Contract articles index
- ACA (Association of Consultant Architects)
- Addendum.
- Adjudication in construction contracts
- Agreement.
- Alternative dispute resolution for construction ADR
- Appointing consultants for building design and construction
- Approximate quantities cost plan
- Arbitration in the construction industry
- Base date in construction contracts
- Bespoke construction contract.
- Bill of quantities BOQ
- Budget for building design and construction projects
- Certificate of making good defects
- Collaborative practices for building design and construction
- Collateral warranties for building design and construction
- Concession Contracts Regulations.
- Construction contractor.
- Consultant agreements.
- Contract documents for construction.
- Contractual chain.
- Contractual obligation.
- Contractual right.
- Construction contract
- Construction contract conditions
- Construction manager
- Construction Management Contract
- Contract administrator for construction contracts
- Client's representative
- Core clause.
- Design agreements between an employer and a specialist designer.
- Design and Build Contract
- Earned value for construction contracts
- Estoppel contracts
- Extension of time EOT in construction contracts
- FIDIC.
- Final certificate for construction contracts
- Fluctuations in construction contracts
- Forms of tender for main contractors, sub-contractors and sub-sub-contractors.
- Forms of contract for the supply of goods.
- Forms of bond.
- Forward contract.
- Hybrid construction contract.
- Intermediate building contract
- Integrated supply team
- Interim certificates in construction contracts
- Invitation to tender for construction contracts
- JCT-CE Contract
- JCT (The Joint Contracts Tribunal)
- Job order contracting.
- Liquidated damages in construction contracts
- Major Project Construction Contract.
- Management Building Contract
- Measured Term Contract
- Memorandum of understanding.
- Minor Works Building Contract
- Model Services Contract MSC.
- Modifying clauses in standard forms of construction contract.
- Named supplier in construction contracts
- NEC.
- Onerous contract.
- PPC 2000.
- Pre-qualification questionnaire PQQ for construction contracts
- Pre-tender estimate for contracts
- Prolongation in construction contracts
- Sectional completion in construction contracts
- Set off in construction contracts
- Tender sum for construction contracts
- Tender report for construction contracts
- Set off in construction contracts
- Sectional completion in construction contracts
- Standard Building Contract
- Sub-contracts.
- Sub-sub-contracts.
- Reserved contract.
- Retention in construction contracts
- Pre-qualification questionnaire PQQ for construction contracts
- Pre-tender estimate for contracts
- Prime Cost Building Contract
- Repair & Maintenance Contract
- Tender documentation for construction projects.
- Traditional contract for construction.
- What is an EPC contract?
Featured articles and news
Ministers to unleash biggest building boom in half a century
50 major infrastructure projects, 5 billion for housing and 1.5 million homes.
RIBA Principal Designer Practice Note published
With key descriptions, best practice examples and FAQs, with supporting template resources.
Electrical businesses brace for project delays in 2025
BEB survey reveals over half worried about impact of delays.
Accelerating the remediation of buildings with unsafe cladding in England
The government publishes its Remediation Acceleration Plan.
Airtightness in raised access plenum floors
New testing guidance from BSRIA out now.
Picking up the hard hat on site or not
Common factors preventing workers using head protection and how to solve them.
Building trust with customers through endorsed trades
Commitment to quality demonstrated through government endorsed scheme.
New guidance for preparing structural submissions for Gateways 2 and 3
Published by the The Institution of Structural Engineers.
CIOB launches global mental health survey
To address the silent mental health crisis in construction.
New categories in sustainability, health and safety, and emerging talent.
Key takeaways from the BSRIA Briefing 2024
Not just waiting for Net Zero, but driving it.
The ISO answer to what is a digital twin
Talking about digital twins in a more consistent manner.
Top tips and risks to look out for.
New Code of Practice for fire and escape door hardware
Published by GAI and DHF.
Retrofit of Buildings, a CIOB Technical Publication
Pertinent technical issues, retrofit measures and the roles involved.
New alliance will tackle skills shortage in greater Manchester
The pioneering Electrotechnical Training and Careers Alliance.