Bespoke construction contract
Most construction projects are procured using a standard form of contract that includes standardised, non-negotiated provisions, usually in pre-printed, or digital form. These are sometimes referred to as boilerplate contracts, contracts of adhesion, or take it or leave it contracts.
In the construction industry, there are a number of standard contracts, subcontracts, warranties and appointment agreements published by organisations such as the Joint Contracts Tribunal (JCT), the Royal Institute of British Architects (RIBA), the Institution of Civil Engineers and so on. Such agreements can be effective as they have a track record of being used between parties, and their precise meaning has been tested by case law. Standard form contracts are very often cheaper than bespoke alternatives, familiar to the parties involved (reducing tendering, negotiation and administration costs), and tend to contain fewer unforeseen anomalies.
They can also allow some flexibility, with a wide range of variations, options and schedules that can be tailored to meet the needs of a specific project without altering the construction of the contract clauses.
For more information see: Standard form of contract.
Where this does not give sufficient flexibility, it is possible to amend standard forms of contract. However, this is not always recommended, as there is a complex interaction between many of the terms of standard forms, and modification can change the balance of risk and create legal uncertainty.
For more information see: Modifying clauses in standard forms of construction contract.
Bespoke contracts are specially drafted to suit the specific requirements of a particular project. On some projects, in particular the more complex ones, creating a bespoke contract may be seen as the most efficient means of agreeing terms. Bespoke contracts are also commonly used for very simple supply agreements, where the standard forms may be considered unnecessarily complex and inflexible.
The seminal Latham Report advised against the use of bespoke contracts, but despite this, 24% of respondents to the National Construction Contracts and Law Survey 2012 indicated that they choose to use purpose-written bespoke contracts.
Bespoke contracts may not adequately or fairly make provision for all circumstances, and they are not supported by a history of case law. A large number of legal issues have been created by non-standard bespoke contracts, and they are often costly and time consuming to draft, and disputes can be costly and time consuming to resolve in court.
Bespoke clauses can unintentionally make the meaning of contracts ambiguous, and this can be seized upon by parties in dispute, or seeking additional time or payment. On large projects, there can also be extensive schedules, specifications and other contract documents which may also contain conflicting or ambiguous provisions.
For these and other reasons, contractors tend to be wary of bespoke contracts, with the perception that most clients’ create bespoke contracts to transfer risk.
However, the contractor have little choice but to accept the client’s bespoke contract if they want the work. The commercial judgment should consider:
- How much they want the job in question (perhaps they see it as being a high-profile project that will reap benefits in terms of publicity and future business opportunities).
- How much they are prepared to do for the client in question (perhaps if they have a good working history with the client, or hope that they will offer them more work in the future).
- What the potential risks and costs are.
- How much they can charge to do the job and whether this makes it worth taking on the contractual risks.
Since the contract will govern the relationship between the parties, it is important that it is carefully reviewed and all legal issues considered. This may require seeking legal advice.
English law does not require a particular form to contracts, and so the terms and ultimately the risk allocation is the choice of the parties involved. However, the Housing Grants, Construction and Regeneration Act applies to all contracts for 'construction operations' setting out requirements relating to payment and adjudication. The Scheme for Construction Contracts (England and Wales) Regulations applies when construction contracts do not comply with the Act
[edit] Related articles on Designing Buildings
- Boilerplate
- Breach of contract.
- Causes of construction disputes.
- Construction contract.
- Contract documents.
- Contract negotiation.
- Design and build.
- Essentials of a contract.
- JCT.
- Latham report.
- Levelling the playing field
- Modifying clauses in standard forms of contract.
- Preliminary contracts.
- Procurement route.
- Standard form of contract.
Featured articles and news
Industry Competence Steering Group restructure
ICSG transitions to the Industry Competence Committee (ICC) under the Building Safety Regulator (BSR).
Principal Contractor Competency Certification Scheme
CIOB PCCCS competence framework for Principal Contractors.
The CIAT Principal Designer register
Issues explained via a series of FAQs.
Conservation in the age of the fourth (digital) industrial revolution.
Shaping the future of heritage
Embracing the evolution of economic thinking.
Ministers to unleash biggest building boom in half a century
50 major infrastructure projects, 5 billion for housing and 1.5 million homes.
RIBA Principal Designer Practice Note published
With key descriptions, best practice examples and FAQs, with supporting template resources.
Electrical businesses brace for project delays in 2025
BEB survey reveals over half worried about impact of delays.
Accelerating the remediation of buildings with unsafe cladding in England
The government publishes its Remediation Acceleration Plan.
Airtightness in raised access plenum floors
New testing guidance from BSRIA out now.
Picking up the hard hat on site or not
Common factors preventing workers using head protection and how to solve them.
Building trust with customers through endorsed trades
Commitment to quality demonstrated through government endorsed scheme.
New guidance for preparing structural submissions for Gateways 2 and 3
Published by the The Institution of Structural Engineers.
CIOB launches global mental health survey
To address the silent mental health crisis in construction.
New categories in sustainability, health and safety, and emerging talent.
Key takeaways from the BSRIA Briefing 2024
Not just waiting for Net Zero, but driving it.
Comments