Latent defects
It is the nature of construction projects that faults and defects caused by failures in design, workmanship or materials, may not become apparent or readily detectable (even with the exercise of reasonable care) until many years after completion of the project, long after the end of the defects liability period. Such defects are known as latent defects (as opposed to patent defects which are apparent).
Examples of common latent defects include:
- Defective basement tanking allowing water penetration.
- Inadequate wind-posts or wall ties causing movement damage to walls.
- Under-strength concrete or misplaced reinforcement allowing movement damage to the structure.
- Inadequate foundations causing subsidence of the building.
It is also a feature of construction projects that the completed building will have a life-cycle of many years often with a succession of future owners who had no involvement in the original construction, but who have a liability to maintain the structure.
After the end of the defects liability period the building owner does not have a contractual right to insist that the contractor rectifies defects not notified during that period (as will often be the case with latent defects). The building owner must instead seek redress in an action for damages, for breach of contract, or for negligence. In the case of dwellings there is a statutory remedy provided by the Defective Premises Act 1972.
These rights of action are not perpetual; actions for breach of contract are time barred after 6 years from the date of breach (usually the completion of the building although with a failure of design the breach may occur earlier) see the Limitation Act 1980 Section 5. For a contract under seal, the period is 12 years (see the Limitation Act 1980 Section 8). Clearly therefore it is important to the building owner that all contracts are made under seal; not so for the contractor, the professional consultant or their insurers. Where the claim is for negligence, the time limit is six years from the date on which the cause of action accrued, which will be the date when the damage occurred.
Complex arguments arise in respect of economic loss. This may be many years after the completion of the building. The provisions of the Latent Damage Act 1986 Section 1 (by way of a new Section 14A to the Limitation Act) provides a limitation period for negligence of 3 years from the first knowledge of the cause of action and (by way of a new section 14B to the Limitation Act) an overriding 15 year long-stop from the act of negligence giving rise to the damage. Section 3 of the Act is important as it gives a new cause of action to successive owners.
Commercial fixes for latent defects and successive owners include, collateral warranties, guarantees, building warranty schemes and latent defects insurance. Latent defects insurance first appeared in the UK in the 1980s, imported from Europe and known as decennial insurance. It soon fell out of favour as a result of being over-hyped and overpriced. Latent defect insurance is now making a comeback.
[edit] Related articles on Designing Buildings
- Caveat emptor.
- Certificate of making good defects.
- Collateral warranties.
- Damage caused by construction works.
- Defective Concrete Blocks Grant Scheme.
- Defects liability period.
- Defects.
- Design liability.
- Defects list.
- Final certificate.
- Flooring defects.
- Guarantees.
- Ground heave.
- Inspection.
- Making good.
- Opening up works for inspection and testing.
- Patent defects.
- Practical completion.
- Professional consultant's certificate.
- Professional indemnity insurance.
- Pyrite and mica redress issues in Dail Eireann.
- Retention.
- Settlement.
- Site inspector.
- Soft landings.
- Using satellite imagery to monitor movements in megaprojects.
- Why do buildings crack? (DG 361).
[edit] External references
Featured articles and news
The 5 elements of seiri, seiton, seiso, seiketsu and shitsuke.
Shading for housing, a design guide
A look back at embedding a new culture of shading.
The Architectural Technology Awards
The AT Awards 2025 are open for entries!
ECA Blueprint for Electrification
The 'mosaic of interconnected challenges' and how to deliver the UK’s Transition to Clean Power.
Grenfell Tower Principal Contractor Award notice
Tower repair and maintenance contractor announced as demolition contractor.
Passivhaus social homes benefit from heat pump service
Sixteen new homes designed and built to achieve Passivhaus constructed in Dumfries & Galloway.
CABE Publishes Results of 2025 Building Control Survey
Concern over lack of understanding of how roles have changed since the introduction of the BSA 2022.
British Architectural Sculpture 1851-1951
A rich heritage of decorative and figurative sculpture. Book review.
A programme to tackle the lack of diversity.
Independent Building Control review panel
Five members of the newly established, Grenfell Tower Inquiry recommended, panel appointed.
Welsh Recharging Electrical Skills Charter progresses
ECA progressing on the ‘asks’ of the Recharging Electrical Skills Charter at the Senedd in Wales.
A brief history from 1890s to 2020s.
CIOB and CORBON combine forces
To elevate professional standards in Nigeria’s construction industry.
Amendment to the GB Energy Bill welcomed by ECA
Move prevents nationally-owned energy company from investing in solar panels produced by modern slavery.
Gregor Harvie argues that AI is state-sanctioned theft of IP.
Experimental AI housing target help for councils
Experimental AI could help councils meet housing targets by digitising records.
BSRIA Occupant Wellbeing survey BOW
Occupant satisfaction and wellbeing tool inc. physical environment, indoor facilities, functionality and accessibility.
Comments
Is it not time to look at a new model for regulating the construction industry. The need to identify the cause of the defect is essential as only then can the correct response to applied. There is a current model which is used in another industry which could be applied to the construction sector and it would make individuals accountable for their work and ensure a better product reached the market.