Resource leveling
Resource leveling (or resource levelling) is a project management technique in which the demand for limited resources is accommodated by adjusting the project programme. In construction, resource leveling can be used to analyse the large variations in resource usage that can occur over time, and which can be inefficient and costly.
Speed of delivery may suggest that certain activities should be performed simultaneously. However, resources such as labour or plant may not be available in the quantities required, or may be occupied by a different activity. Practically therefore, activities may need to be scheduled sequentially, even though this may be slower.
Resource leveling can be used to determine when the project will be completed given the availability of resources.
In some situations, project scheduling may involve a combination of resource leveling and resource smoothing. Resource smoothing is an assessment technique used where the priority is the constraint on time rather than resources. It can be used to determine how best to complete the work by the required deadline, whilst minimising inefficiencies in resource demand.
Project management software can be used for resource leveling, which automatically calculates resource availability and potential delays and updates tasks accordingly. More complex software can be used to level resources company-wide, with the allocation of resources across multiple concurrent projects.
Common techniques that are used by project managers to assist with resource leveling, include:
The Society of Construction Law Delay and Disruption Protocol, 2nd edition, defines resource levelling as: '...the process of amending a schedule to reduce the variation between maximum and minimum values of resource requirements. The process removes peaks, troughs and conflicts in resource demands by moving activities within their early and late dates and taking up float. Most project planning software offers an automated resource-levelling routine that will defer the performance of a task within the imposed logical constraints until the resources assigned to the tasks are available.'
[edit] Related articles on Designing Buildings Wiki
- Acceleration of construction works.
- Critical path method CPM.
- Fast-track construction.
- Gantt chart.
- Line of balance (LOB).
- Milestones.
- Pareto analysis.
- Programme float.
- Project crashing.
- Resource allocation in design and construction.
- Resource management in construction.
- Scheduling construction activities.
- Time-location chart.
- Time management of construction projects.
- Wiest-Levy method.
Featured articles and news
The Home Energy Model and its wrappers
From SAP to HEM, EPC for MEES and FHS assessment wrappers.
Future Homes Standard Essentials launched
Future Homes Hub launches new campaign to help the homebuilding sector prepare for the implementation of new building standards.
Building Safety recap February, 2026
Our regular run-down of key building safety related events of the month.
Planning reform: draft NPPF and industry responses.
Last chance to comment on proposed changes to the NPPF.
A Regency palace of colour and sensation. Book review.
Delayed, derailed and devalued
How the UK’s planning crisis is undermining British manufacturing.
How much does it cost to build a house?
A brief run down of key considerations from a London based practice.
The need for a National construction careers campaign
Highlighted by CIOB to cut unemployment, reduce skills gap and deliver on housing and infrastructure ambitions.
AI-Driven automation; reducing time, enhancing compliance
Sustainability; not just compliance but rethinking design, material selection, and the supply chains to support them.
Climate Resilience and Adaptation In the Built Environment
New CIOB Technical Information Sheet by Colin Booth, Professor of Smart and Sustainable Infrastructure.
Turning Enquiries into Profitable Construction Projects
Founder of Develop Coaching and author of Building Your Future; Greg Wilkes shares his insights.
IHBC Signpost: Poetry from concrete
Scotland’s fascinating historic concrete and brutalist architecture with the Engine Shed.
Demonstrating that apprenticeships work for business, people and Scotland’s economy.
Scottish parents prioritise construction and apprenticeships
CIOB data released for Scottish Apprenticeship Week shows construction as top potential career path.
From a Green to a White Paper and the proposal of a General Safety Requirement for construction products.
Creativity, conservation and craft at Barley Studio. Book review.
The challenge as PFI agreements come to an end
How construction deals with inherited assets built under long-term contracts.
Skills plan for engineering and building services
Comprehensive industry report highlights persistent skills challenges across the sector.
Choosing the right design team for a D&B Contract
An architect explains the nature and needs of working within this common procurement route.
Statement from the Interim Chief Construction Advisor
Thouria Istephan; Architect and inquiry panel member outlines ongoing work, priorities and next steps.