Pre-qualification questionnaire PQQ for construction contracts
A pre-qualification questionnaire (PQQ, sometimes referred to as a supplier assessment questionnaire) sets out a series of questions for potential tenderers to answer regarding their level of experience, capacity and financial standing. The answers to these questions enable the client to produce a short list of suppliers that are likely to be most appropriate for their project. Short-listed suppliers may then be invited to tender for the contract.
Using a pre-qualification questionnaire has the effect of reducing the number of potential tenders to those that are genuinely appropriate for the project, saving a great deal of wasted time for potential tenderers who would not have any realistic chance of winning the contract. It also saves time for the client processing and assessing inappropriate tenders.
Pre-qualification questionnaires should be focused and simple to complete, (perhaps with limits to the number of words that can be submitted in response to each question) otherwise they may just replicate the tender process itself. They should also make it very clear what the tender process is for, so potential tenderers can properly assess whether they have the appropriate experience, capacity and financial standing.
Where possible a scoring and weighting system should be prepared for rating submitted information and potential tenderers should be informed of the details of the system that will be used.
The information requested should be straight-forward, relevant and proportionate to the size of the contract. It might request:
- Company details (including legal status).
- Details of insurance cover.
- Financial information (such as recent accounts).
- Relevant experience.
- Information about technical and professional ability.
- Information about capability and capacity.
- Health and safety policy.
- Quality assurance policy.
- Environmental management policy.
- Equal opportunities policy.
- Relevant references.
- A BIM assessment to determine BIM capability, gaps in skills and training needs.
Systems such as Construction Line go some way to standardising and simplifying the tender process by allowing tenderers to provide pre-qualification information just once that can then be presented to multiple potential clients.
The government requires public clients to use PAS 91, a standardised wording for pre-qualification questionnaires.
NB In December 2013, Enterprise Minister Matthew Hancock set out a range of measures intended to make it easier for small businesses to grow in Small Business: GREAT Ambition. Measures were announced to tackle late payment and to remove the barriers to public contracts by abolishing pre-qualification questionnaires (PQQs) for low-value contracts and mandating the use of core PQQs for high-value contracts.
In March 2021, a new pre-qualification system went live. Developed by Build UK with support from the Civil Engineering Contractors Association, and endorsed by the Construction Leadership Council (CLC), the system has been adopted by contractors and clients including Balfour Beatty, Costain, HS2, Mace, Multiplex and Skanska. It is also supported by a number of leading trade associations, such as electrotechnical sector body ECA.
[edit] Related articles on Designing Buildings
- Appointing consultants.
- Common assessment standard.
- Constructionline.
- Construction contract.
- ESPD and the decline of the PQQ.
- Expression of interest.
- Invitation to tender.
- Mid tender interview.
- PAS 91.
- Pre qualification questionnaires and PAS 91.
- Pre-qualification standard 2021.
- Pre tender interview.
- Procurement route.
- Selection criteria.
- Supplier assessment questionnaire.
- Tender documentation.
- Tender evaluation.
- Tender processes.
- The benefits of e-procurement in construction.
[edit] External references
- OGC Pre-Qualification Questionnaire for selecting suppliers.
- OGC PQQ.
- Construction Line.
- OGC Supplier Selection and Pre-Qualification: Guidance, tools and tips.
- OGC Pre-Qualification Questionnaire.
- Pre-qualification - PAS 91: the use of this standardised wording for PQQ's has been mandated within Government.
- PACE Guidance on the Appointment of Constractors and Consultants P480 Pre Selection Procedures.
Featured articles and news
Heat pump announcements, what homeowners need to know
An 'ultimate guide to heat pumps' from a heating company.
Construction contract awards reach £7.1bn in February
Their highest level in seven months.
The journey to sustainability in heritage
Research is the key to better understanding.
Heritage approaches to adaptation, mitigation and loss.
Bridging the gap between policy, finance and installation.
Development on brownfield land
Definition, background, policy and the latest consultation.
With the Design Framework for Building Services.
Retrofit of Buildings, a CIOB Technical Publication
Pertinent technical issues, measures and the roles involved.
ECA joins HSE campaign to support mental health
Working Minds’ five simple steps based on risk assessment.
Mental health in the construction industry
Mental health issues in brief with related articles.
Transitional arrangements, Building Control and the BSR.
For pre-October buildings with substantial progress by April.
How to write an inspection and test plan
ITPs for quality control and assurance particular elements.
Why quality counts in domestic ventilation systems
From products, to systems to the installation.
Empowering the Future with CIOB Academy
Lifelong learning, upscaling, and reskilling for the built environment.
Winners of the 2024 ASBP Awards
Project, Product and Initiative according to the 6 pillars.
Comments
[edit] To make a comment about this article, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.