Base date in construction contracts
A 'base date' is a reference date from which changes in conditions can be assessed.
The base date in construction contracts is generally used as a mechanism for the allocation of risk between the client and contractor for changes that might occur in the period between the contractor pricing the tender and the signing of the contract. This period can be very long and changes that occur may have a significant impact on the costs of the works.
The base date sets the reference date from which the conditions under which the tender was prepared are considered to have been known by the contractor and so are properly reflected in their price. If specified conditions change before the contract is implemented, then the contract may be adjusted to reflect this.
On very small projects, where the time frame is short, this may not be considered necessary. On larger projects, the base date can be used to allow changes to the contract sum, or sometimes extensions of time, or even to determine which rules will apply to the contract (for example which edition of arbitration rules).
The exact provisions will depend on the specific form of contract that is adopted. For example, in the Joint Contracts Tribunal (JCT) Design and Build Contract, the base date determines the allocation of risk in relation to changes in statutory regulations, changes to VAT exemptions and changes to definitions of dayworks.
Traditionally the base date was set as the date of tender, however this was sometimes found to give rise to uncertainty because of the complexity and duration of tendering procedures. The usual practice now is to insert a date in the contract linked to the date of the return of tenders.
The FIDIC suite of standard conditions of contract (the Red Book and Yellow Book), set the base date at 28 days before the latest date for the submission of tender. The JCT Design and Build Contract suggests a date that is 10 days prior to the date of the return of tenders.
NB: According to NRM1: Order of cost estimating and cost planning for capital building work, the term ‘base date of cost data’ means; ‘...the date on which rates and prices contained within cost analyses or benchmark analyses are taken as a basis for calculations.’
And the term 'estimate base date' means '...the date on which the cost limit (excluding inflation – i.e. the sum of the works cost estimate, project/design team fees estimate, other development/project costs estimate and risk allowance estimate) is established as a basis for calculating inflation, changes or other related variances.'
NB: Fluctuation clauses are a way of dealing with inflation on large projects that may last for several years. The contractor may be asked to tender based on current prices and then the contract makes provisions for them to be reimbursed for price changes over the duration of the project (a fluctuating price). This may be done by setting a base date for specified items and defining the price indices by which fluctuations will be assessed.
Fluctuation may allow for; changes in taxation; changes in the cost of labour, transport and materials; and even changes in head office or administrative costs.
NB: NRM3 Order of cost estimating and cost planning for building maintenance works, defines the 'estimate base date' as '...the date on which the cost limit (i.e. the sum of the works cost estimate, project/design team fees estimate, other related costs estimate and risk allowance estimate, excluding inflation) is established as the basis for calculating inflation, changes or other related variances.'
ICMS: Global Consistency in Presenting Construction Life Cycle Costs and Carbon Emissions, 3rd edition, November 2021, published by the ICMS (International Cost Management Standard) Coalition, defines the base date as: ‘The date at which the individual Construction Costs in ICMS cost reports apply exclusive of Price Level Adjustments after that date. However, there can be a separate allowance for Price Level Adjustments under the Risk Allowances Group. A different date (the Common Date) applies to Life Cycle Costs.’
[edit] Related articles on Designing Buildings
Featured articles and news
Specifying XPS in masonry cavity walls below DPC level
Moisture requirements, DPCs and third party certification.
Types of rigid foam insulation
A brief description and some of the main construction types.
Metal composite material panel systems MCM and MCP
Sandwich finishes, forms, details, core and their impacts.
Cumbria's vernacular architecture
A history of building impeded by unsettled times.
CIOB and MMC Ireland announce strategic partnership
For better working conditions, and a more productive construction sector.
More than just glass.
Grenfell Phase 2 final report for construction, at a glance
Twenty-three key issues raised and their recommendations.
Industry responds to the final Grenfell inquiry phase 2 report
Construction body responses to the long-awaited 7 volumes.
Chief construction advisers in brief
From July 2008 to November 2015.
The Grenfell phase 2 final report key summary points
And recommendations for the construction industry.
Approved Document B: Fire Safety upcoming updates
Including sprinklers in care homes, National classes and Fire resistance.
CIOB Podcast: 21st Century Construction
Catch up on the many previous episodes.
Tools and processes supporting a robust golden thread
BSRIA Handover Information and O&M Manuals guidance.
Industry survey highlights persistent skills gap
Building engineering business survey by ECA in partnership with BESA, SELECT and SNIPEF.
IHBC Conservation Professional Practice Principles
Spotlighted in HEF Historic Environment Overview.
CIAT collaborates with CIOB, CIfA, Icon to launch The Arc
Helping clients find specialist historic environment professionals.
Government building safety remediation data releases
Show some progress, but a 50% gap not yet started.
Testing For A Safer Future; an initial industry response
A response to the Independent Review of the Construction Product Testing Regime.
Requirements for UK buildings in certain circumstances.
Comments
[edit] To make a comment about this article, or to suggest changes, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.