photo courtesy of CIAT.
Contents |
[edit] Introduction
The architectural practice of rhp has been involved with the remarkable Faculty of History building for over a decade. The company's most recent project has the been the refurbishment of the Seeley Library.
[edit] History
The Seeley Library is Grade II* listed and lies within the West Cambridge conservation area. The Library was commissioned through an invited architectural competition during March 1963 and for which the design by James Stirling (and his then partner James Gowan) was considered to respond perfectly to the brief.
Construction of the Seeley Library commenced in October 1964 and the building was occupied towards the end of 1968. It was listed in April 2000 and is the second of three university commissions by James Stirling distinguished by their ‘functional expressionism’ and use of red brick and glass. The Leicester University Engineering Building (1961-3, Grade II), was the first and the Florey Building, Queen’s College, Oxford (1966-71, Grade II) the third.
“They are amongst the most important and recognisable British buildings of the 1960s and have been the inspiration for designers and their buildings world-wide.” Statement of Heritage Significance – The History Faculty, University of Cambridge, Beacon Planning, June 2017.
[edit] The setting
The Seeley Library stands in the grounds of a former large 19th century domestic property, ‘Traverston’, fronting onto West Road, which was one of three properties purchased by the University in 1961. The original site spanned the gardens of two properties and when one of the tenants refused to give up part of their garden, the competition design was rotated anti-clockwise to fit within the boundary of the one property. As a consequence, the glazed roof of the Library faces south, into the site, and the elevation with the twin towers, originally intended to face east towards the main circulation route, faces north.
Stirling and Gowan was dissolved in December 1963, and the library commission was transferred to James Stirling’s new practice. The project was constrained by a budget and timescale imposed by the University Grants Committee.
The competition drawings were submitted in a planning application on 26 June 1963 and approval was granted on 23 July 1963. The project was tendered in July 1964 and construction commenced in October 1964.
[edit] Preservation aspects
An Historic Structures Report was commissioned from John McAslan & Partners in 2000, following the building’s inclusion on the List of Buildings of Historic Interest. This report stands alongside a masterplan for conservation and adaptation which has informed subsequent projects of repair and maintenance. The building was originally Grade II listed in 2000 but its status was raised to Grade II* in March 2018. This change did not vary rhp’s approach, as the company had already considered the significant heritage of the building when planning the project.
The refurbishment works were designed to improve the aesthetic and functional aspects of the library whilst respecting its status and world-wide reputation.
As the library is a popular and well used facility, it was crucial the works did not disturb the students. To achieve this, they were carried out in a phased manner which allowed for extensive research into samples and their suitability to be carried out.
The students were also involved in the selection of materials, for example, desk lights were trialled using both warm and cool lamps which meant these could be tested throughout the year with the changing lighting conditions and enabled the library to make an informed choice. The cork floor refurbishment has been particularly successful in unifying the space and bringing it back into the original design aesthetic and, during darker hours, the impact of the improved desk lighting can be really seen.
[edit] Impact
Dr Linda Washington, Head of Humanities and Social Sciences Libraries & Seeley Librarian has said “the Library looks terrific and the refurbished desks, floor, new shelving and lights are a massive improvement. Library staff all really appreciate the time and attention to detail that has gone into this project, and I have particularly been impressed by the prompt and thorough communications keeping everyone up to date.”
Over the years, rhp has developed an excellent relationship with the Cambridge City Conservation Officer and the University’s Planning Officer which helped the Listed Building application run smoothly, and ensure the project was delivered on time and budget during a very constrained programme.
[edit] Project overview at-a-glance
Programme and construction value:
- Phase 1: six weeks, £50K
- Phase 2, 15 weeks, £460K
Overview of works:
- Providing 24-hour access to the library, basement, WCs and JCR social spaces with the introduction of new security doors to the ground and first floor.
- Improving disabled access with the installation of a new platform lift.
- New safety glazing to first floor mezzanine balcony balustrades.
- Additional and replacement book shelves.
- Refurbishing of the original beech reading desks and adding new desk lighting, USB and power outlets.
- Cleaning and general redecoration including refurbishment of the original cork library floor.
- Improving environmental conditions to Reference Room 6 by the introduction of a new secondary glazing system.
This article originally appeared in the Architectural Technology Journal (at) issue 132 published by CIAT in winter 2019. It was written by Toni Page MCIAT CIAT-Accredited Conservationist.
--CIAT
[edit] Related articles on Designing Buildings Wiki
IHBC NewsBlog
‘Local Heritage Listing: Identifying and Conserving Local Heritage’ Published
Historic England has published a new edition of its advice note on how local heritage listing and local heritage lists can be formally identified as part of the wider range of designation so that they can be taken into account in planning applications.
Hammersmith Bridge illuminated red in Valentine’s Day message to Government
The stunt aimed at highlighting ongoing delays to its repair, as the 133-year-old west London bridge has been closed to traffic since April 2019 when cracks appeared in its pedestals.
Drone Surveying a London Landmark
Uninhabited Aerial Vehicles (UAVs) have been used to undertake a survey of the Lloyd’s building’s external façade in the heart of the City of London.
Green Party calls for no VAT on refurbishment in new Parliamentary petition
The petition calls on the government to remove VAT on refurbishment projects and raise VAT on non-Passivhaus new-build construction to 20 per cent. Retrofitting is carbon-efficient but the current VAT regime privileges new build over refurbishment.
Conservation Professionals Concerned about Future Planning Policy
Directors of the IHBC and the Victorian Society are among those whose opinions are featured in the RICS in-house publication Modus as it explores heritage impacts in England’s planning proposals.
Learn all about the Professions in Building Conservation at upcoming Conference
Glasgow City Heritage Trust (GCHT) 3-day online conference aimed at anyone working, or interested in working, within the building and heritage sectors.
New use for abandoned oil rigs: Offshore reefs!
One way in which these old rigs can be remarkably useful is that the subsurface rig can provide the ideal skeleton for coral reefs, allowing the remarkable ecosystems beneath the waves come into their own.
Birnbeck Pier, in Weston-super-Mare, to undergo Restoration
A new company – Birnbeck Holdings Limited – has now been set up by CNM Estates which has purchased Birnbeck Island and the historic pier.
Ecclesiastical Heritage Risk Barometer 2020 Published
The publication offers research to help answer the question: ‘How can the heritage sector adapt and thrive in the digital age’?
Victorian Bath House dug up from under a Manchester Car Park
A stunning Victorian Bath House has been uncovered during works on creating the city’s first public park in over 100 years.