Jumpform v slipform
Contents |
[edit] Introduction
Jumpform and slipform are both systems of concrete construction that use a self-climbing formwork to construct multi-storey structures, typically building cores and shafts, as well as chimneys and silos. They are both climb-form systems.
In both cases, formwork into which concrete is poured, climbs vertically up the structure being constructed; sometimes this is from power provided by hydraulic rams and electric motors and can mean that craneage is reduced to a minimum. Both systems feature one or more decks or platforms surrounding the construction for workers to carry out the necessary operations as construction proceeds, such as pouring and monitoring concrete compaction, placing reinforcement and finishing the concrete.
Whether slipform or jumpform, the formwork is supported on the concrete that has already been cast below it, so it does not rely on support from other parts of the building; this allows the shaft or core to progress ahead of the rest of the building works.
However, there are important differences between the two systems in terms of operation, speed and the result achieved.
[edit] Jumpform
Typically, jumpform is used on buildings more than five storeys high, although if a fully-climbing system, it can be applied to 20-storeys and more.
Jumpform is characterised by progression in a series of steps or ‘jumps’, progressing to the next section only after the concrete in the previous one has achieved the necessary strength. For example, after a 2m section has been poured and set, the formwork is ‘jumped’ to pour the next 2m section. The system is particularly suited to situations where the resulting joints between jumps will be concealed at every level e.g by the floors of a building.
Jumpform can be very productive, fast and efficient yet minimise the labour required and craneage costs. There are three main type of jumpform:
- Normal – involves formwork that is lifted off by crane and reattached at the next level above.
- Guided – similar to the normal method above but units remain anchored to the structure during the raising operation by crane. This method can be safer and more controlled.
- Self-climbing – this type of jumpform is raised on rails and so does not require a crane.
There could also be trailing platforms and screens that can be used to help workers apply any required finishing to the concrete or retrieve anchors used on the pour below.
Jumpform systems are highly engineered and so can be quickly and accurately adjusted in all planes. However, they depend on the availability of a skilled workforce on site.
[edit] Slipform
Slipform is a continuous pour system involving a self-climbing formwork that supports itself on the core or shaft being constructed, moving slowly over the concrete as it is cast in a continuous, monolithic pour. It can be used to achieve tapered structures with walls of diminishing thickness and is regarded as being more economical when used for structures over seven storeys high.
Slipform typically has three platforms – a lower platform for concrete finishing; a middle platform at the top level of the concrete being poured, and an upper platform for storing materials.
Normally advancing at a rate of around 300mm per hour, slipform can be regarded as a method of vertical extrusion. This can result in a smooth, continuous concrete finish without any joints, an effect which may be required where the finished structure will be visible e.g bridge pylons or a chimneys. However, slipform may entail higher costs due to the required round-the-clock working until the necessary height of structure has been achieved. Like jumpform, it also requires the availability on site of a small, highly-skilled workforce.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Introducing or next Guest Editor Arun Baybars
Practising architect and design panel review member.
Quick summary by size, shape, test, material, use or bonding.
Types of rapidly renewable content
From forestry to agricultural crops and their by-products.
Terraced houses and the public realm
The discernible difference between the public realm of detached housing and of terraced housing.
Put digitalisation and sustainability at the core of curricula
Project management educators are urged.
Looking back at the influence of climate events
From a designer and writer: 'There are limits to growth but no limits to development'.
Terms, histories, theories and practice.
Biophilic design and natural light
Letting in the light and natural elements into spaces.
APM Programme Management Conference 2024
Strategies for Success.
Residential takes the reins as contract awards even out
Contracts down, but remain above the last quarter of 2023.
Celebrating Eid and the largest mud-brick building.
Barry Kingscote claims prestigious CIOB CMYA Award.
The British Mosque: an architectural and social history
The story of some 1,500 mosques or more in Britain.
Heat pump refrigerants, efficiencies and impacts
R12 to R1270 what are the differences?
Global heat pump market in 2023
Challenging times with positive but modest outlook.
Beyond the infrastructure pipeline
Opportunities and chokepoints.