Trade contractor
On construction management contracts, a construction manager is appointed on a consultancy and management basis to provide advice to the client during the pre-construction stages and then to manage the construction of the works. The works are divided into packages which are contracted to separate contractors. These contractors are referred to as trade contractors rather than sub-contractors (as they are contracted directly by the client, rather than being sub-contracted to the construction manager). The separate appointment of trade contractors should reduce the cost of contracts, as the management element is being provided by the construction manager. It also allows the advancement of some works (such as groundworks or piling) which might begin even before design of the above-ground works is complete.
Characteristics of trade contracts include:
- Trade contractors may be appointed through a single-stage procurement process, or through a two-stage process with a pre-construction services agreement for the first stage.
- Each trade contract must have its own separate practical completion certification and so they may have different defects liability periods. Certification cannot be dependent on completion of works outside of the scope of the contract. As trade contracts may be completed at different times, the construction manager must ensure that measures are in place to protect completed work from ongoing activities.
- Trade contracts (such as the Joint Contracts Tribunal (JCT) CM/TC 2011) do not include provisions for liquidated damages, instead the trade contractor indemnifies the client's direct loss and/or expense for lateness.
- Trade contracts may allow for retention, or may include a requirement for a retention bond.
- Trade contracts should include requirements to adopt collaborative practices.
- As there is no main contractor, trade contractors should provide master programmes for their works.
- Trade contractors should be required to provide regular information in relation to key performance indicators.
- Where they carry out design, trade contractors may be required to provide as-built drawings.
Notes
- On management contracts, contractors are known as 'works contractors'.
- For a detailed description of the sequence of tasks necessary on a construction management contract, see the work plan: construction management: outline work plan.
NB A trades contractor (with an 's') is a more general term which simply refers to a contractor who undertakes a particular class of construction work, such electrical installation. See Trades contractor for more information.
[edit] Related articles on Designing Buildings
- Back-to-back provisions in construction contacts.
- Collaborative practices.
- Collateral warranties.
- Construction manager.
- Construction contract.
- Contracting.
- Contractor.
- Contractors master programme.
- Main contractor.
- Management contract.
- Operative.
- Procurement route.
- Sub-agent.
- Sub-contractor.
- Trade body.
- Types of contractor.
- Works contractor.
Featured articles and news
Guidance notes to prepare for April ERA changes
From the Electrical Contractors' Association Employee Relations team.
Significant changes to be seen from the new ERA in 2026 and 2027, starting on 6 April 2026.
First aid in the modern workplace with St John Ambulance.
Ireland's National Residential Retrofit Plan
Staged initiatives introduced step by step.
Solar panels, pitched roofs and risk of fire spread
60% increase in solar panel fires prompts tests and installation warnings.
Modernising heat networks with Heat interface unit
Why HIUs hold the key to efficiency upgrades.
Reflecting on the work of the CIOB Academy
Looking back on 2025 and where it's going next.
Procurement in construction: Knowledge hub
Brief, overview, key articles and over 1000 more covering procurement.
Sir John Betjeman’s love of Victorian church architecture.
Exchange for Change for UK deposit return scheme
The UK Deposit Management Organisation established to deliver Deposit Return Scheme unveils trading name.
A guide to integrating heat pumps
As the Future Homes Standard approaches Future Homes Hub publishes hints and tips for Architects and Architectural Technologists.
BSR as a standalone body; statements, key roles, context
Statements from key figures in key and changing roles.
ECA launches Welsh Election Manifesto
ECA calls on political parties at 100 day milestone to the Senedd elections.
Resident engagement as the key to successful retrofits
Retrofit is about people, not just buildings, from early starts to beyond handover.
Plastic, recycling and its symbol
Student competition winning, M.C.Esher inspired Möbius strip design symbolising continuity within a finite entity.
Do you take the lead in a circular construction economy?
Help us develop and expand this wiki as a resource for academia and industry alike.
Warm Homes Plan Workforce Taskforce
Risks of undermining UK’s energy transition due to lack of electrotechnical industry representation, says ECA.
Cost Optimal Domestic Electrification CODE
Modelling retrofits only on costs that directly impact the consumer: upfront cost of equipment, energy costs and maintenance costs.
























Comments
To start a discussion about this article, click 'Add a comment' above and add your thoughts to this discussion page.