Resource leveling
Resource leveling (or resource levelling) is a project management technique in which the demand for limited resources is accommodated by adjusting the project programme. In construction, resource leveling can be used to analyse the large variations in resource usage that can occur over time, and which can be inefficient and costly.
Speed of delivery may suggest that certain activities should be performed simultaneously. However, resources such as labour or plant may not be available in the quantities required, or may be occupied by a different activity. Practically therefore, activities may need to be scheduled sequentially, even though this may be slower.
Resource leveling can be used to determine when the project will be completed given the availability of resources.
In some situations, project scheduling may involve a combination of resource leveling and resource smoothing. Resource smoothing is an assessment technique used where the priority is the constraint on time rather than resources. It can be used to determine how best to complete the work by the required deadline, whilst minimising inefficiencies in resource demand.
Project management software can be used for resource leveling, which automatically calculates resource availability and potential delays and updates tasks accordingly. More complex software can be used to level resources company-wide, with the allocation of resources across multiple concurrent projects.
Common techniques that are used by project managers to assist with resource leveling, include:
The Society of Construction Law Delay and Disruption Protocol, 2nd edition, defines resource levelling as: '...the process of amending a schedule to reduce the variation between maximum and minimum values of resource requirements. The process removes peaks, troughs and conflicts in resource demands by moving activities within their early and late dates and taking up float. Most project planning software offers an automated resource-levelling routine that will defer the performance of a task within the imposed logical constraints until the resources assigned to the tasks are available.'
[edit] Related articles on Designing Buildings Wiki
- Acceleration of construction works.
- Critical path method CPM.
- Fast-track construction.
- Gantt chart.
- Line of balance (LOB).
- Milestones.
- Pareto analysis.
- Programme float.
- Project crashing.
- Resource allocation in design and construction.
- Resource management in construction.
- Scheduling construction activities.
- Time-location chart.
- Time management of construction projects.
- Wiest-Levy method.
Featured articles and news
A case study and a warning to would-be developers
Creating four dwellings for people to come home to... after half a century of doing this job, why, oh why, is it so difficult?
Reform of the fire engineering profession
Fire Engineers Advisory Panel: Authoritative Statement, reactions and next steps.
Restoration and renewal of the Palace of Westminster
A complex project of cultural significance from full decant to EMI, opportunities and a potential a way forward.
Apprenticeships and the responsibility we share
Perspectives from the CIOB President as National Apprentice Week comes to a close.
The first line of defence against rain, wind and snow.
Building Safety recap January, 2026
What we missed at the end of last year, and at the start of this...
National Apprenticeship Week 2026, 9-15 Feb
Shining a light on the positive impacts for businesses, their apprentices and the wider economy alike.
Applications and benefits of acoustic flooring
From commercial to retail.
From solid to sprung and ribbed to raised.
Strengthening industry collaboration in Hong Kong
Hong Kong Institute of Construction and The Chartered Institute of Building sign Memorandum of Understanding.
A detailed description from the experts at Cornish Lime.
IHBC planning for growth with corporate plan development
Grow with the Institute by volunteering and CP25 consultation.
Connecting ambition and action for designers and specifiers.
Electrical skills gap deepens as apprenticeship starts fall despite surging demand says ECA.
Built environment bodies deepen joint action on EDI
B.E.Inclusive initiative agree next phase of joint equity, diversity and inclusion (EDI) action plan.
Recognising culture as key to sustainable economic growth
Creative UK Provocation paper: Culture as Growth Infrastructure.
Futurebuild and UK Construction Week London Unite
Creating the UK’s Built Environment Super Event and over 25 other key partnerships.
Welsh and Scottish 2026 elections
Manifestos for the built environment for upcoming same May day elections.
Advancing BIM education with a competency framework
“We don’t need people who can just draw in 3D. We need people who can think in data.”