New code of estimating practice
The Code of Estimating Practice was originally published by the Chartered Institute of Building (CIOB) in 1996. It went on to become a highly-respected industry resource, providing an authoritative guide to the principles of, and good practice in, estimating for building work for those involved in procuring and pricing construction works, both in the public and private sectors.
It presents estimating as part of the wider process of commercial management for construction businesses. This is not simply a matter of winning a bid - if the bid is successful, the estimate goes on to form the basis of the contractor’s budget and cost management strategy.
The seventh edition was published in 2009 and included new material on estimating strategy, tendering, procedures and best practice, as well as the build-up of unit rates of cost, overheads and profit, and e-commerce.
In March 2018, it was re-branded as the New Code of Estimating Practice. https://www.wiley.com/en-gb/New+Code+of+Estimating+Practice-p-9781119329640
This new version has been completely rewritten to include more contextual and educational material, and now covers:
- Estimating practice.
- The bidding process.
- The fundamentals in formulating a bid.
- The pre-qualification process.
- Procurement options.
- Contractual arrangements and legal issues.
- Preliminaries.
- Temporary works.
- Cost estimating techniques.
- Risk management.
- Logistics.
- Resource and production planning.
- Computer-aided estimating.
- Information and time planning.
- Resource planning and pricing.
- Preparation of an estimator’s report.
- Bid assembly and adjudication.
- Pre-production planning and processes.
- Site production.
--CIOB
[edit] Related articles on Designing Buildings Wiki
- Approximate quantities cost plan.
- Bills of quantities.
- Budget.
- Chartered Institute of Building.
- All-in rates.
- Contract sum analysis.
- Contract sum.
- Cost consultant.
- Cost control.
- Cost engineering.
- Cost plans for construction projects.
- Elemental cost plan
- Final account.
- Initial cost appraisals.
- Mark-up.
- Measurement.
- New Rules of Measurement.
- Pre-tender estimate.
- Procurement.
- Project overheads.
- Tender documents.
- Top down and bottom up estimating.
Featured articles and news
Ministers to unleash biggest building boom in half a century
50 major infrastructure projects, 5 billion for housing and 1.5 million homes.
RIBA Principal Designer Practice Note published
With key descriptions, best practice examples and FAQs, with supporting template resources.
Electrical businesses brace for project delays in 2025
BEB survey reveals over half worried about impact of delays.
Accelerating the remediation of buildings with unsafe cladding in England
The government publishes its Remediation Acceleration Plan.
Airtightness in raised access plenum floors
New testing guidance from BSRIA out now.
Picking up the hard hat on site or not
Common factors preventing workers using head protection and how to solve them.
Building trust with customers through endorsed trades
Commitment to quality demonstrated through government endorsed scheme.
New guidance for preparing structural submissions for Gateways 2 and 3
Published by the The Institution of Structural Engineers.
CIOB launches global mental health survey
To address the silent mental health crisis in construction.
New categories in sustainability, health and safety, and emerging talent.
Key takeaways from the BSRIA Briefing 2024
Not just waiting for Net Zero, but driving it.
The ISO answer to what is a digital twin
Talking about digital twins in a more consistent manner.
Top tips and risks to look out for.
New Code of Practice for fire and escape door hardware
Published by GAI and DHF.
Retrofit of Buildings, a CIOB Technical Publication
Pertinent technical issues, retrofit measures and the roles involved.
New alliance will tackle skills shortage in greater Manchester
The pioneering Electrotechnical Training and Careers Alliance.